Gary Jones and Carolyn Jones v. Pesak Brothers Construction, Inc.

416 S.W.3d 618, 2013 WL 4824453, 2013 Tex. App. LEXIS 11503
CourtCourt of Appeals of Texas
DecidedSeptember 10, 2013
Docket01-12-00535-CV
StatusPublished
Cited by12 cases

This text of 416 S.W.3d 618 (Gary Jones and Carolyn Jones v. Pesak Brothers Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gary Jones and Carolyn Jones v. Pesak Brothers Construction, Inc., 416 S.W.3d 618, 2013 WL 4824453, 2013 Tex. App. LEXIS 11503 (Tex. Ct. App. 2013).

Opinion

OPINION

JANE BLAND, Justice.

When their newly-constructed house showed signs of foundation distress, Gary and Carolyn Jones sued their builder, Pe-sak Brothers Construction Company (Pe-sak Brothers), for breach of a construction contract, express and implied warranties, negligent construction of the home, and for violations of the Texas Deceptive Trade *621 Practices Act. After a jury trial on the Joneses’ claims, the trial court entered a take-nothing judgment, in accordance with the jury’s verdict.

On appeal, the Joneses challenge the legal and factual sufficiency of the evidence supporting the jury’s findings. They also contend that the trial court erred in refusing to submit their negligence claim to the jury and by striking their sixth amended petition, and they raise challenges to certain of the trial court’s evidentiary rulings. We hold that sufficient evidence supports the jury’s verdict, and the trial court did not err in deciding the other challenged rulings. We therefore affirm.

Background

In 2006, the Joneses hired Pesak Brothers to build a house for them on the Joneses’ seventy-eight-acre property near Columbus, Texas. Pesak Brothers referred the Joneses to Steven Kieschnick, of Kieschnick’s Designs in Wood, to select a floor plan from several blueprints that he had available. After selecting a plan, the Joneses returned to Pesak Brothers and signed a two-page construction agreement. The agreement specifies the square footage of the living area, garages, and porches, as well as the materials' that Pesak Brothers would use in constructing the home. It itemizes the specifications for the foundation, framing, roofing, electrical wiring, insulation, exterior finish, painting, plumbing, floors, doors, windows, interiors, gas outlets, and air conditioning and heating. Pesak Brothers bid $310,000 for the total construction cost, but the agreement explains that the Pesak Brothers would calculate the amount due based “on a cost plus 10% for operating expenses and liability insurance.” The agreement does not address grading of the land surrounding the construction site.

Kieschnick provided a list entitled “Specifications for the home of Mr. & Mrs. Gary Jones.” The list identifies Kieschnick as a “draftsman and craftsman,” and it reiterates and elaborates on the construction tasks and items identified in the Pesak agreement. Pertinent to this appeal, the list recites that “[gjeneral notes, all materials and workmanship should meet or exceed local building code and also the Universal Building Code Book. Any changes made should be cleared with the homeowner.” Among other things, Kieschnick’s list specifies: “Excavation — virgin soil”; “Gutters and Downspouts — none”; and “Landscaping— by owner.” Kieschnick’s list is otherwise silent with respect to the diversion of water outside the home or the grading or other improvements to the land. Kiesch-nick’s list is unsigned, and neither the Pesak agreement nor Kieschnick’s list refers to or acknowledges the existence of the other.

Before Pesak Brothers completed its construction, Robert Pesak and Mr. Jones discussed who would take responsibility for completing the grading near the house and hardscaping on the lot. Pesak asked Mr. Jones “if he wanted [Pesak Brothers] to do the grading and he said no, that he was going to.” Mr. Jones owned three pieces of earth-moving equipment — a tractor, a front-end loader, and an excavator. He had gained experience using them to clear over 200 fallen trees on his Louisiana property following Hurricane Katrina, and he enjoyed moving soil around on his property with them. Mr. Jones told Pesak that he would contract directly with Sanchez Construction to install the concrete driveway, patio, and sidewalks surrounding the house. Mr. Jones acknowledged that, by contracting with Sanchez directly for the hardscaping, the Joneses avoided the “cost plus ten percent” that Pesak Brothers *622 would have charged under the construction agreement, and that the Joneses also saved money by choosing to grade the property themselves.

Pesak Brothers completed construction, and the Joneses closed on the house in December 2006. Pesak presented the Joneses with a final invoice in the amount of $334,839.96. Pesak explained that the amount due exceeded the estimate contained in the agreement because of additional items not accounted for in the original estimate that Pesak Brothers provided, at the Joneses’ request, during construction. Mr. Jones protested that final amount and insisted that he had agreed to pay no more than $300,000 for the house. Mr. Jones told the jury that he suspected that Pesak Brothers had added the “cost plus ten percent” provision after the Joneses signed the agreement. The parties negotiated the claimed overage. Pe-sak Brothers ultimately agreed with the Joneses to split the difference in the claimed overage amount and accepted $20,000 in exchange for signing the certificate of completion. In the certificate, the parties averred:

1. Improvements Debts or Liens. Except as indicated below, Contractor states that there are no unpaid debts and OWNER states that he has not received any notices from any contractors or subcontractors with respect to the Project or with respect to any of the following items which may be remaining on the Property: Mirror, shutters on the front of house, Home Warranty Policy, concrete steps and bonus room as per plans and specifications dated as of March 22, 2006
3. Certificate of Completion. The project has been completed in a good and workman-like manner and in accordance with the plans and specifications approved by the Owner. The Contractor has duly paid all bills and invoices for any labor and/or materials furnished in connection with the Project and has not received notices of any claim of mechanic’s or materialman’s liens against the property. The OWNER has fully accepted the completed Project and has not received notices of any kind of any claim of mechanic’s or materialman’s liens against the property.

The evidence is uncontested that, other than the typical grading that builders perform in the course of constructing the home, neither Pesak Brothers nor its subcontractors graded the site before the parties executed the certificate of completion.

In January 2007, around the same time that the Joneses moved into the house, Sanchez added a sidewalk on the north side of the house, a driveway on the east side, and a patio on the south side. Mr. Jones used his front-end loader to contour the land around the house. Mr. Jones also attempted to divert water from the house’s foundation by cutting three terraces on the west side, and he built a stone wall uphill from the house. He conceded that he did not know any particular grading requirements, such as the degree of slope, to use.

In February, Mr. Jones called Pesak to report that he had found cracks in the exterior mortar. Pesak told Mr. Jones to add soil around the foundation. Eventually, cracks appeared in the inside walls, and windows and doors began to stick. According to Pesak, Mr. Jones’s failure to grade the foundation soon after Pesak Brothers completed construction caused this damage. Pesak also testified that the placement of the sidewalks, patio, and driveway prevented adequate grading around the home. He explained that the *623

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Amazing Paws v. Melissa Pedraza
Tex. App. Ct., 1st Dist. (Houston), 2026
Ramachandran v. Jain
N.D. Texas, 2022
Elizabeth Magro v. Alejandro Magro Junior
Court of Appeals of Texas, 2020
in Re M.F.D.
Court of Appeals of Texas, 2016
Richardson v. Wal-Mart Stores Texas, LLC
192 F. Supp. 3d 719 (S.D. Texas, 2016)
Sandra Perez v. Brian Williams
474 S.W.3d 408 (Court of Appeals of Texas, 2015)
Pamela Lou Burden v. Steven Bradley Burden
420 S.W.3d 305 (Court of Appeals of Texas, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
416 S.W.3d 618, 2013 WL 4824453, 2013 Tex. App. LEXIS 11503, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gary-jones-and-carolyn-jones-v-pesak-brothers-construction-inc-texapp-2013.