G. C. Buildings, Inc. v. RGS Contractors, Inc.

Court of Appeals of Texas·Decided October 13, 2014·No. 05-13-00151-CV·Published

Opinion

AFFIRMED; Opinion Filed October 13, 2014.

S In The

Court of Appeals

Fifth District of Texas at Dallas No. 05-13-00151-CV

G.C. BUILDINGS, INC., Appellant V.

RGS CONTRACTORS, INC., Appellee

On Appeal from the 191st Judicial District Court Dallas County, Texas

Trial Court Cause No. DC-03-04559-J

MEMORANDUM OPINION

Before Justices Francis, Lang-Miers, and Myers Opinion by Justice Myers

G.C. Buildings, Inc. appeals the trial court’s judgment that it take nothing on its claims

against RGS Contractors, Inc. for breach of contract following a trial before the court. Appellant brings four issues on appeal contending (1) appellant provided evidence on each element of its contract cause of action and there was no contrary evidence; (2) appellant is not estopped from pursuing damages; (3) appellant did not assign its claims to the United States Department of Housing and Urban Development (HUD); and (4) certain of the trial court’s “findings” were not proper findings of fact. We affirm the trial court’s judgment.

BACKGROUND

In 1997, appellant hired appellee to build an apartment complex on property owned by appellant in Oklahoma. The project was financed by a $7 million loan from GMAC Commercial Mortgage, and that loan was insured by HUD. The contract called for completion of work by

February 1, 1999. Due to a fire, the parties extended the completion date to May 4, 2000. Although the buildings were substantially completed and possession was turned over to appellant by June 8, 2000, there was an extensive punch list of problems with the individual units that prevented most of them from being leased. The contract provided that the date of final completion was “the date the HUD representative signs the final HUD Representative’s Trip Report.” The final trip report was signed on October 12, 2000, 161 days after May 4.

From May to December 2000, appellant made monthly (and occasionally bimonthly)

interest payments on the loan, averaging about $46,520 per month and totaling $372,156.14. Appellant’s income from rentals was $1,500 in June 2000 and by August 2000 had risen to $9,000. Appellant’s chief financial officer testified that if all the apartments had been rentable in May 2000, the rental income would have been $77,400 per month. In January 2000, appellant defaulted on the loan and abandoned the property to GMAC and HUD.

The contract between appellant and appellee contained a liquidated-damages provision stating that if the construction was not completed timely, the amount appellee would be paid under the contract

shall be reduced by $2,101.68, as liquidated damages, for each day of delay until the date of final completion. When the Owner cost certifies to HUD, the actual cost of interest, taxes, insurance, mortgage insurance premiums, and construction and permanent loan extension fees, as approved by the Commissioner, for the period from the scheduled date of completion through the date construction was actually completed, shall be determined. The lesser of the liquidated or actual damages shall be applied.

Appellant did not certify to HUD “the cost of interest, taxes, insurance, mortgage insurance premiums, and construction and permanent loan extension fees . . . from the scheduled date of completion through the date construction was actually completed.” Instead, appellant approved appellee being paid with no deduction for actual or liquidated damages for the delay.

In May 2003, appellant brought suit against appellee, alleging appellee breached the contract by not finally completing construction by May 4, 2000. Appellant sought “liquidated damages of $2,101.68 per day for each day of delay until final completion or the actual cost of interest, taxes, insurance, mortgage insurance premiums and extension fees, whichever is less.” Alternatively, appellant sought “its actual damages based on the General Conditions and applicable common law.”

During trial, appellant presented evidence that it made interest payments after May 4, 2000 on the loan of $372,156.14. Appellant calculated the amount of liquidated damages as $338,370.48. Appellant’s chief financial officer testified appellant would have had to make the interest payments regardless of whether the project was timely completed. The trial court concluded that appellant “has failed . . . to establish a proper measure of damages against” appellee.”

DAMAGES

In its first issue, appellant contends it “provided evidence on each element of its contract cause of action and there was no contrary evidence.” We interpret appellant’s issue as contending that appellant proved its breach-of-contract cause of action as a matter of law, and that the trial court’s determination that appellant did not prove its cause of action was against the great weight and preponderance of the evidence.

