Gai Consultants, Inc. v. Public Service Commission

19 Ct. Cl. 141
West Virginia Court of Claims·Decided October 1, 1992·No. CC-92-124·Published

Opinion

PER CURIAM:

This claim was submitted for decision based upon the allegations in the Notice of Claim and the respondent’s Answer.

Claimant seeks $12,359.33 for engineering services provided respondent. The invoices for the services were not processed for payment in the proper fiscal year; therefore, the claimant has not been paid. The respondent admits the validity and amount of the claim and states that there were sufficient funds expired in the appropriate fiscal year with which the claim could have been paid.

In view of the foregoing, the Court makes an award in the amount of $12,359.33.

Award of $12,359.33.

Free access — add to your briefcase to read the full text and ask questions with AI

Gai Consultants, Inc. v. Public Service Commission, 19 Ct. Cl. 141 (W. Va. Super. Ct. 1992).

19 Ct. Cl. 141 (Gai Consultants, Inc. v. Public Service Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.