Gary Lorenzon Contractors Inc. v. Allstates Mechanical Ltd.

52 Pa. D. & C.4th 567, 2001 Pa. Dist. & Cnty. Dec. LEXIS 432
CourtPennsylvania Court of Common Pleas, Philadelphia County
DecidedMay 10, 2001
Docketno. 1224
StatusPublished

This text of 52 Pa. D. & C.4th 567 (Gary Lorenzon Contractors Inc. v. Allstates Mechanical Ltd.) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Philadelphia County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gary Lorenzon Contractors Inc. v. Allstates Mechanical Ltd., 52 Pa. D. & C.4th 567, 2001 Pa. Dist. & Cnty. Dec. LEXIS 432 (Pa. Super. Ct. 2001).

Opinion

SHEPPARD JR., J.,

Defendants, Allstates Mechanical Ltd. and Fidelity Deposit Company of Maryland, have filed preliminary objections to the complaint of plaintiff, Gary Lorenzon Contractors Inc. For the reasons set forth, the court is entering a contemporaneous order overruling the objections.

BACKGROUND

In March 2000, John Walters, then an estimator for Allstates, contacted Lorenzon about bidding for a construction project for the School District of Philadelphia. On April 7,2000, Lorenzon submitted a bid proposal to perform certain demolition, roofing and structural steel work in connection with the project. Three days later, Allstates entered into a contract with the district to act as general contractor for the project. In connection with the contract, Allstates executed and delivered to the district [569]*569a labor and material payment bond, with Fidelity as surety.

Allstates mailed Lorenzon a proposed subcontract agreement on April 27, 2000 with a proposed cost of $69,000. The subcontract included a forum selection clause requiring that “any and all actions brought by any party... in connection with this agreement” be brought in the Court of Common Pleas of Delaware County “where venue shall be and is hereby established.” (Forum selection clause.) Complaint exhibit B, ¶2. Lorenzon responded on May 4, 2000 by seeking clarification of certain terms in the subcontract, including the required use of American steel and the exclusion of work on a thermal plant penthouse unit from the subcontract’s scope. In spite of the parties’ failure to execute the subcontract, Norman Long, Allstates’ manager for the project, subsequently directed Lorenzon to proceed with its portion of the project. Believing that its interpretation of the subcontract had been accepted, Lorenzon commenced work on the project.

In July 2000, Long left Allstates and was replaced as project manager by Walters. Shortly before August 3, 2000, Walters requested that Lorenzon submit a proposal to provide labor and material for the installation of the structural steel for the thermal plant. On September 18, 2000, Lorenzon submitted a proposal to provide labor only at a cost of $44,000. Lorenzon contends that Walters orally agreed to the thermal plant proposal by instructing Lorenzon to start immediately and assured Lorenzon that Allstates would provide a $44,000 purchase order for this additional work.

Lorenzon asserts that it completed the thermal plant work on September 27, 2000 and submitted an invoice [570]*570to Allstates for $44,000. Sometime during that week Walters contacted Lorenzon, stating that a mistake in the thermal plant’s steel configuration design required construction modification. Walters allegedly acknowledged that the mistake was not caused by Lorenzon and requested that Lorenzon make the modifications as soon as possible, with a purchase order for the additional steel to be provided by Allstates. According to the complaint, Lorenzon incurred additional expenses of $107,918.33 in materials and labor costs between September 28 and October 25, 2000 in completing the modifications.

Up through October 9,2000, Lorenzon had been paid only $30,071 for its labor and services. On that day, Gary Lorenzon, a principal of Lorenzon, met with Walters and Anthony Maraño, president of Allstates, to discuss how Allstates would pay for the modifications. According to Lorenzon, Allstates agreed to pay for the modifications on a time and material basis, and Maraño reaffirmed that the subcontract did not include work on the thermal plant.

On October 10, 2000, Lorenzon requested payment from Allstates beyond that already made, and, when Allstates agreed, Gary drove to Allstates’ office to pick up a check. Upon his arrival, he was told that Allstates would not pay Lorenzon unless he signed the subcontract. Reluctantly, Gary agreed and signed what he believed to be a copy of the subcontract.1 The next day, Lorenzon’s counsel wrote to Walters to confirm that the clarifications of Lorenzon’s May 4 letter had been incor[571]*571porated into the subcontract. Walters responded that this was so.

