Galassi Mosaic & Tile Co. v. City of Boston

4 N.E.2d 291, 295 Mass. 544, 1936 Mass. LEXIS 1149
CourtMassachusetts Supreme Judicial Court
DecidedOctober 28, 1936
StatusPublished
Cited by13 cases

This text of 4 N.E.2d 291 (Galassi Mosaic & Tile Co. v. City of Boston) is published on Counsel Stack Legal Research, covering Massachusetts Supreme Judicial Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Galassi Mosaic & Tile Co. v. City of Boston, 4 N.E.2d 291, 295 Mass. 544, 1936 Mass. LEXIS 1149 (Mass. 1936).

Opinion

Pierce, J.

This is an action of tort. The declaration alleges, in substance, that the plaintiff, a duly organized corporation, is engaged in the manufacture and sale of mosaic and tile; that by St. 1929, c. 297, it was provided that the city of Boston should proceed with the laying out and construction of a tunnel, which should consist of two or more roadways or lanes for vehicular traffic, under Boston Harbor, between the city of Boston proper and the East Boston end thereof; that pursuant to said legislative requirements one Wilbur W. Davis, an engineer in the employ of the defendant, in its transit department, conferred with the president of the plaintiff corporation relative to the furnishing and proper installation of the material for the interior surfacing of the East Boston Tunnel; that it was then and there stated (by said Davis) to the plaintiff “that because of the various and divers problems existing, and particularly of the necessity of adequate drainage and ventilation, and to avoid corrosion and destruction by reason of moisture, [545]*545. . . it was essential that a surfacing material somewhat different, and peculiarly adapted to the situation should be devised for use in said Tunnel”; that at the request of the defendant acting through its duly authorized agents and representatives, the plaintiff “undertook and began a process of experimentation necessitating much time, effort and study relative to the devising of a suitable material for the use in the interior surfacing of said East Boston Tunnel, which could be properly and adequately applied”; that “after long and arduous preparation and scientific labor, the plaintiff developed a tile which could be set directly upon the concrete wall, without the use of a base of terra cotta or concrete”; that subsequently the plaintiff was informed by engineers of the city of Boston “that it had been demonstrated that only one and three quarters inches could be allowed for the lining or surfacing material and that because of seepage and the deposit of calcium carbonate formations it was requisite that there be an air space behind the tiling and provision made for gathering and taking care of said seepage”; that, thereupon, the plaintiff continued its experimentation and study of said problem in an effort to devise a material and method of installation suitable for use in the tunnel; that after long and arduous study and experimentation the plaintiff successfully developed a process involving the use of a tile eight inches by eight inches, with grooves across the back and stainless steel rods set horizontally in cement in the upper and lower grooves, being fastened by stainless clips and expansion bolts set in cement against the concrete walls, thereby at once taking care of the problem of drainage and circulation of air behind the lining and at the same time meeting the limited space requirements; that “said process, and the method of installation, were entirely novel, having never been developed or used elsewhere in the trade and being hitherto unknown to the defendant”; that “the use of said tile and method of installation was not only entirely novel but was peculiarly adapted to the surfacing requirements of said East Boston Tunnel'in that it provided for maximum effective drainage, convenient and speedy replacement of any part that might [546]*546become damaged”; that it would entirely solve the problem raised by exigencies of space requirements and would provide a tile which was nonstaining, attractive in appearance, entirely durable and affording a maximum light reflection with a minimum of glare; that a period of a year and a half was consumed by the plaintiff in the experimentation and scientific labor required for the adaptation and perfection of said tile and method of installation; that throughout this period the plaintiff through its duly authorized president was in frequent and constant consultation with the officers and agents of the defendant; that throughout the progress of the work the defendant was constantly apprised of the work being carried on by the plaintiff; that demonstrations were made by the plaintiff for the benefit of said agents and representatives of the defendant for the purpose of showing the practicability and advantage in the use of material and installation devised and adapted by the plaintiff as aforesaid; that upon the completion of said work, at the request of the defendant, its agents and representatives, a section of said lining was erected and set up at the office of the transit department of the city of Boston and another section was erected and set up at the East Boston Tunnel in order to demonstrate its application to the walls of said concrete tunnel; and that said work of experimentation and scientific labor were undertaken by the plaintiff upon the understanding with the agents and representatives of the defendant that “if the plaintiff was successful in this new type of surfacing material and method of installation ... it would be awarded the contract for the surfacing of said . . . Tunnel by reason of the fact that said process or device would be entirely novel and unknown to the general trade, and by reason of said novelty it would result that the plaintiff would be the only one to whom said contract could be given after the practicability and durability of said device was satisfactorily demonstrated.” The declaration further alleged that after the completion of this work by the plaintiff, as aforesaid, and after said materials had been set up and demonstrated to the defendant, it was then represented'to the plaintiff for the first time that it was necessary, by virtue [547]*547of the statutory provisions and the requirements of the city ordinances, that the contract for the surfacing of the tunnel be let only after public advertising and sealed competitive bidding; that it was further represented to the plaintiff that if it would furnish the specifications for use in said contract and for the purpose of inviting competitive public bidding, and would bid upon said specifications, it would necessarily be the lowest responsible bidder and be awarded the contract, and would thereby be rewarded for the publication of said process and method of installation; that thereafter the said transit department advertised for sealed proposals for the furnishing and installation of tile for said tunnel completely and entirely in accordance with the specifications prepared by the plaintiff and the process of tiling material and method of installation devised and invented by the plaintiff as aforesaid; that in full and complete reliance on the' officers and agents of the defendant the plaintiff submitted a sealed bid for the work; and that subsequently and on or about August 16, 1933, it was announced by said transit department of the defendant that a contract for the furnishing and installation of tile of said East Boston vehicular tunnel in accordance with the plans entirely devised by the plaintiff, as aforesaid, had been awarded to The C. M. Tyler Company. The plaintiff further alleged “that these representations made by the officers and agents of the defendant . . .

