G. H. Lindekugel & Sons, Inc. v. Brezina Construction Co.

160 N.W.2d 121, 83 S.D. 404, 1968 S.D. LEXIS 117
CourtSouth Dakota Supreme Court
DecidedJuly 18, 1968
DocketFile 10423
StatusPublished
Cited by4 cases

This text of 160 N.W.2d 121 (G. H. Lindekugel & Sons, Inc. v. Brezina Construction Co.) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
G. H. Lindekugel & Sons, Inc. v. Brezina Construction Co., 160 N.W.2d 121, 83 S.D. 404, 1968 S.D. LEXIS 117 (S.D. 1968).

Opinion

BIEGELMEIER, Judge.

This is an action for breach of a subcontract plaintiff claimed it entered into with defendant. Both are engaged in heavy construction work. This action resulted from the proposed construction in North Dakota of an earthen dam faced with rock rip-rap *405 by the U.S. Army Engineers, the letting to be held June 15, 1965, at Omaha, Nebraska. Most of the negotiations were conducted between Marnel Lindekugel for plaintiff and Robert Brezina for defendant, the first of which were in the spring of 1965 when Lindekugel 1 called Brezina and expressed interest in the 'two companies submitting a joint venture bid. Lindekugel had prior rock rip-rap experience on other dams. After learning some North Dakota company had tied up the rock sources in that area, Lindekugel advised Brezina he was not in a position to give a competitive bid on the rock and so was not interested in the joint venture, but would give the best price it could as a prospective subcontractor. The two met at Omaha where they discussed the matter and Lindekugel orally gave Brezina some figures on the rip-rap and concrete work with the understanding he would give exact figures before noon the 15th. Brezina asked Lindekugel if he was bidding the rock to any other contractor, was advised he was not but was bidding exclusively with Brezina, whereupon Brezina said he would use Lindekugel's bid in his bidding. On the morning of the 15th Hamann, another employee of Lindekugel, at its direction submitted a handwritten exclusive or "closed" quote or bid as it is described in the briefs. It was dated June 15, 1965, was $200,000 more than the oral figure and Brezina over the telephone expressed his dissatisfaction with the figure without indicating Lindekugel would have the contract if the United States accepted Brezina's bid. This handwritten Lindekugel bid totaled $1,288,580; it included cement, steel and rock rip-rap. Defendant was the successful bidder; its contract with the United States contained a provision for "value engineering". The latter provision allowed a contractor to suggest different methods of performing the contract which, if approved, split the savings between the United States and the contractor.

On August 2, at Pierre, South Dakota, plaintiff's brief relates "Lindekugel prepared a subcontract for Brezina to sign according to the terms of his closed quote to Brezina." It was type *406 written and while dated June 15th was not in accord with the "closed" quote for it totaled $1,032,891.40 and omitted items 6 and 11 through 19. This Lindekugel proposal contained a signature line for acceptance by Brezina who refused to sign it as he was exploring use of soil cement for rock rip-rap under the value engineering clause.

On August 12th, George and Marnel Lindekugel met at Brezina's office in Rapid City, South Dakota, with a letter and a new quotation, offer or proposal #3 which, under the value engineering clause, used a soil cement method rather than rock rip-rap. It was dated August 12, 1965 and totaled $909,723.96. It also contained a place for Brezina's acceptance. Marnel Lindekugel testified he told Brezina they had brought three proposals with them to "try to * * * fit in with his proposal for value engineering with us doing the work * * * He (Brezina) said, well, he was not prepared, at that time, to sign anything". This testimony will be mentioned later.

By letter of September 17th Lindekugel notified Brezina it was preparing to send equipment to the project site in a few days. The Brezina reply dated September 23rd stated "We have no subcontract agreement with your organization * * * We reiterate that until such time as a subcontract is negotiated .between us, if any, we can accept no obligation to you." On October 25th Lindekugel wrote Brezina "Since you deny that any agreement exists * * * we find it necessary as of this date to withdraw any offers made at the time of the letting, 15 June 1965 or any offers subsequent to that date."

Marnel Lindekugel testified he talked to Robert Brezina over the phone on October 26th and Brezina told him the Engineers had said the value engineering (soil cement method) was not acceptable which put him in poor shape. "I said, 'Maybe we can still work it out, if you would send me my contract,' and he said, * * * T would like to wait until I get it (engineer's official word) in writing.'" Lindekugel further testified Brezina called him on November 2nd saying "he would like to go ahead with the rock arrangement, and I said, 'Well, Bob,' I said, *407 'if you will send me a contract, we can go ahead with it,' and I said, 'I will withdraw my letter of the 25th.' (There was some discussion of bond costs) 'Bob, if that's all there is standing between us,' I said, 'include the deduct in the contract, and send me the subcontract, and I will sign it, and we will go to work,' and he said, 'It will be in the mail today.' " Lindekugel also testified he sent a letter to Brezina dated November 4th wherein he said "we are withdrawing our letter mailed to you on 25 October 1965. * * * we are willing to proceed with our original agreement. * * * We would, however, appreciate your subcontract on this matter at the very earliest". Defendant never signed or sent an acceptance of any of the subcontracts to plaintiff. The trial court directed a verdict for defendant and plaintiff appealed from the judgment thereon.

There seems to be some confusion of the issue or issues on appeal. Plaintiff's complaint contained two counts. Count One alleged the parties had entered into a contract on or before June 14, 1965 and this contract was breached by Brezina prior to October 25, 1965. Plaintiff at the trial introduced evidence that it was a custom in the contracting business in South Dakota that when a subcontractor gave a "closed" quote to a prime contractor, the latter would give the subcontract to the subcontractor at the figure quoted. Plaintiff-appellant's brief, under a title "Custom And Usage" quotes this testimony and then under Questions Presented By Assignments Of Error, Point I "first contends that a good and valid contract was entered into between the parties on the 15th day of June in Omaha upon the Defendant being awarded the prime contract", yet after referring to its later actions, the brief continues: "By the acts of these parties such contract was totally vitiated." Then under Point II plaintiff asserts "No one could possibly contend that either of the parties could have enforced the contract of the 15th (sometimes mentioned as the 14th) of June." Later argument is made however under Point III that the June 15th quote was a closed quote and under Point IV that it bound defendant. Defendant's contract with the United States also prevented the start of the embankment operations until July 1, 1966, more than a year later and defendant's answer included the defense of the Statute of Frauds. *408 The trial court mainly relied on this defense in directing the verdict for defendant. See SDC 10.0605(1) and Brown v. Wisconsin Granite Co., 47 S.D. 635, 201 N.W. 555. Plaintiff-appellant's brief is generally directed to the questions of the Statute of Frauds, part performance and custom and usage under Count One.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weitzel v. Sioux Valley Heart Partners
2006 SD 45 (South Dakota Supreme Court, 2006)
Setliff v. Akins
2000 SD 124 (South Dakota Supreme Court, 2000)
Williams v. Denham
162 N.W.2d 285 (South Dakota Supreme Court, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
160 N.W.2d 121, 83 S.D. 404, 1968 S.D. LEXIS 117, Counsel Stack Legal Research, https://law.counselstack.com/opinion/g-h-lindekugel-sons-inc-v-brezina-construction-co-sd-1968.