G. D. Womack Trenching, Inc. v. Maitland Water System, Inc.

CourtLouisiana Court of Appeal
DecidedApril 7, 2004
DocketCA-0003-1579
StatusUnknown

This text of G. D. Womack Trenching, Inc. v. Maitland Water System, Inc. (G. D. Womack Trenching, Inc. v. Maitland Water System, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
G. D. Womack Trenching, Inc. v. Maitland Water System, Inc., (La. Ct. App. 2004).

Opinion

STATE OF LOUISIANA COURT OF APPEAL, THIRD CIRCUIT

03-1579

G. D. WOMACK TRENCHING, INC.

VERSUS

MAITLAND WATER SYSTEM, INC., ET AL.

**********

APPEAL FROM THE SEVENTH JUDICIAL DISTRICT COURT PARISH OF CATAHOULA, NO. 22,666 HONORABLE KATHY A. JOHNSON, DISTRICT JUDGE

ELIZABETH A. PICKETT JUDGE

Court composed of Jimmie C. Peters, Marc T. Amy, and Elizabeth A. Pickett, Judges.

AFFIRMED.

Sam O. Henry, III Blackwell, Chambliss, Henry, Caldwell, Cagle & Camp, LLP P. O. Box 1829 West Monroe, LA 71294-1829 (318) 388-1000 Counsel for Defendant/Appellant: Jabar Corporation

Virgil Russell Purvis, Jr. Smith, Taliaferro, Purvis & Boothe P.O. Box 277 Jonesville, LA 71343 (318) 339-8526 Counsel for Defendant/Appellant: Maitland Water System, Inc.

George Trippe Hawthorne Kean, Miller, Hawthorne, D’Armond, McCowan & Jarman P.O. Box 3513 Baton Rouge, LA 70821-3513 (225) 387-0999 Counsel for Plaintiff/Appellee: G. D. Womack Trenching, Inc. PICKETT, Judge.

Maitland Water System, Inc., appeals the judgment of the trial court which

withdrew the award of a public contract to Jabar Corporation and awarded the contract

to G. D. Womack Trenching, Inc. Jabar also appeals this judgment.

FACTS

Maitland Water Systems, Inc. (Maitland), a public corporation, was required

to move some of its water lines because the Louisiana Department of Transportation

and Development (DOTD) planned to widen Louisiana Highway 15 from Sicily Island

to the Concordia Parish line. Maitland and DOTD entered into a contract regarding

the relocation of the lines. Maitland was responsible for doing the work, DOTD was

to pay for the work, and all plans had to be coordinated and approved by DOTD

through its project engineer, James Free. Maitland retained McManus Consulting

Engineers (McManus) to oversee the preparation for the project, including soliciting

bids for work related to the relocation of the water lines. One of the elements of the

project involved digging a trench, placing pipe, and backfilling the trench.

McManus advertised the right to bid on the project in September 2002. The Bid

Form, which had been sent to DOTD for approval in June 2002, included a Base Bid

and an Additive Alternative No. 1. The Base Bid included all phases of the project.

The Alternate Bid was included because in the areas within the road’s right of way,

it was contemplated that the trenches could not simply be backfilled with the dirt

originally removed from the trench but had to be filled with select backfill. The

alternate bid form suggested that 3,650 cubic yards of backfill would have to be

removed, disposed of, and replaced with select backfill. The bid form asked for a unit

price per cubic yard for this work.

1 The bids were opened on October 8, 2002, by Max Larche of McManus. The

total amount of the bids was as follows:

Contractor Base Bid Alternative No. 1 Total Womack $212,218.00 $21,900.00 $239,118.00 KCS Construction $235,192.40 $34,675.00 $269,867.40 Camo Construction $256,018.80 $35,587.50 $291,606.30 Jabar $197,926.71 $87,602.00 $285,528.71

While Jabar had the lowest Base Bid, its bid for Alternative No. 1 was at a rate

of $4.00 per cubic yard for disposal of backfill and $20.00 per cubic yard for select

fill. Since Womack’s bid for Alternative No. 1 was at a rate of $1.00 for disposal of

backfill and $5.00 for select fill, its total bid price was lower.

