Gaiennie Co. v. Pouchereau
This text of 9 Teiss. 81 (Gaiennie Co. v. Pouchereau) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinions
Plaintiff contracted to do certain plumbing work for defendant for the fixed price of $66.50 and in the same contract, to lay certain sewer pipes- at' 30 cents per running foot, if permitted by the Sewer Board. This permission was granted and 160 feet of pipe were laid. The plumbing was also completed.
Plaintiff then filed two suits in the City Court on the same day, one for the price of the plumbing, $66.50; and the other for the sewer pipes. $48.00.
The suit first mentioned was prosecuted to final judgment and resrdted in a judgment for the plaintiff.
Plaintiff then -undertook to prosecute the second suit and was met with the objection that, having claimed in the first suit less than was due, it cannot now recover the balance; and defendant relies on Articles 91 and 156 of the Code of Practice.
After mature consideration we conclude that, under [82]*82the jurisprudence those articles have no application to the case at bar.
In American Mfg. Co. vs. Massman, 7 Court of App. 256, we held, following Brandagee vs. Chamberlain, 2 Rob. 207, and In re Dimmick, 111 La. 658, that those articles prohibited only “the dividing of a single and indivisible debt, and suing on each part severally;” that they had no application to separate and distinct debts “nor where the debt i.s divisible and the different parts or installments are demandable severally, or at different .times.”
In the case at bar the debt appears to us clearly divisible, and to have been made so ex industria. Two different objects were contracted for; the one absolutely, the other conditionally only. The considerations were also kept distinct; for the plumbing a fixed price was agreed upon, the price for the sewer pipes was to be so much per foot.
Thus it was held in Glaze vs. Sheriff, 40 An. 692, that a contract is legally divisible “which sets forth two distinct considerations for two different objects, although for one main purpose only.”
A contract of this sort creates what the Civil Code designates a “conjunctive” obligation, giving rise to “as many different obligations as there are different objects,” all of which may be severally discharged or enforced. C. C. 2063, 2065.
It is therefore ordered that the judgment appealed from be reversed, and it is now ordered that there be judgment in favor of the plaintiff and appellant, Gaiennie Co. Limited ,and against defendant and appellee, A. Bouchereau, for the full sum of $48.00 (Forty-eight dollars) with legal interest from judicial demand and costs of both Courts.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
9 Teiss. 81, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gaiennie-co-v-pouchereau-lactapp-1911.