G. T. Leach Builders, L. L. C. v. Sapphire Vp, Lp

456 S.W.3d 570, 2013 WL 2298447, 2013 Tex. App. LEXIS 6456
CourtCourt of Appeals of Texas
DecidedMay 23, 2013
Docket13-11-00793-CV
StatusPublished
Cited by4 cases

This text of 456 S.W.3d 570 (G. T. Leach Builders, L. L. C. v. Sapphire Vp, Lp) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
G. T. Leach Builders, L. L. C. v. Sapphire Vp, Lp, 456 S.W.3d 570, 2013 WL 2298447, 2013 Tex. App. LEXIS 6456 (Tex. Ct. App. 2013).

Opinion

MEMORANDUM OPINION

Memorandum Opinion by

Chief Justice VALDEZ.

This is an interlocutory .appeal challenging the trial court’s denial of appellants’ motions to compel arbitration. Appellee, Sapphire, V.P., L.P. sued appellants for breach of contract and negligence for damage to its condominium complex caused by Hurricane Dolly. The appellants include: (1) the architectural firm that designed the condominium complex, ZCA Residential, LLC (“ZCA”) 1 ; (2) thé general contractor, G.T. Leach Builders, LLC (“GTL”); (3) the subcontractors, CHP & Associates, Consulting Engineers, Inc. (“CHP”), Comfort Systems USA — South Central fik/a Atlas Comfort Systems USA, LLC (“Atlas”), and Power Design, Inc. (“PDI”); and (4) the insurance providers for the condominium complex, Arthur J. Gallagher Risk Management Services, Inc., Tracy Williams, and Adams Insurance Services, Inc., (collectively the “Insurance Appellants”). We affirm.

*574 I.Background

In July 2008, during construction of a condominium complex Sapphire owned, Hurricane Dolly hit South Padre Island, Texas causing damage to the complex. In November 2009, Sapphire filed its original petition in Cameron County against the “Insurance Appellants” for negligence and breach of contract seeking $3.5 million for water damage and $6 million for “soft costs.” 2 Sapphire claimed that the Insurance Appellants had failed to procure insurance to adequately compensate Sapphire for any damage caused during -the construction of the complex. According to Sapphire, the builder’s risk policy that would have covered all of the damages, including soft costs, was allowed to expire before- the hurricane hit, even though the construction of the complex had not been completed. 3

In July 2010, Sapphire filed its original petition against ZCA in Harris County, Texas, seeking damages for negligence and breach of contract in designing the condominium complex. Sapphire alleged that ZCA’s negligence related to the design of the project that led to the water damage, and Sapphire sought $26.3 million in damages and $6 million for other expenses, delay costs, and lost sales revenue. ZCA designated GTL, CHP, PDI, and Atlas (collectively the “Construction Appellants”) as responsible third parties.

On March 28, 2011, the trial court granted the Insurance Appellants’ motion to designate the Construction Appellants as responsible third parties in the Cameron County lawsuit. Accordingly, Sapphire amended its Cameron County pleadings on April 11, 2011 to include the Construction Appellants as defendants. Sapphire alleged that the Construction Appellants were negligent in their respective duties because the louvers, mechanical/electrical rooms, and other areas in the upper floors of the condominium complex were not designed and constructed properly which resulted in water entering and damaging the building during the hurricane. Sapphire also sued the Construction Appellants for breach of contract claiming that the Construction Appellants had “agreed that all of their services would be of the standard and quality that prevails among reputable [professionals] engaged in similar practices in the State of Texas on projects similar to the Sapphire project” and had failed to do so.

In May 2011, all appellants filed motions to transfer venue and then filed motions to abate. The trial court denied the appellants’ motions to transfer venue and. abate. The parties do not challenge the trial court’s rulings on these motions.

On August 11, 2011, the Construction Appellants filed a joint motion for continu- *575 anee requesting a new trial date of May 7, 2012 and entry of a new docket control order subject to their motions to transfer venue in Cameron County. 4 On August 31, 2011, the Cameron County trial court granted the Construction Appellants’ motion for continuance and set a trial date of April 2, 2012.

On October 13, 2011, all of the parties signed an agreed discovery control plan/scheduling order, agreeing to deadlines for designation of responsible third parties, joinder of new parties, designation of expert witnesses, discovery, dispositive motions and pleas, summary judgment motions, alternative dispute resolution, and amendments to pleadings. The parties also agreed to a pretrial conference or docket call on February 15, 2012 and to the previously set trial date of April 2, 2012.

On November 3, 2011, Adams filed a motion for summary judgment on the basis that Sapphire could not show that there was privity of contract with Adams because its contract for insurance was with GTL; therefore, Adams argued it owed no duty to an additional insured, such as Sapphire. Adams further argued that the evidence conclusively established that it did not enter into an oral or written contract with Sapphire to procure insurance for the project. The trial court granted the summary judgment in favor of Adams with regards to Sapphire’s claim for breach of contract but denied it with regards to Sapphire’s negligence claim. 5

GTL then served Sapphire with a written demand to arbitrate the issues raised in the lawsuit and filed its motion to compel arbitration and to stay the litigation pursuant to the Texas Arbitration Act (the “TAA”) in Cameron County. GTL relied on a provision in its contract with Sapphire (the “General Contract”) it claimed required arbitration of Sapphire’s claims. All other appellants filed similar motions to compel arbitration and/or join GTL’s motion to compel arbitration.

Sapphire challenged the motions to compel arbitration on two grounds: (1) only GTL had a contractual arbitration provision, so the other defendants had no right to compel arbitration; and (2) GTL’s conduct of agreeing by Rule 11 to go to trial, together with the totality of the conduct of all. of the parties in the case, constituted waiver of GTL’s right to compel arbitration. Sapphire argued that it did not have a written contract with any of the appellants, except for GTL, and that its contract with GTL “specifically provide[d] that there are no third party beneficiaries and that non-signatories to the contract [could not] claim any rights under its terms, including the right to arbitrate.” Sapphire also argued that GTL could not demand arbitration because a clause in the General Contract prohibited the parties from demanding arbitration after the statute of limitations had expired. 6 After a hearing on December 7, 2011, the trial court denied the appellants’ motions to compel arbitration. The trial court did not state its basis for denying arbitration. This interlocutory appeal followed.

II. STANDARD OF REVIEW

We apply an abuse of discretion standard to the trial court’s denial of ap *576 pellants’ motions to compel arbitration. Okorafor v. Uncle Sam & Assocs., Inc., 295 S.W.3d 27, 38 (Tex.App.-Houston [1st Dist.] 2009, pet. denied).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
456 S.W.3d 570, 2013 WL 2298447, 2013 Tex. App. LEXIS 6456, Counsel Stack Legal Research, https://law.counselstack.com/opinion/g-t-leach-builders-l-l-c-v-sapphire-vp-lp-texapp-2013.