On October 11, 2002, Larche sent the bid tabulation sheet and Jabar’s low Base

Bid to John Tyler of DOTD. After reviewing the bid sheets, Tyler called Larche and

told him that the project did not require 3,650 cubic yards of backfill to be replaced

with select fill because select fill would only have to be used where the water line

crossed the road. After speaking with Tyler, Larche reviewed the plans and

determined that no more than 140 cubic yards of backfill would have to be disposed

of and replaced with select fill. On October 24, 2002, Larche recalculated the total

amounts of the bids, changing only the quantity for the Alternative No.1. The result

was as follows:

Contractor Base Bid Alternative No. 1 Total Womack $212,218.00 $890.00 $218,058.00 KCS Construction $235,192.40 $1330.00 $236,522.40 Camo Construction $256,018.80 $1365.00 $256,383.80 Jabar $197,926.71 $3360.00 $201,286.71

Following this recalculation, it was determined that Jabar was the lowest bidder.

McManus recommended to Maitland that the contract be awarded to Jabar. DOTD

approved, and the contract was awarded to Jabar. The other bidders, including

2 Womack, were given notice that Jabar had been awarded the contract on November

18, 2002.

Representatives of Jabar, McManus, and Maitland met to discuss the project on

January 9, 2003. On January 14, because DOTD requested that a stop work order

issue because of delays in clearing and grubbing, a stop work order was issued by

McManus. The letter from Larche to Jabar specifically stated that Jabar should

continue ordering materials for the project. On April 11, 2003, Jabar sent an invoice

to DOTD for pipe that it had purchased for the project and was stockpiling at the

Maitland office.

On May 5, 2003, Womack filed a petition against Maitland and Jabar to enjoin

performance of the contract between Maitland and Jabar and to declare the contract

illegal and void. Womack claimed that its bid was the lowest bid and that Maitland

engaged in post-bid manipulation that made Jabar’s bid the lowest bid. Womack also

sought an order declaring it to be the lowest bidder and awarding it the contract. The

trial court issued a Temporary Restraining Order on May 5, 2003.

Maitland and Jabar answered the petition, asserting that the bid was not

manipulated for the purpose of awarding Jabar the bid. Maitland claimed it had the

authority by the terms of the bid itself to modify the alternate bid to conform to the

work requirements of DOTD. Maitland and Jabar also claimed that Womack’s suit

was untimely and that the delay of six months before filing suit constituted waiver of

objection. The trial court held a hearing on May 29, 2003, which the parties stipulated

would constitute trial of the preliminary and permanent injunctions and all other

issues.

The trial court issued a written ruling on August 23, 2003. The trial court ruled

that the reduction of the quantities in the alternate bid was a violation of La.R.S.

3 38:2212. The trial court further found that the bid form, reserving to Maitland the

right to decrease quantities, did not allow Maitland to recalculate the bid using lower

quantities for the alternate bid. The trial court further found that Womack’s suit was

not untimely. The trial court declared the contract between Maitland and Jabar null

and void and ordered Maitland to award the contract to Womack. Finally, the trial

court authorized Maitland to issue a change order allowing it to purchase the pipe

Jabar had stockpiled and deducting that from the contract awarded to Womack. A

judgment to that effect was signed on September 8, 2003. Maitland and Jabar now

appeal that ruling.

ASSIGNMENTS OF ERROR

Maitland asserts three assignments of error:

1. The Trial Court erred in its conclusion under the undisputed facts that the recalculation of the alternative bids and the award to Jabar violated La.R.S. 38:2212.

2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Airline Const. v. Ascension Parish School Board
568 So. 2d 1029 (Supreme Court of Louisiana, 1990)
Haughton Elevator Division v. STATE, ETC.
367 So. 2d 1161 (Supreme Court of Louisiana, 1979)
Gray v. State Ex Rel. Department of Highways
202 So. 2d 24 (Supreme Court of Louisiana, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
G. D. Womack Trenching, Inc. v. Maitland Water System, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/g-d-womack-trenching-inc-v-maitland-water-system-inc-lactapp-2004.