Gary Cooper v. Clinton Utilities Board

CourtCourt of Appeals of Tennessee
DecidedJuly 23, 2010
DocketE2009-01734-COA-R3-CV
StatusPublished

This text of Gary Cooper v. Clinton Utilities Board (Gary Cooper v. Clinton Utilities Board) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gary Cooper v. Clinton Utilities Board, (Tenn. Ct. App. 2010).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE July 6, 2010 Session

GARY COOPER v. CLINTON UTILITIES BOARD

Appeal from the Circuit Court for Anderson County No. A7LA0655 Hon. Donald R. Elledge, Judge

No. E2009-01734-COA-R3-CV - FILED JULY 23, 2010

Plaintiff brought this action, charging defendant utility breached its contract with plaintiff to construct a line and deliver electricity to his property. Defendant filed a Motion for Summary Judgment and the Trial Judge held that there was no meeting of the minds between the parties and defendant was not obligated to construct a line to deliver electricity to plaintiff's dwelling. On appeal, we affirm.

Tenn. R. App. P.3 Appeal as of Right; Judgment of the Circuit Court Affirmed.

H ERSCHEL P ICKENS F RANKS, P.J., delivered the opinion of the Court, in which D. M ICHAEL S WINEY, J., and J OHN W. M CC LARTY, J., joined.

Robert W. White, Maryville, Tennessee, for the appellant, Gary Cooper.

Rebecca B. Murray and Catherine E. Shuck, Knoxville, Tennessee, for the appellee, Clinton Utilities Board.

OPINION

In this action plaintiff filed a detailed Complaint, in which he alleged in 2003 he decided to tear down an existing residence on his property and replace it with a manufactured home, and he contacted several officials from defendant and the county to discuss the placement of the home, and was advised that the electric power line would have to be relocated. He further alleged that he met with defendant's officials on the property and discussed the technical requirements and placement of the home. Plaintiff attached a memorandum of their agreement prepared by defendant. Plaintiff alleged that defendant agreed to relocate the power line in accordance with “option 2" as shown on the diagram which was attached. Further, that defendant agreed to split the cost of $1,600.00 equally with plaintiff, with plaintiff paying $800.00 up front.

Plaintiff further alleged that in reliance with their agreement, he demolished the existing residence and caused the manufactured home to be installed.

Plaintiff alleged that defendant never relocated the power line as it agreed to do, and as a result, Anderson County would not issue a certificate of occupancy for the new home, and the defendant refused to connect power to the home. Plaintiff concluded by alleging defendant breached the contract and sued to recover his damages.

Defendant answered and Counterclaimed, denying that it had an agreement with plaintiff, and that plaintiff rejected the proposals it provided in 2003 and 2004, and in its Counterclaim, asserted that it offered two proposals to plaintiff, through counsel, but plaintiff rejected both proposals. Defendant asked that plaintiff be required to remove his structure and be restrained from further encroaching on defendant's easement.

Defendant filed a Motion for Summary Judgment, saying there was never an agreement between the parties, and thus it was entitled to the summary judgment because plaintiff had illegally placed a structure on its easement. Defendant attached a letter from plaintiff's former counsel, dated May 26, 2004, which states that "proposal No. 2" seemed the most viable option, but plaintiff could not contribute to the cost of the same. The letter states that plaintiff would, however, perform the necessary clearing work of trees and shrubs. Another letter dated July 15, 2004, stated that "no agreement has been reached between these parties".

Defendant filed an Affidavit of Ernest Marvin Bowles, II., who stated that he was the Assistant General Manager and Director of Engineering and Operations for defendant, and that his duties included working with customers on requests for relocation of electrical lines. He stated that defendant's representative met with plaintiff on the property on three different occasions in 2002 and 2003 to discuss relocating the line, but plaintiff did not agree to any proposals offered. He stated that a bullet point memo was faxed to plaintiff after the July 29, 2003, meeting, which detailed an option with a cost of $1,600.00, and that plaintiff would contribute $800.00. He testified that plaintiff never responded to this proposal, but requested another meeting in March 2004. At the 2004 meeting they discussed the relocation of the

-2- line and he observed at that time that the original residence had been torn down and a concrete pad placed directly within the defendant's easement. He testified that he inspected the new pad, and determined that it encroached on the area where they had previously discussed relocating the line as shown on Exhibit 2, and that this was no longer feasible. He testified that subsequent to that meeting, defendant proposed a new plan based on plaintiff's placement of the manufactured home, but determined that none of plaintiff’s neighbors would agree to grant the necessary easements. He said that defendant informed plaintiff that he would have to get the necessary easements before they could proceed.

In his further testimony, Bowles said that they had heard nothing further from plaintiff until April 2004, when they were contacted by plaintiff’s attorney, and that defendant's counsel and other representatives met with plaintiff and his counsel on the property to discuss relocation of the line on May 20, 2004. Bowles stated that they presented two options for relocating the line, and that plaintiff thought option 1 was not viable, but that they reviewed the costs associated with option 2, and determined the cost would be $4,000.00 and plaintiff’s portion would be $2,000.00. The two options were attached to his deposition.

After this meeting, Bowles testified that several letters were then sent back and forth between the parties’ counsel, but the end result was that no agreement was ever reached.

Defendant then filed a Statement of Material Facts and a Memorandum of Law in support of its motion.

Plaintiff filed his own Affidavit in response, and stated that his initial meeting was with Mr. Bowles alone, and occurred in June or July 2003, that Mr. Bowles told him what defendant could do with regard to relocating the line, and drew a sketch attached as Exhibit 1. At the conclusion of their meeting, he said that Mr. Bowles told him he would “see to” relocating the line, and never mentioned that plaintiff would incur any cost.

Plaintiff stated that he later received information that he would be responsible for $800.00 for his part of the cost in moving the line, and he received the bullet point document that was attached to Bowles’ affidavit. Plaintiff stated that the document states that defendant would not begin line relocation until after plaintiff obtained a building permit and paid his part of the cost. Plaintiff stated that he had the home placed on the pad and then contacted the defendant to connect power, but his request was refused, and he stated that defendant then began putting forth other options for relocating the line.

Plaintiff stated that he met with Bowles in early 2004, and he was told the original plan would not work because they could not get agreement from another property owner for the placement of the necessary guy wires. Plaintiff stated that he was not given the

-3- opportunity to pay the $800.00, and was told the line relocation would not go forward in the manner agreed. Plaintiff stated that he asked defendant to either move the line in the manner originally agreed or to move it in accordance with Option 2, but explained that the cost of $2,000.00 would be very problematic for him. He stated he offered to pay $500.00 right then if they would do it for a total of $800.00 and Bowles refused to take the money.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hannan v. Alltel Publishing Co.
270 S.W.3d 1 (Tennessee Supreme Court, 2008)
Morton v. Morton
182 S.W.3d 821 (Court of Appeals of Tennessee, 2005)
Shedd v. Gaylord Entertainment Co.
118 S.W.3d 695 (Court of Appeals of Tennessee, 2003)
Byrd v. Hall
847 S.W.2d 208 (Tennessee Supreme Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Gary Cooper v. Clinton Utilities Board, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gary-cooper-v-clinton-utilities-board-tennctapp-2010.