DAUGHERTY, District Judge.

This case involves the basic question of whether or not the defendant, Houston Compress Steel Company, has the right to remove a part of a steel and sheetiron building which had been severed from the realty, or if such right has been lost and ownership of said building now belongs to the plaintiff, Bonnie Gaither, dba Cavanaugh Coal Company, the owner of the realty on v/hich such building is located.

In 1953 the plaintiff bought approximately 850 acres in Leflore County, Oklahoma, at bankruptcy sale. At all times herein involved, the husband of the plaintiff, Bonnie Gaither, acted as her agent and within the scope of his authority as such. Prior to this purchase a large steel and sheetiron building with certain machinery located therein, along with other buildings, were purchased at bankruptcy sale by a predecessor in title to the defendant, Houston. These buildings and contents were severed from the land by the bankruptcy court and a prescribed period of time was allowed for their removal from the land on which they were situated. To extend the removal period, the other buildings were eventually conveyed to the plaintiff as the land owner. A further extension of time for removal until January 1, 1959, of said steel and sheetiron building and machinery therein, was entered into on December 2 or 3, 1957, between plaintiff as the land owner and the defendant’s predecessor in title, and as consideration for this extension the defendant’s predecessor in title agreed upon removal to leave in place the support beams that held up the floor. Defendant’s predecessor in title was represented by one Simon Elliott in the act of obtaining said last extension agreement. . Said Elliott hired a watchman to safeguard and care for said property at about the time of obtaining said last extension.

Said building and the machinery located therein, were not removed by January 1, 1959. In February, 1959, it became necessary to replace the original watchman who had been hired and the plaintiff assisted Elliott in hiring a new watchman at $150.00 per month. This new watchman happened to be a relative of plaintiff named Curtis Garrett. Garrett lived in a house nearby furnished by plaintiff and apparently did some chores or work for plaintiff, as well as being engaged as a watchman for the owner of the building and machinery. This watchman continued to look after and hold possession of said property for Elliott and the defendant, Houston, until the defendant, Houston, started removal of the building and machinery by its agents, one of whom was Buck Love, co-defendant herein.

After January 1,. 1959, the plaintiff never demanded rent from Elliott nor a further extension agreement, nor did [998]*998plaintiff ever demand that Elliott remove the property at or within any time. The defendant, Houston, or its predecessors in title paid the ad valorem taxes on said building and machinery for all years from 1955 until 1962, inclusive. This property was assessed separately from the land.

In May of 1961, Elliott sold the said building and machinery to the defendant, Houston Compressed Steel Company. Before completing the purchase of this property, the defendant Houston, by Mr. Byers, its President, called the plaintiff by long distance telephone regarding the proposed purchase for the purpose of discussing same and the matter of the steel support beams referred to in the last extension agreement. A further long distance telephone conversation was had between the same parties about three weeks after the sale was completed to the defendant, Houston. During neither conversation or thereafter did the plaintiff claim ownership of the building or machinery save the right to the support beams holding up the floor pursuant to the last extension agreement, or did plaintiff voice objection or give warning to the defendant, Houston, about its buying the property.

In January or February, 1962, the defendant, Houston, sent its agents to the property to remove the machinery and dismantle the building. At this time the watchman Garrett was still in possession of the building and machinery for the defendant. Upon commencing said removal by the agents of defendant, the plaintiff for the first time claimed ownership of the entire building but allowed the defendant to remove all machinery therein and to open the sides of the building for such purpose as necessary to remove said machinery, which removal of machinery was completed by May of 1962. This claim of plaintiff was made to Buck Love, the agent of defendant, Houston, in January or February of 1962. Love communicated this information to the defendant, Houston, which was the defendant Houston’s first notice of any such claim by the plaintiff.

In May, 1962, at about the time the machinery was all removed, the plaintiff filed a suit in State Court requesting an injunction against the defendant, Houston, preventing the removal of the building. A temporary restraining order was issued by the State Court against removal, which has been kept in force and effect. This case was removed to this court, which has jurisdiction by virtue of a diversity of citizenship with the required amount being involved. By subsequent amendment in this court, plaintiff seeks recovery for the damage to the building occasioned by the defendant’s removal of the machinery which plaintiff claims was unnecessarily done in connection with said removal of machinery. The defendant, Houston, by its pleadings, claims ownership of the building with the right to remove same except the steel beams which support the wall next to the lake and requests damages from plaintiff for the wrongful detention of said building. The claim for damages for wrongful detention was withdrawn by defendant, Houston, during the trial.

Thus, the plaintiff, according to opening statement, claims ownership of the building from the floor down by virtue of the last extension agreement and claims ownership of the building above the floor by reason of the defendant, Houston, and its predecessors in title, failing to remove the same by January 1, 1959, the termination date of the last written extension. Plaintiff makes no claim to the machinery but requests judgment for damages to the building brought about through the removal of said machinery by the defendant, Houston.

The defendant, Houston, claims it owns the building except for those steel beams which support the lake wall, asserting that it and its predecessors in title occupied and had possession of said building and machinery after the termination date of the last extension agreement of January 1, 1959, and at all times thereafter on a continuous basis until they were enjoined by the temporary restraining order issued by the State [999]*999Court in the suit filed in May, 1962, by the plaintiff. The defendant, Houston, further asserts that plaintiff aided them in their continuous possession of said property, acquiesced in their possession and occupancy of the same, and never made any demand for rent or removal or made claim of ownership until dismantling began in January or February, 1962.

It appears from the testimony that the steel in the building is valued at approximately $20,000.00, and within such figure the steel beams supporting the floor have a value of approximately $3,000.00. The testimony is further to the effect that 120 days would be a reasonable time required for the removal of the building.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Berry v. Opel
1944 OK 360 (Supreme Court of Oklahoma, 1944)
Hancock v. Maurer
1924 OK 862 (Supreme Court of Oklahoma, 1924)
Turner v. Bishop
1937 OK 445 (Supreme Court of Oklahoma, 1937)
Jones v. Goldsberry
1926 OK 523 (Supreme Court of Oklahoma, 1926)
Brown v. Reno Electric Light & Power Co.
55 F. 229 (U.S. Circuit Court for the District of Nevada, 1893)

Cite This Page — Counsel Stack

Bluebook (online)
221 F. Supp. 996, 1963 U.S. Dist. LEXIS 9781, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gaither-v-byers-oked-1963.