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Phipps Products Corp. v. Massachusetts Bay Transportation Authority
443 N.E.2d 115 (Massachusetts Supreme Judicial Court, 1982)
Morash & Sons, Inc. v. Commonwealth
296 N.E.2d 461 (Massachusetts Supreme Judicial Court, 1973)
Reynolds Boat Co. v. City of Haverhill
260 N.E.2d 176 (Massachusetts Supreme Judicial Court, 1970)
City of Boston v. Came
17 Mass. App. Dec. 103 (Mass. Dist. Ct., App. Div., 1959)
City of Boston v. Guarino
15 Mass. App. Div. 167 (Mass. Dist. Ct., App. Div., 1950)
Cole Drug Co. v. City of Boston
14 Mass. App. Div. 203 (Boston Municipal Court, 1949)
Metcalfe v. Town of Franklin
9 Mass. App. Div. 37 (Mass. Dist. Ct., App. Div., 1943)
Sweeney v. City of Boston
34 N.E.2d 658 (Massachusetts Supreme Judicial Court, 1941)
Baumgardner v. City of Boston
23 N.E.2d 121 (Massachusetts Supreme Judicial Court, 1939)
Cook v. Overseers of Public Welfare
22 N.E.2d 189 (Massachusetts Supreme Judicial Court, 1939)
Daddario v. City of Pittsfield
17 N.E.2d 894 (Massachusetts Supreme Judicial Court, 1938)
Sloper v. City of Quincy
16 N.E.2d 14 (Massachusetts Supreme Judicial Court, 1938)
New England Trust Co. v. City of Boston
15 N.E.2d 255 (Massachusetts Supreme Judicial Court, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
4 N.E.2d 291, 295 Mass. 544, 1936 Mass. LEXIS 1149, Counsel Stack Legal Research, https://law.counselstack.com/opinion/galassi-mosaic-tile-co-v-city-of-boston-mass-1936.