Fulton v. Des Jardins

227 P.2d 240, 67 Wyo. 517, 1951 Wyo. LEXIS 38
CourtWyoming Supreme Court
DecidedFebruary 6, 1951
Docket2482
StatusPublished
Cited by10 cases

This text of 227 P.2d 240 (Fulton v. Des Jardins) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fulton v. Des Jardins, 227 P.2d 240, 67 Wyo. 517, 1951 Wyo. LEXIS 38 (Wyo. 1951).

Opinion

*523 OPINION

Blume, Justice.

This is an action brought by Stuart T. Fulton against Sam Des Jardins and Thurston Block Plant, Inc., a corporation. Sam Des Jardins made default and judgment was entered against him. A judgment for $461.50 in favor of plaintiff was rendered against Thurston Block Plant, and it was enjoined as asked in the petition. From that judgment the corporation has appealed to this court.

The plaintiff in his petition alleged that he was the original contractor upon a contract for construction for the State of Wyoming of a new livestock building at the Wyoming State Fair Grounds in Douglas, Wyoming. Under that contract he agreed to pay all labor for material used in the construction. Plaintiff further alleged that on June 11,1949 the two defendants jointly agreed with the plaintiff to furnish 10,571 concrete blocks and the labor for laying the same, required for the walls of the said building, together with cement blocks and labor for laying the same for 94 windows in the building requiring 12 blocks each, the blocks to be furnished at the rate of 44% cents per block, making a total contract price of $5003.96; that defendants dealt jointly with the plaintiff and made no agreement with respect to their separate interests; that it is the custom in the building trade in the Casper area of which Douglas is a part, that payments on the joint contract price for labor and blocks be made to the person on the job in charge of the receiving and laying of the same; that plaintiff paid Des Jardins the sum of $3400 on and before July 8, 1949; that on July 16 plaintiff advanced for labor to workmen the sum of $781.46 and that on July 18, 1949 he paid to the Thurston Block Plant, Inc., a corporation, *524 the sum of $1100, making a total so paid the sum of $5281.46; that these payments made to the defendant Des Jardins were made to him upon the express representation that he had the authority to receive the same for and on account of said contract for settlement between the defendants; that in addition to that he has incurred a liability of $184 for two workmen, namely Elmer Johnson and Robert Lundgren, for labor per-file a lien against the plaintiff and the building and the bondsmen of the plaintiff; that defendant Thurston bondsme nof the plaintiff; that defendant Thurston Block Plant, Inc., claims that there is due it, the sum of $1014.40, which is not true, and it should be and was asked to be enjoined from filing any claim with the State of Wyoming for this amount of money. Plaintiff asked for an accounting, and claimed the sum of $277.50 as overpayment on the cause of action above mentioned, and the sum of $241.90 upon another cause of action. This last cause of action, however, was disallowed by the court and plaintiff has not appealed in that connection. The defendant filed an answer denying the allegations of plaintiff except the allegation in reference to the contract with the State of Wyoming, and filed a cross-petition claiming that there is due it the sum of $1014.20 for 10,571 concrete blocks furnished at the rate of 20 cents for the construction of the building above mentioned.

The plaintiff testified that Thurston, president and manager of appellant, called him up on the telephone. That in that conversation he, Fulton, told Thurston that he was trying to get a price for cement blocks and labor. Thurston suggested that he knew a man — the defendant Des Jardins — whom he thought to be a good brickmason, and wanted to know if he, Fulton, would be interested in meeting them. The meeting was arranged and took place at Douglas. Plaintiff testifed *525 that: “I made it very definite to them (meaning both defendants) that I figured my job on the basis of blocks in the wall.” Later “I called Mr. Thurston and asked him if he thought they (meaning both defendants) would consider a price of 44% cents (per block), if they would take the job and labor at 44% cents that I would make an agreement to that effect.” Thurston stated that he would get into communication with Des Jardins. In addition, plaintiff wrote a letter to Thurston in which he “told him that the letter was to confirm what we had talked on over the phone; that I would agree to pay them (meaning both defendants) 44% cents a block for the blocks in the wall.” The letter was not in evidence, but Thurston admitted receiving it, and that he had turned it over to Des Jardins. The latter called plaintiff, stating that “they” would do the job for 44% cents a block in the wall. Plaintiff was, to a large extent, corroborated by Mrs. Fulton; and Thurston admitted on the witness stand that the combined price for the material and labor was to be 44% cents per block in the wall. That he accepted the offered contract is shown by the fact that the material was delivered. He denied, however, any joint liability with Des Jardins, but claimed that he was to receive 20 cents per block for the material. To resolve any conflict in the evidence was under many decisions of this court for the trial court and with its finding we cannot interfere. Hence, since the trial court found in favor of plaintiff, we must either consider the contract as creating a joint liability, as the trial court held, or, which is perhaps better in view of the fact that Thurston found and dealt with Des Jardins —that Thurston undertook to deliver the material and employed Des Jardins as his agent to put the blocks in the wall. The matter is not of the importance attributed to it by counsel, as may be noted by the discussion below, though consistent therewith.

*526 Appellant pleaded in a reply filed in the case as follows : “That said plaintiff dealt with this defendant corporation through an agent of said corporation, and that said agent was not authorized to make any agreement to ‘jointly’ furnish material and labor with said Des Jardins.” And counsel further contends that a corporation is engaged only in the manufacture and sale of cement blocks and, consequently, has no power whatever to enter into a contract involving responsibility for laying the blocks in the wall. Thurston testified as follows:

“Q. And are you an officer of the Thurston Block Plant, Inc.?
“A. Yes, sir, I am president of the corporation.
“Q. What is your authority as president of the corporation?
“A. As president of the corporation I have authority to call all corporation meetings which involve policy or change of policy, which is my responsibility to call meetings for such, and to operate as general manager of the Thurston Block Plant.
“Q. And in what business is Thurston Block Plant engaged ?
“A. We are in the business of producing and selling blocks.
“Q. Do you in your business go into partnership with people who buy blocks to lay them for other people ? “A. We do not.
“Q. Do you have any facilities, such as supervisors or managers or foremen to handle such business ?
“A. We have not.”

Plaintiff did not plead that the contract entered into by the appellant was ultra vires. It is said in 19 C. J. S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moncrief v. Williston Basin Interstate Pipeline Co.
880 F. Supp. 1495 (D. Wyoming, 1995)
Christensen v. Oedekoven
888 P.2d 228 (Wyoming Supreme Court, 1995)
Gaub v. Simpson
866 P.2d 765 (Wyoming Supreme Court, 1993)
Prenalta Corp. v. Colorado Interstate Gas Co.
944 F.2d 677 (Tenth Circuit, 1991)
Compass Insurance Co. v. Cravens, Dargan & Co.
748 P.2d 724 (Wyoming Supreme Court, 1988)
Commercial Union Insurance Co. v. Postin
610 P.2d 984 (Wyoming Supreme Court, 1980)
System Terminal Corporation v. Cornelison
364 P.2d 91 (Wyoming Supreme Court, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
227 P.2d 240, 67 Wyo. 517, 1951 Wyo. LEXIS 38, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fulton-v-des-jardins-wyo-1951.