Garvin, Secretary of the Delaware DNREC v. Booth

CourtSuperior Court of Delaware
DecidedJanuary 27, 2022
DocketS18M-10-040 JJC
StatusPublished

This text of Garvin, Secretary of the Delaware DNREC v. Booth (Garvin, Secretary of the Delaware DNREC v. Booth) is published on Counsel Stack Legal Research, covering Superior Court of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Garvin, Secretary of the Delaware DNREC v. Booth, (Del. Ct. App. 2022).

Opinion

IN THE SUPERIOR COURT OF THE STATE OF DELAWARE

SHAWN M. GARVIN, : SECRETARY OF THE : DELAWARE DEPARTMENT OF : NATURAL RESOURCES & : C.A. No. S18M-10-040 JJC ENVIRONMENTAL CONTROL, : : Plaintiff, : v. : : JOSEPH W. BOOTH, : MARGARET A. BOOTH, & : THORO-KLEEN, INC., : : Defendants. : :

OPINION & ORDER

Submitted: November 19, 2021 Decided: January 27, 2022

Upon Plaintiff’s Motion for Summary Judgment - GRANTED

Devera B. Scott, Deputy Attorney General, Department of Justice, Dover, Delaware, William J. Kassab, Deputy Attorney General, Department of Justice, New Castle, Delaware, and Kayli H. Spialter, Deputy Attorney General, Department of Justice, Wilmington, Delaware, Attorneys for the Plaintiff.

Christopher M. Coggins, Esquire, Coggins Law, LLC, Wilmington, Delaware, Attorney for the Defendants.

Clark, R. J. Plaintiff Shawn M. Garvin, as Secretary of the Delaware Department of Natural Resources and Environmental Control (hereinafter both the Secretary and the Agency are collectively referred to as “DNREC”) sues Defendants Joseph Booth, Margaret Booth, and Thoro-Kleen, Inc. (hereinafter collectively the “Booths”). In DNREC’s suit, it seeks reimbursement from the Booths for payments that it made to a brownfield developer’s contractor. Specifically, DNREC paid the contractor for the studies and planning necessary to address releases of perchloroethylene (“PCE”) and trichloroethylene (“TCE”) at the former Thoro-Kleen Dry Cleaning and Laundry site (the “Site”) in Georgetown. The Site is a certified brownfield and DNREC used funds from Delaware’s Hazardous Substance Cleanup Fund (the “Fund”) to pay the contractor.1 This decision addresses DNREC’s motion and the Booths’ cross-motion for summary judgment. DNREC contends that there are no material issues of fact regarding the Booths’ obligation to reimburse it for what it paid the contractor. In contrast, the Booths allege that DNREC identifies no recoverable damages because amounts paid to the contractor of a brownfield developer do not qualify as “remedial costs incurred” by DNREC. Rather, the Booths contend that DNREC’s payments to the contractor were nothing more than “public assistance.” Accordingly, the Booths argue that Delaware’s Hazardous Substances Cleanup Act (“HSCA” or the “Act”) does not permit DNREC to recover the costs. 2 For the reasons discussed below, brownfield funds that DNREC pays to a brownfield developer’s contractor are recoverable costs pursuant to one of HSCA’s recovery provisions, 7 Del. C. § 9109(e) (“Section 9109(e)”). Because DNREC’s payments are remedial costs incurred as contemplated by Section 9109(e), and

1 See 7 Del. C. § 9113 (creating the Hazardous Substance Cleanup Fund). 2 Id. §§ 9101-9126.

2 because there are no genuine issues of material fact regarding the amount DNREC seeks, the Court grants summary judgment in favor of DNREC.

I. FACTS OF RECORD AND PROCEDURAL HISTORY This decision resolves issues that followed an October 31, 2017 Order (the “Order”) issued by DNREC. The Order declared the Booths to be liable for environmental contamination at the Site. Because the procedural background is so important in this case, the Court will discuss it in some length. It is appropriate to do so because (1) the procedural history became so distorted and (2) the parties’ procedural choices that caused those disconnections dictate the results in this case. The consequences of the parties’ choices benefit DNREC, in part (by fixing the Booths’ liability), and the Booths, in part (by limiting the amount DNREC can recover). Accordingly, the Court explains this history in detail, not with the intent to be critical, but rather to explain how those choices dictate the result. After the Court discusses the history, it will highlight the facts in the summary judgment record that relate to the amount DNREC seeks.