When reviewing a trial court’s findings of fact and conclusions of law for legal and factual sufficiency, we apply the same standards used in reviewing the evidence supporting jury findings. Catalina v. Blasdel, 881 S.W.2d 295, 297 (Tex. 1994). When an appellant attacks the legal sufficiency of the evidence to support an issue on which the appellant had the burden of proof, the appellant must show the evidence establishes, as a matter of law, all vital facts in support of the issue. Dow Chem. Co. v. Francis, 46 S.W.3d 237, 241 (Tex. 2001). In reviewing

a “matter of law” challenge, we first examine the record for evidence supporting the finding, and then examine the entire record to determine if the contrary proposition is established as a matter of law. Id. We sustain the point of error only if the contrary proposition is conclusively established. Id.

When a party attacks the factual sufficiency of an adverse finding, it must demonstrate the adverse finding is against the great weight and preponderance of the evidence. Id. at 242. We must consider and weigh all of the evidence and can set aside the finding only if the evidence is so weak or if the finding is so against the great weight and preponderance of the evidence that it is clearly wrong and unjust. Id.

One of the elements of a claim for breach of contract that appellant had the burden of proving is that the breach of the contract caused appellant’s damages. See Marquis Acquisitions, Inc. v. Steadfast Ins. Co., 409 S.W.3d 808, 813 (Tex. App.—Dallas 2013, no pet.) (elements of breach of contract are “(1) a valid contract; (2) performance or tendered performance by the plaintiff; (3) breach of the contract by the defendant; and (4) damages sustained by the plaintiff as a result of the breach.”). To recover damages for breach of contract, appellant had to prove it suffered some pecuniary loss as a result of the breach. S. Elec. Servs., Inc. v. City of Hous., 355 S.W.3d 319, 324 (Tex. App.—Houston [1st Dist.] 2011, pet. denied). The “losses must be the natural, probable, and foreseeable consequence of the defendant’s conduct.” Id. (citing Mead v. Johnson Group, Inc., 615 S.W.2d 685, 687 (Tex. 1981)). The absence of a causal connection between the alleged breach and the damages sought will preclude recovery. Id.

In its brief on appeal, appellant argues it

submitted evidence based on an out of pocket measure of damages premised on its interest payments prior to final completion and ending when it abandoned the project. Those amounts are set forth in GCB exhibits 8 and 9 and aggregate $372,156.14. Alternatively, GCB submitted evidence of liquidated damages of $338,370.48 per Article 2E [sic] of the Construction Contract.

Appellant’s chief financial officer testified that appellant had to make those interest payments regardless of whether the apartments were timely completed:

Q. After May [4, 2000], you were already obligated to make interest payments under the mortgage, were you not?

A. Yes.

....

Q. GCB would have been making interest payments to GMAC regardless of how many apartments were available for occupancy, correct?

A. Yes, we have a commitment to pay GMAC for the money we borrowed from them.

....

Free access — add to your briefcase to read the full text and ask questions with AI

G. C. Buildings, Inc. v. RGS Contractors, Inc., (Tex. Ct. App. 2014).

G. C. Buildings, Inc. v. RGS Contractors, Inc. (G. C. Buildings, Inc. v. RGS Contractors, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Dow Chemical Co. v. Francis
46 S.W.3d 237 (Texas Supreme Court, 2001)
In Re Office of Attorney General of Texas
264 S.W.3d 800 (Court of Appeals of Texas, 2008)
Catalina v. Blasdel
881 S.W.2d 295 (Texas Supreme Court, 1994)
Mead v. Johnson Group, Inc.
615 S.W.2d 685 (Texas Supreme Court, 1981)
Nikolai v. Strate
922 S.W.2d 229 (Court of Appeals of Texas, 1996)
Southern Electrical Services, Inc. v. City of Houston
355 S.W.3d 319 (Court of Appeals of Texas, 2011)
Marquis Acquisition, Inc. v. Steadfast Insurance Company and Julie Fry
409 S.W.3d 808 (Court of Appeals of Texas, 2013)