Gage v. City of Portland

860 P.2d 282, 123 Or. App. 269, 1993 Ore. App. LEXIS 1562
CourtCourt of Appeals of Oregon
DecidedSeptember 22, 1993
Docket93-030; CA A80355
StatusPublished
Cited by8 cases

This text of 860 P.2d 282 (Gage v. City of Portland) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gage v. City of Portland, 860 P.2d 282, 123 Or. App. 269, 1993 Ore. App. LEXIS 1562 (Or. Ct. App. 1993).

Opinion

*271 DEITS, P. J.

Petitioners seek review of LUBA’s decision affirming the City of Portland’s approval of respondent FP-35 Partners’ application for a minor amendment to a planned unit development (PUD). We reverse.

The city granted final development plan approval for the original PUD in September, 1984, more than eight years before its approval of the amendment in the present proceeding. In their first assignment to LUBA and to us, petitioners contend that the city hearings officer, who rendered the final decision, erred by not responding in her order to petitioners’ argument that, under former PCC 33.79.140 and 33.79.150, 1 the final approval of the original plan had expired before the granting of the amendment here, because no development had taken place within eight years of the original plan’s approval. According to petitioners, the two code provisions should be interpreted as meaning that final plan approvals expire under those circumstances, that the plan was, therefore, not in effect at the time that the city took final action on the present application, and that there was, therefore, no PUD in existence to which an amendment could then be allowed. 2

PCC 33.79.140(a) provided that preliminary PUD approvals remain valid for a period of three years, and that final development plans for the entire site or for the first phase of phased developments must be submitted within that time. Under PCC 33.79.140(e), approval of the final development plan constituted a final decision on the PUD application. PCC 33.79.150(d) provided that, in the case of phased PUD projects, the “sum of the years between the first approved final phase and the last approved final phase may not exceed 8 years.”

According to petitioners, those code provisions should be interpreted to mean that final plan approvals have an eight-year duration within which development must occur, and they otherwise expire after eight years. Petitioners argued to LUBA that, under Clark v. Jackson County, 313 Or *272 508, 836 P2d 710 (1992) and Weeks v. City of Tillamook, 117 Or App 449, 844 P2d 914 (1992), the hearings officer’s failure to interpret the two code provisions and to address petitioners’ argument that the 1984 final approval had lapsed required that the decision be remanded to the city to consider and address those issues in its order.

In Clark, the Supreme Court held that LUBA and reviewing courts must accept local interpretations of local land use legislation that are not contrary to the language or apparent purpose or policy of the legislation, read in its context. Weeks is one of a series of decisions by this court, made in the aftermath of Clark, that attempt to implement Clark and to redefine the parts of the pre-Clark system of LUBA and judicial review that do not survive the Supreme Court’s decision. We concluded in Weeks that Clark implicitly, but necessarily, requires local governments, rather than LUBA or us, to make initial interpretations of local provisions “that are necessary to their decisiones],” when the local legislation “is capable of more than one tenable interpretation.” 117 Or App at 454. In the absence of such a local interpretation, we held, LUBA may not supply an interpretation ab initio, but must remand for the local government to make the necessary interpretation in its order. See also Larson v. Wallowa County, 116 Or App 96, 840 P2d 1350 (1992); West v. Clackamas County, 116 Or App 89, 840 P2d 1354 (1992).

The rationale of Weeks is twofold. First, it holds that Clark’s principle of deferential LUBA and judicial review of local interpretations necessarily implies a recognition that it is the prerogative of local governments to interpret their own legislation in the first instance, and it carries with it an assignment of interpretive responsibility to local governments as well as a rule concerning how LUBA and the courts are to review those interpretations. See also Green v. Hayward, 275 Or 693, 706, 552 P2d 815 (1976). The second reason for our conclusion in Weeks was that, for LUBA and the courts to be able to review local interpretations under the Clark standard, the local orders must contain any interpretations that are necessary to their decisions and must articulate those interpretations adequately to make review possible. See also Green v. Hayward, supra, 275 Or at 706.

*273 LUBA rejected petitioners’ argument. It looked to the language of the two code provisions and concluded that they are unambiguous and have no arguable bearing on the duration of final plan approvals, but relate only to the times within which final plans must be submitted and final approvals must be obtained. Having rejected petitioners’ contrary understanding of the provisions, LUBA went on to explain:

“In Weeks v. City of Tillamook, supra, the [C]ourt of [A]ppeals said Clark requires that this Board not interpret a local government’s ordinances in the first instance, but rather review the local government’s interpretation of its ordinances. However, the code provisions at issue in Weeks were complex and ambiguous, and their interpretation was the core of the challenged land use decision. We do not believe Weeks should be read to establish a principle that this Board must remand the decision for a local interpretation to be made wherever a petitioner can identify an arguably relevant, but clear and unambiguous, code provision that is not interpreted in the challenged decision.”

Petitioners now contend to us that LUBA erred in that holding. They assert that, under Clark and Weeks, “[i]t is the city that must address and resolve this issue first on remand, ’ ’ and that LUBA erred by taking the initial interpretive task upon itself.

In this case, as in Friends of the Metolius v. Jefferson County, 123 Or App 256, 860 P2d 278 (1993), a predictable, if not inevitable, consequence of Clark has manifested itself: The focus of the petitioners’ arguments is not on whether the local decision was right or wrong, but on what body is empowered to decide what questions in connection with the decision and its review. However, that focus is engendered, and possibly necessitated, by Clark.

The key to LUBA’s reasoning was that Clark and Weeks do not require a remand for local interpretation of “arguably relevant” and uncomplicated local provisions that LUBA determines for itself are unambiguous and cannot be interpreted in the manner that the propounding party suggests. We have said, in Goose Hollow Foothills League v. City of Portland, 117 Or App 211, 218, 843 P2d 992 (1992), and Reusser v. Washington County, 122 Or App 33, 36 n 1, 857

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gage v. City of Portland
891 P.2d 1331 (Court of Appeals of Oregon, 1995)
Sullivan v. City of Ashland
882 P.2d 633 (Court of Appeals of Oregon, 1994)
Gage v. City of Portland
877 P.2d 1187 (Oregon Supreme Court, 1994)
Zippel v. Josephine County
876 P.2d 854 (Court of Appeals of Oregon, 1994)
Friends of Bryant Woods Park v. City of Lake Oswego
868 P.2d 24 (Court of Appeals of Oregon, 1994)
O'Neal v. Deschutes County
867 P.2d 532 (Court of Appeals of Oregon, 1994)
Department of Land Conservation & Development v. Crook County
860 P.2d 907 (Court of Appeals of Oregon, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
860 P.2d 282, 123 Or. App. 269, 1993 Ore. App. LEXIS 1562, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gage-v-city-of-portland-orctapp-1993.