Lorenzon alleges that Allstates still owes it $203,557.87 and has not made any payments for the modifications. In addition, Allstates allegedly has retained Lorenzon property with a value of $7,000. On this basis, Lorenzon has asserted claims for breach of the oral agreement for the construction of the thermal plant, unjust enrichment, violations of the Pennsylvania Contractor and Subcontractor Payment Act,2 replevin and breach of suretyship agreement.3

DISCUSSION

Defendants argue that the forum selection clause requires that this action be brought in Delaware County4 and that 12 paragraphs in the complaint include more than one material allegation, in violation of Pa.R.C.P. 1022.5 This court submits that the objections are without merit.

I. The Forum Selection Clause Does Not Render Venue in Philadelphia Improper

When preliminary objections challenge venue, “the defendant is the moving party and bears the burden of [572]*572supporting [its] claim” of improper venue. Liggitt v. Liggitt, 253 Pa. Super. 126, 131, 384 A.2d 1261, 1263-64 (1978). See also, Gale v. Mercy Catholic Medical Center Eastwick Inc., Fitzgerald Mercy Division, 698 A.2d 647, 652 (Pa. Super. 1997) (the moving party has the burden of showing that the original choice of venue is improper). Consequently, to prevail, the defendants must show that Philadelphia constitutes improper venue.

Pennsylvania law holds that, where a forum selection clause purports to make an otherwise proper venue improper, “it would be contrary to public policy to allow an agreement made in advance of the dispute to oust said tribunal’s jurisdiction.” Central Contracting Co. v. C.E. Youngdahl & Co., 418 Pa. 122, 132-33, 209 A.2d 810, 815-16 (1965) (citing Rea’s Appeal, 13 W.N.C. 546 (1883)). See also, Healy v. Eastern Bldg. & Loan Ass ’n, 17 Pa. Super. 385, 392 (1901) (an agreement to sue only in New York does not prevent plaintiff from bringing action in a Pennsylvania court). However, this does not mean that an agreement limiting the forum for future dispute resolution is per se invalid:

“The modem and correct mle is that while private parties may not by contract prevent a court from asserting its jurisdiction or change the rales of venue, nevertheless, a court in which venue is proper and which has jurisdiction should decline to proceed with the cause when the parties have freely agreed that litigation shall be conducted in another forum and where such agreement is not unreasonable at the time of litigation. ” Central Contracting, 418 Pa. at 133, 209 A.2d at 816. (emphasis added) See also, Morgan Trailer Mfg. Co. v. Hydraroll Ltd., 759 A.2d 926 (Pa. Super. 2000) (using the test laid out in Central Contracting

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Liggitt v. Liggitt
384 A.2d 1261 (Superior Court of Pennsylvania, 1978)
Morgan Trailer Mfg. Co. v. Hydraroll, Ltd.
759 A.2d 926 (Superior Court of Pennsylvania, 2000)
Churchill Corp. v. Third Century, Inc.
578 A.2d 532 (Supreme Court of Pennsylvania, 1990)
Williams v. Gruntal & Co.
669 A.2d 387 (Superior Court of Pennsylvania, 1995)
Gale v. Mercy Catholic Medical Center Eastwick, Inc.
698 A.2d 647 (Superior Court of Pennsylvania, 1997)
Central Contracting Co. v. C. E. Youngdahl & Co.
209 A.2d 810 (Supreme Court of Pennsylvania, 1965)
Healy v. Eastern Building & Loan Ass'n
17 Pa. Super. 385 (Superior Court of Pennsylvania, 1901)
General State Authority v. Sutter Corp.
356 A.2d 377 (Commonwealth Court of Pennsylvania, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
52 Pa. D. & C.4th 567, 2001 Pa. Dist. & Cnty. Dec. LEXIS 432, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gary-lorenzon-contractors-inc-v-allstates-mechanical-ltd-pactcomplphilad-2001.