Gardner, L. v. Bruder, L.

Superior Court of Pennsylvania·Decided July 10, 2015·No. 672 WDA 2014·Unpublished

Opinion

NON-PRECEDENTIAL DECISION - SEE SUPERIOR COURT I.O.P. 65.37

LISA GARDNER AND MARK MONAHAN, IN THE SUPERIOR COURT OF PENNSYLVANIA

Appellees

v.

LEE BRUDER, T/D/B/A BRUDER CONSTRUCTION CO.,

Appellant No. 672 WDA 2014

Appeal from the Judgment Entered March 31, 2014 In the Court of Common Pleas of Allegheny County Civil Division at No(s): AR-12-001706

BEFORE: BOWES, OLSON, and STRASSBURGER,* JJ. MEMORANDUM BY BOWES, J.: FILED JULY 10, 2015 Lee Bruder t/d/b/a/ Bruder Construction Co. appeals from the judgment entered on the non-jury verdict in favor of Lisa Gardner and her husband, Mark Monahan (collectively referred to as “Appellees”), in the amount of $21,655. We affirm in part, reverse in part, and remand with instructions.

On March 26, 2011, Appellees entered a written contract with Appellant to demolish an existing garage behind Appellees’ home in the Mexican War Streets neighborhood of Pittsburgh, Pennsylvania, and build a new two-car garage. Pursuant to the written accord, a form contract

published by the American Institute of Architects (“AIA”), Appellees would

*

Retired Senior Judge assigned to the Superior Court.

compensate Bruder $27,475, subject to additions and deductions as provided by the agreement.1 According to the scope of work document attached to the written agreement, the original plan was to build a detached one-level carriage- house style2 garage with a pitched roof. Those plans outlined a garage constructed of 620 square feet of masonry block with brick veneer covering the front and rear walls from ground to the gutter. The front side of the garage incorporated a wood-clad two-bay garage door. The rear of the structure had an additional single car garage door, a window, and a door for pedestrian access. The contract amount included the cost to build a 6’ x 12’ trussed roof with appropriate weatherization, shingles, gutters, and downspouts. While not expressly included in the scope of work that Appellant presented to Appellees prior to executing the construction contract, the agreement also covered several items that had been previously agreed upon. That work included connecting the garage to the existing electrical supply in the residence, installing an electric garage door opener,

1 The parties employed the 1987 edition of AIA Document A107 entitled “Abbreviated Form of Agreement Between Owner and Contractor.” 2 A carriage-house style of garage generally refers to a detached garage with living space above the garage area. In order to save money on construction cost, the initial construction plan omitted the second-floor living space completely. However, as discussed in the body of this memorandum, Appellees ultimately settled on a one-and-one-half-story structure in that style.

digging a trench for the installation of PEX water supply lines, and grading the back yard for proper drainage. Prior to signing the construction agreement, Mr. Monahan listed the omitted tasks on a Post-It note in Appellant’s presence and affixed that note to the scope of work that Appellant had prepared. Appellant eventually executed a change order (Change Order No. 2) that acknowledged those tasks as included in the original contract.

The demolition phase started as scheduled and construction progressed for approximately one month. On April 28, 2011, the parties agreed to amend the scope of work to include a stripped-down one-half story addition for $6,750.3 To facilitate the alterations, Appellant drafted Change Order No. 1 that read, “Build additional ‘1/2 story’ onto garage of 725 SF of 8[”] block. Included are two dormer openings; one at yard and one at street side.” Defendant’s Exhibit C. Appellant signed the change order and presented it to Appellees for approval.

Concerned that the change order was too vague and that Appellant had, again, omitted agreed upon tasks, Mr. Monahan drafted a revised change order that specified the height of the one-half story addition (six feet), the pitch of the roof (6’ x 12’), and the composition of the window or

3 The revisions did not include a staircase or any interior framing. The one- half-story interior was essentially a shell that Appellees could finish in the future.

door to be placed in the two dormer openings. In addition, the revised change order included cutting and installing a window in the south facing gable and additional brick veneer covering the front, rear, and exposed side of the structure. As Appellees interpreted their agreement with Appellant as including these items, the revised change order did not alter the expected increase of $6,750 to the contract price.

Appellees executed their version of the change order and mailed it to Appellant along with a $5,000 progress payment and the $6,750 advance payment that Appellant requested to construct the addition. Appellant did not sign the amended change order, but he accepted both payments and continued to perform the construction work according to the revised design. In the ensuing months, Appellees became dissatisfied with Appellant’s lack of progress and the quality of the work he performed. They also were unhappy with Appellant’s failures to repair damage that his employees caused to the neighboring property or to execute the revised Change Order No. 1. Appellant never repaired the damage satisfactorily or executed the revised Change Order No. 1. Indeed, the scope of the work contained in that change order was contested at trial and it remains a central contention on appeal.

Ultimately, it became apparent that the parties disagreed about the scope of Change Order No. 1. and the additional costs associated with Appellees’ proposed alteration of the planned electrical system. As it relates to the substantial electrical alterations, on July 18, 2011, Appellees paid

Appellant $1,500, which they believed covered the cost of permits and materials. On July 20, 2011, Appellant prepared Change Order No. 3 in the amount of $4,500. The change order, which Mr. Monahan denied receiving, purportedly covered the following:

1. Add 100A[4] electrical panel in the garage [and] 100A service at exterior.

2. Add 8 receptacles in conduit on interior walls.
3. Provide City of Pittsburgh electrical inspection.

Defendant’s Exhibit L. Appellant completed portions of the electrical alterations, but the extent of Appellant’s performance under the proposed change order is unclear from the certified record. Conversely, the record reveals that Appellant’s proposed $4,500 increase under Change Order No. 3 did not include Appellees’ prior $1,500 payment. See Defendant’s Exhibit S.

After communications soured, the pace of work slowed, and Appellant eventually stopped performing. By August 17, 2011, Appellees had paid Appellant $28,250 toward the contract price of $34,225. Appellees requested a refund for work that was not completed. Appellant countered with demands for payment for work he performed beyond the scope of the contract prior to Appellees’ decision to terminate the contract, i.e., the

additional brick veneer and the expanded electrical work.

4 The ampere, also identified and “A” or “amp,” is the base unit for measuring electric current.

On March 13, 2012, Appellees filed a civil complaint against Appellant seeking $21,655 in damages. Appellant eventually filed a counter claim for unjust enrichment totaling $14,775.5 The matter was assigned to compulsory arbitration, and the board of arbitrators awarded Appellees the damages they requested. Appellant appealed the award, and the case proceeded to a nonjury trial de novo on September 17, 2013.

Free access — add to your briefcase to read the full text and ask questions with AI

Gardner, L. v. Bruder, L., (Pa. Ct. App. 2015).

Gardner, L. v. Bruder, L. (Gardner, L. v. Bruder, L.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ferrer v. Trustees of the University of Pennsylvania
825 A.2d 591 (Supreme Court of Pennsylvania, 2002)
Helpin v. Trustees of the University of Pennsylvania
10 A.3d 267 (Supreme Court of Pennsylvania, 2010)
Allegheny County Housing Authority v. Johnson
908 A.2d 336 (Superior Court of Pennsylvania, 2006)
J.J. DeLuca Co. v. Toll Naval Associates
56 A.3d 402 (Superior Court of Pennsylvania, 2012)
Lambert v. Durallium Products Corp.
72 A.2d 66 (Supreme Court of Pennsylvania, 1950)