A. Procedural and Other Basic Background Mr. and Mrs. Booth have owned the Site since September 2, 1986. When they acquired title to the real estate, they also acquired the dry-cleaning business that operated there. They ran the business until September 2010. After they ceased operations, DNREC sent the Booths a January 2014 notice of violation. In that notice, DNREC contended that the Booths were potentially responsible parties for the release of PCE and TCE into the Site’s soil and groundwater. In that notice of violation, DNREC suggested that the Booths participate in DNREC’s Voluntary Cleanup Program, but the Booths declined. After several years

3 of back and forth, Secretary Garvin and the Booths met to discuss the case in May 2017. At that meeting, the parties discussed the Booths’ claimed innocent landowner defense pursuant to 7 Del. C. § 9105(c). The Booths contended that they qualified as innocent landowners because the releases occurred before they assumed control of the Site and because they met other requirements for the defense. In response, the Secretary told them that the defense did not apply and that he would stand by his employees’ recommendations regarding their liability. Approximately six days later, a DNREC program manager, Timothy Ratsep, sent the Booths a written settlement demand seeking to resolve the matter.3 After the Booths met with Secretary Garvin and received the letter, they made their first unconventional procedural choice. Namely, they attempted to appeal both matters to the Environmental Appeals Board (hereinafter referred to as the “EAB” or “the Board”).4 Specifically, they attempted to appeal (1) the Secretary’s oral statement wherein the Secretary told the Booths that he considered them liable, and (2) Mr. Ratsep’s letter. While the parties began litigating that appeal before the Board, DNREC issued its first and only written order on the matter on October 31, 2017 (again, hereinafter the “Order”). DNREC maintained at that point, and this Court and the Delaware Supreme Court later agreed, that the Order constituted its final agency action regarding the matter.5 In the Order, DNREC rejected the Booths’ innocent landowner defense, and found them liable for the release of PCEs and TCEs at the Site.6 It also ordered the

3 See Appellant’s Reply Br., D.I. 13, at Ex. 48, Booth v. Garvin, 2019 WL 462486 (Del. Super. Feb. 6, 2019) (including Mr. Ratsep’s letter as an exhibit). 4 EAB Appeal No. 2017-08. 5 Booth v. Garvin, 2019 WL 462486 (Del. Super. Feb. 6, 2019) (finding that neither the Secretary’s oral statement nor the demand letter constituted final agency action and finding the Order to be the only appealable agency action), aff’d, 217 A.3d 700 (Del. 2019) (TABLE). 6 Def. Mot. Summ. J., Ex. 6.

4 Booths, inter alia, to hire a consultant and provide DNREC with a completed remedial investigation and feasibility study to address necessary remedial measures.7 Finally, the Order informed the Booths that they had the right to appeal that decision to the Board.8 It also separately recognized that the Booths had an existing hearing date in November 2017 for their first filed EAB appeal.9 The Booths then timely appealed the Order.10 At that point, DNREC urged them to consolidate their two EAB appeals so the Board could address the substantive matters in the case.11 In fact, consolidating the two appeals at that point would have provided the only practical solution to the problem that the Booths litigation choices had caused. The Booths nevertheless made another unusual procedural decision – they rejected the proposal.12 The Board then continued the hearing that had been scheduled for November 2017. Again, that first EAB hearing would have addressed only the Booths’ attempt to appeal the Secretary’s oral statement and the settlement demand.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brzoska v. Olson
668 A.2d 1355 (Supreme Court of Delaware, 1995)
Moore v. Sizemore
405 A.2d 679 (Supreme Court of Delaware, 1979)
Public Water Supply Co. v. DiPasquale
735 A.2d 378 (Supreme Court of Delaware, 1999)
Leatherbury v. Greenspun
939 A.2d 1284 (Supreme Court of Delaware, 2007)
Total Care Physicians, P.A. v. O'Hara
798 A.2d 1043 (Superior Court of Delaware, 2001)
Lynch v. Athey Products Corp.
505 A.2d 42 (Superior Court of Delaware, 1985)
Hurtt v. Goleburn
330 A.2d 134 (Supreme Court of Delaware, 1974)
BP Amoco Chemical Co. v. Sun Oil Co.
166 F. Supp. 2d 984 (D. Delaware, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
Garvin, Secretary of the Delaware DNREC v. Booth, Counsel Stack Legal Research, https://law.counselstack.com/opinion/garvin-secretary-of-the-delaware-dnrec-v-booth-delsuperct-2022.