Garber v. Wright Cast Stone, Co.

146 So. 449, 167 Miss. 37, 1933 Miss. LEXIS 87
CourtMississippi Supreme Court
DecidedMarch 6, 1933
DocketNo. 30240.
StatusPublished
Cited by2 cases

This text of 146 So. 449 (Garber v. Wright Cast Stone, Co.) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Garber v. Wright Cast Stone, Co., 146 So. 449, 167 Miss. 37, 1933 Miss. LEXIS 87 (Mich. 1933).

Opinion

Cook, J.,

delivered the opinion of the court.

This appeal is from a decree of the chancery court of Hinds county, awarding the appellee a recovery of four thousand six hundred fourteen dollars and fifty-three cents against I. C. Garber and A. L. Dickson, composing the firm of Garber & Dickson, general contractors, and United States Fidelity & Guaranty Company, as surety on a bond executed by said contractors to guarantee the performance of their contract with the building commission of the state of Mississippi for the construction of *43 three public buildings on the campns of the University of Mississippi.

On the 6th day of June, 1929, the appellants, Garber & Dickson, entered into a contract with the state building-commission to furnish all materials and do all work necessary to construct, according to certain plans and specifications, three buildings at the said University, viz., the hospital building, graduate and classroom building, and demonstration high school building; and duly executed bond with United States Fidelity & Guaranty Company, as surety, for the performance of the contract, and the .payment of laborers and materialmen. Thereafter the following contract was entered into between appellants, Garber & Dickson, and the appellee:

“Garber & Dickson, Jackson, Miss.
“Gentlemen: We propose to furnish cast stone and cast granite where stone and granite are shown on plans and called for in specifications of Frank P. Gates & Company, Architects, Jackson, Miss., on Demonstration High School, Graduate School and Classroom Building, and General Hospital Building for the University of Mississippi, located at Oxford, Miss., with full freight allowed to Oxford, Miss., as follows:
Demonstration High School.................$ 4,738.00
General Hospital.......................... 7,834.00
Graduate School and Class Boom Building ... 20,678.00
$33,250.00
"Delivery: Cast stone on Demonstration High School to be delivered first. All cast stone to be delivered in order of use and as required. In case you (the General Contractors) are delayed on any of the building, such delay being caused solely by our failure, to deliver cast stone as needed, we agree to forfeit a sum not to exceed damages in so far as you are liable and .in no case to exceed fifty dollars per day on each building.
*44 “Terms: Eighty-Five per cent (85%) of the value of all stone delivered on the job will become due between the 1st and 10th of the month following delivery of same. Balance to be paid when all stone is set in the buildings and accepted by the Architect and Commission.
“Very truly yours,
“Wright Cast Stone Co. Inc.
“NHW-W By Neldien H. Wright.
“Accepted: Garber &• Dickson
“By: A. L. Dickson
“Dated: 6 — 19—29.”

The bill of complaint filed herein set up the making of the contract between Garber & Dickson and the state building commission, the execution of the performance bond, the making of the contract between Garber & Dickson and the appellee, and alleged that the appellee delivered, in compliance with its contract, all the material for the graduate school and classroom building, and demonstration high school building, and also stone for the hospital building, aggregating seven hundred sixteen dollars and forty cents; and that it was at all times ready, willing, and able to deliver all the remainder of said material for the hospital building, but, through no fault of the appellee, the said Garber & Dickson refused to take or receive the remainder of said material for said building.

It was further averred that the appellee furnished certain extra stone, amounting to three hundred twenty-eight dollars and thirty cents, and had incurred expense in making estimates, drawings, models, moulds, etc., for the manufacture of the stone for the hospital building amounting to seven hundred eighty-three dollars and thirty cents, and, at the request of said contractors, it had furnished certain labor and had incurred certain expenses in connection with the stone which went into the building, aggregating six hundred sixty-eight dollars and *45 forty cents, for all of which it alleged liability on the part of said Garber & Dickson. There were exhibits annexed to the bill of complaint showing the entire amount of stone and extras furnished to the contractors, an itemized statement of the extra cost of stone for the hospital building, on account of the failure to take the entire contract amount, aggregating seven hundred eighty-three dollars and forty cents, and other items claimed for labor on stone, etc., amounting to six hundred sixty-eight dollars and forty cents, together with a list of credits, the account showing a balance alleged to be due the appellee of five thousand two dollars and sixty-three cents, for which a decree was sought. •

The answer admitted that appellee furnished the stone for the graduate school and classroom building, demonstration high school building, stone of the value of seven hundred sixteen dollars and forty-one cents for the hospital building, and extras amounting to three hundred twenty-eight dollars and thirty cents. As to the items aggregatihg seven hundred eighty-three dollars and forty cents, it denied that appellee had incurred expense in making estimates, drawings, models, and moulds for the manufacture of the other stone, and denied the correctness of each item going to make this aggregate sum, and averred that they were unnecessary, unreasonable, and excessive. The answer also denied the appellants’ liability for the item of six hundred sixty-eight dollars and forty cents for labor furnished by the appellee in the construction of the buildings, and claimed additional credits amounting to one hundred twenty-two dollars and sixty cents, and also a credit of three thousand nine hundred dollars, as liquidated damages at fifty dollars per day for seventy-eight days’ delay due to the failure of the complainant (appellee) to deliver stone according to contract.

As to the item of three thousand nine hundred dollars *46 damages for delay, the appellants averred that, under the contract between Garber &

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Henry Marks v. United States
260 F.2d 377 (Tenth Circuit, 1959)

Cite This Page — Counsel Stack

Bluebook (online)
146 So. 449, 167 Miss. 37, 1933 Miss. LEXIS 87, Counsel Stack Legal Research, https://law.counselstack.com/opinion/garber-v-wright-cast-stone-co-miss-1933.