Gallaher v. District of Columbia

19 Ct. Cl. 564, 1884 U.S. Ct. Cl. LEXIS 24, 1800 WL 1244
CourtUnited States Court of Claims
DecidedMay 26, 1884
DocketNo. 21
StatusPublished
Cited by1 cases

This text of 19 Ct. Cl. 564 (Gallaher v. District of Columbia) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gallaher v. District of Columbia, 19 Ct. Cl. 564, 1884 U.S. Ct. Cl. LEXIS 24, 1800 WL 1244 (cc 1884).

Opinion

Soopield, J.,

delivered the opinion of the court:

December 22, 1873, the claimants contracted with the Board of Public Works to build the unfinished part of the Tiber Creek sewer. Under this contract they constructed 3,184.4 lineal feet. The contract price was $113 a lineal foot. The work done at this rate amounted to $359,837.20. They were paid thereon $324,400.71, leaving an unpaid balance of $35,436.49.

The defendant objects to the payment of most of this balance, and claims that in the construction of the sewer the claimants made certain variations from the specifications of the contract, whereby the cost to them and the value to the defendant was lessened at the rate of $8.94 a lineal foot. The whole amount of deduction claimed on this account is $28,468.53. This de[575]*575fense will be considered in connection with the next stated item of the claimants’ demand.

Under instructions of the defendant’s .engineers, claimants built the arch of the sewer V¿ feet in height, laid the foundation timbers and planking 41 feet in length, and built the abutment 'walls 5¿- feet thick; whereas the contract required 1 foot less for the height .of the arch, 4 feet less for the length of the foundation timbers and planking, and, as they allege, 2 feet less for the thickness of the abutment walls. This enlargement of the sewer cost the claimants $56,712.59.

Before examining these two items of the claim and the defenses thereto, it is proper to observe that the contract is very imperfectly drawn. It provides that the arch shall have a 60-foot span and the abutment walls shall be 5J feet thick, but the foundation timbers and planking shall be 37 feet long.' It provides that the abutment walls shall be built upon the timbers aud planking, but the latter shall extend only from the inside of one wall to the outside of the other. It provides that the rise of the arch shall be 6 feet 6 inches, and shall correspond in size to arch already built, which had a rise of 7 feet 10 inches. It .provides that the skew-back course shall be of the same thickness as the abutment walls, to wit, 3 feet 6 inches, although it elsewhere provides that the abutment walls shall be 5 feet 6 inches in thickness. Some things that should appear in the specifications are entirely omitted, and some things that do appear are stated in very doubtful language. Apparently the scrivener wrote the contract without fully knowing what the parties had agreed upon, and the parties signed it without fully knowing what the scrivener had written.

Fortunately, there is one clause in the contract which, with the action of the parties thereunder, enables us to ascertain their intention.

The sewer had already been partly constructed by other parties. The claimants were to begin where they left off. The construction and size of the new work by the terms of the contract were to be similar to the old. The abutment and skew-back walls of the sample work here referred to and called for were 5 feet 6 inches in thickness; the sleepers were 41 feet in length, extending from outside to outside of the abutment walls, and the skew-back course was built up of rubble masonry. The [576]*576defendant furnished a working plan for the claimants to follow, which, so far as it went, corresponds to the work of the sample. The claimants, without objection or other requirements of the defendant, constructed the sewer substantially in accordance with this working plan and the sample work. They did what apparently they supposed the contract required them to do, and thus furnished us with their understanding and construction of it.

Thus the claimants proceeded with their work until about 680 feet had been completed. It was done under the supervision of Mr. Cluss, the District engineer, and his assistants. No complaint was made on either side. The contractors seemed content to make the enlargement and the defendant content with the quality of the work. Both, it is believed, substantially followed the sample and the working plan, but in some respects differed from the provisions of the contract.

Then came the act of June 20, 1874, by which the Board of Public Works was abolished and Commissioners appointed. Lieutenant Hoxie, of the Army, was detailed as District engineer. His first business was to examine the Tiber Creek sewer. It does not appear that he ever examined the sample work. He saw, however, that the work was not being done as well as the contract required. He particularly objected to the skew-back course. He required, as did the contract, the use of dimension stone. He was informed that the procurement of such stone would cause delay. He finally directed them to construct it of a certain kind of brick-work. At the same time he notified the person in eharge, supposed to be one of the claimants, that he should make a deduction in price, but named no amount. He reported his action to the commissioners, who made no objection. Thereafter the work proceeded to completion under Lieutenant Hoxie’s direction.

When the engineer caihe to make estimates for partial payments he deducted $8.94 a lineal foot for this change in the work. The claimants protested, and the dispute remains unsettled.

Here, then, are two important variations from the written contract, one in the size of the sewer and the other in the quality of the work. The one to the disadvantage of the claimants and the other to the defendant. Both were according to the working plan, so far as it went, and according to the sample. [577]*577In this way 680 feet were completed to the apparent satisfac-faction of both parties. The new engineer did not forbid the work to. proceed, but required it to proceed on a plan of his own, to which the claimants, conformed. To be sure, he said he should make a deduction in the price, but to this the claimants did not assent. It was not made as a condition of allowing them to proceed, but to save time and facilitate the work. It was for the defendant’s convenience, to avoid .delay. We think the work was done, substantially, in conformity to the sample work and the working, plan, and therefore reject the claimants’ demand for $56,712.59, on the one hand, and the defendant’s deduction of $28,468.53 on the other.

By direction of the defendant’s engineer the claimants constructed four lateral sewers, whose united length was 353 feet, and whose united cost was $5,525.19. (Finding IX.) The defendant claims that the claimants were bound by their contract to make these sewers at their own expense. The contract provides that “ all the connections for lateral sewers must be made when and as directed by the engineer.” This certainly requires the claimants to leave proper openings in the Tiber Creek sewer and join the lateral sewers thereto, but not to construct 373 feet of sewerage in order to bring the several parts within joining proximity. It was in contemplation of the original contract to build the Tiber Creek sewer along and near to the outlets of these lateral sewers. Its location was subsequently changed by agreement of the parties. It is said that this change was so favorable to the claimants that they could well afford to construct the extensions under the contract price. That may be so, but as the parties did not so agree the court cannot supply the omission by astrained and arbitrary construction. The •defendant should pay the claimants the reasonable cost, which is $5,525.19.

The claim of $40.25 (Finding IX) should not be allowed because it was required by the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Joice v. United States
51 Ct. Cl. 439 (Court of Claims, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
19 Ct. Cl. 564, 1884 U.S. Ct. Cl. LEXIS 24, 1800 WL 1244, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gallaher-v-district-of-columbia-cc-1884.