Gano v. Chicago & Northwestern Railway Co.

5 N.W. 45, 49 Wis. 57, 1880 Wisc. LEXIS 15
CourtWisconsin Supreme Court
DecidedMarch 30, 1880
StatusPublished
Cited by5 cases

This text of 5 N.W. 45 (Gano v. Chicago & Northwestern Railway Co.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gano v. Chicago & Northwestern Railway Co., 5 N.W. 45, 49 Wis. 57, 1880 Wisc. LEXIS 15 (Wis. 1880).

Opinion

Tayloe, J.

This action was brought to recover damages of the defendant company for the breach of a contract which the plaintiff claims to have made with the company for the delivery of 1,600 yards of stone at certain places upon the line of the defendant’s road. The facts as they appear from the evidence are these:

The plaintiff was the owner of a stone quarry near the line of the defendant’s railroad in Sauk county, in this state. The defendant company were doing some stone-work on the line of their road near Devil’s Nose, and were intending to do some other stone-work at what was called Crawford Creek or Crossing. It would be necessary to have 300 or 400 yards of stone for the work at Devil’s Nose, and about. 1,200 yards at Crawford Crossing. The plaintiff had some talk with Johnson, the chief engineer of the defendant, about furnishing stone for the work at Devil’s Nose, and also for the work which was to be done at Crawford Crossing; but they disagreed about the price, plaintiff wanting $3.50 per yard, and Johnson, the engineer, offering only $3, and no contract was made. Shortly after this conversation with Johnson, one Cel-luyham, who was foreman of the mason work at Devil’s Nose and at Merrimac bridge, on the line of said road, called upon the plaintiff, and, as the plaintiff says and the evidence tends to show, told plaintiff that he was authorized to contract with him on behalf of the defendant for stone for the work at Devil’s Nose, which was then in progress, and also for the work which it was expected would be done at Crawford Creek, and made a contract with plaintiff for 1,600 yards of stone, 400 yards to be delivered at Devil’s Nose and 1,200 yards at [60]*60Crawford Creek, for which the defendant company was to pay the sum of three dollars per yard. Under such contract the plaintiff went on and got out 400 yards for the work at Devil’s Nose, and most of them were delivered at that place and paid for; and he was ready and willing to deliver the 1,200 yards at Crawford Creek, and so informed the engineer, Johnson, and Johnson, on behalf of the company, notified the plaintiff that they would not receive the same, and that the company had made no contract with him for any stone for the work at Crawford Creek.

The evidence also shows that the foreman, Celluyham, had never bought any stone for the company before this purchase made of the plaintiff; that he had no general authority to buy stone for the company; and that in this case he had been directed to buy only such an amount of stone as would be wanted to complete the work at Devil’s Nose, and had no authority whatever to buy stoim for the proposed work at Crawford Crossing. It also appeared that none of the officers of the company had any knowledge that the plaintiff claimed to have made any contract with Celluyham for stone to be delivered for the work at Crawford Crossing, at the times they paid the bills for the stone delivered for the work at Devil’s Nose; and Celluyham himself swore on the trial that he had made no contract with the plaintiff for the delivery of any stone except such as were wanted for the last named work.

Celluyham testified that he was foreman, and had charge of the masonry on the Merrimac bridge and of the culvert called Devil’s Nose culvert; that his duties were to superintend the masonry, stone-cutting and general work; that he employed men, kept their time and reported it, and saw that the work was executed properly according to instructions; and that he never bought any stone for the company, or anything else, except those for the culvert at Devil’s Nose, and a few yards of wall stone, which he was directed- to get of the plaintiff by the assistant engineer, to finish such work. The testi[61]*61mony of. Celluyham upon this point is corroborated by the other witnesses, and no evidence was given showing that Cel-luyham had ever at any time purchased, or had any express authority to purchase, stone or other materials for the defendant company, except as above stated.

The appellant moved for a nonsuit both at the close of the plaintiff’s evidence and when the whole evidence was in, and the refusal of the nonsuit is alleged as error; but, as the majority of the court are of the opinion that there was some evidence in the case which might properly have been submitted to the jury as tending to show that Celluyham had the power to bind the company by a contract for the delivery of the 1,200 yards of stone at the Crawford Crossing as well as the 400 yards at the Devil’s Nose culvert, we shall consider the whole case upon the instructions which were given to the jury, and which were excepted to by the counsel for the defendant.

The exceptions to the refusal to grant a nonsuit and those to the refusal to give the instructions aslced, raise the same questions, viz., whether there was any evidence tending to show that Celluyham was authorized to bind the company by contract for the delivery of the 1,200 yards of stone at Crawford Crossing, or whether there was anything done by the company 'or its authorized agents, after the alleged making of such contract, which tended to prove a ratification of such contract, if made originally without authority.

As said above, the majority of the members of this court hold that there was some evidence given upon the trial of this case which tended to show the agency of Celluyham, or a ratification of his contract afterwards, if made without authority in the first instance, and only disagree with the learned circuit judge as to the effect which should be given to such evidence, if found in favor of the plaintiff. All the justices concurring in this opinion agree that the evidence given for the purpose of establishing the agency of Celluyham [62]*62icoes aot establish such agency as a question of law, and that the learned circuit judge should therefore have submitted the evidence to the jury as evidence tending to prove such agency, and left it with the jury to find as a question of fact whether such evidence established the agency. In this view of the case we are of the opinion that the learned circuit judge erred in several of his instructions to the jury. The instructions given, and which were excepted to by the defendant, were as follows:

1. In reference to said alleged contract, in the absence of any knowledge upon the part of the plaintiff as to whether or not said Celluyham had authority to make it, if such you find the fact to be, I think, and so charge you, that if you should find, from the evidence, that Celluyham was foreman and had charge of the mason work on the line of defendant’s road in the vicinity of Baraboo, or where the stones were to be delivered, and had at the time authority to make some contract with the plaintiff about stone, and had authority to employ men to carry on the work; that Celluyham entered into said contract professedly for the company; that after it was made the plaintiff commenced delivering stone in accordance with it, and continued to do so through a portion of the months of June and July, and they were received and put into the defendant’s road, and paid for at the contract price — the plaintiff had a right to presume, after such receipt and use commenced and was going on, that said Celluyham had authority to make the contract.
“ 2. And the company could not, after the amounts actually received and used were received and used, repudiate it.
“8.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Walker v. Peake
150 S.E. 757 (Supreme Court of South Carolina, 1929)
Gallinger v. Lake Shore Traffic Co.
30 N.W. 790 (Wisconsin Supreme Court, 1886)
Bouck v. Enos
21 N.W. 825 (Wisconsin Supreme Court, 1884)
Gano v. Chicago & Northwestern Railway Co.
17 N.W. 15 (Wisconsin Supreme Court, 1884)

Cite This Page — Counsel Stack

Bluebook (online)
5 N.W. 45, 49 Wis. 57, 1880 Wisc. LEXIS 15, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gano-v-chicago-northwestern-railway-co-wis-1880.