Ft. Worth & D. C. Ry. Co. v. Read Bros. & Montgomery

154 S.W. 1027, 1913 Tex. App. LEXIS 329
CourtCourt of Appeals of Texas
DecidedFebruary 1, 1913
StatusPublished
Cited by8 cases

This text of 154 S.W. 1027 (Ft. Worth & D. C. Ry. Co. v. Read Bros. & Montgomery) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ft. Worth & D. C. Ry. Co. v. Read Bros. & Montgomery, 154 S.W. 1027, 1913 Tex. App. LEXIS 329 (Tex. Ct. App. 1913).

Opinion

DUNKLIN, J.

The Ft. Worth & Denver •City Railway Company has appealed from a judgment in favor of S. R. Bourgeois foreclosing an alleged lien upon a spur track belonging to appellant, under and by virtue of the provisions of article 5640, Revised Statutes 1911, for work performed with tools and teams upon the spur track.

The railway company let the contract for the construction of said spur track to Read Bros. & Montgomery, who employed Bourgeois to do the work upon which his claim for lien was predicated. The jury made findings in ahswer to 45 interrogatories submitted to them, consisting chiefly of questions -of evidence rather than controlling issues in the case, and many of which are substantial duplicates of others, and these findings were supplemented by several additional findings by the trial judge. The suit was instituted "by Read Bros. & Montgomery against the ■railway company to recover the balance due for the entire work done under the contract, and Bourgeois intervened," praying judgment against the plaintiffs for the balance of $1,-136.83, due him from the contractors, and for a lien to secure the same, upon the spur track, against the railway company for such balance.

At a previous trial judgment was rendered in favor of the intervener against the plaintiffs for $1,276, with a foreclosure of lien against the railway company for $1,179 of that amount. From that judgment, an appeal was prosecuted by the railway company to the Court of Civil Appeals at Texarkana, resulting in a reversal of the foreclosure against the railway company, but leaving the judgment in favor of the intervener against the plaintiffs undisturbed; no appeal having been prosecuted from that part of the judgment. The opinion rendered upon that appeal is reported in 140 S. W. 111.

The trial from which this appeal is perfected was between the intérvener and the railway company alone. The jury found in favor of the intervener for the following items of account against the contractors, which were alleged in his petition:

Moving 6,000 yds. of dirt..$ 720 00
1,000 yds. of rock. 700’ 00
Four teams with men and tools on miles 3 and 4... 120 00
Clearing and grubbing 2.87 acres of land on mile 4 at $30.00 per acre. 86 10
Overhaul of dirt filling washout on mile 4.. 100 00
Hire of 8 teams and tools for 44 days working on mile 9 at $1 per day per team. 352 00
Tickets and freight charges. 25 41
Groceries returned... 62 00
$2,165 51

It was proven beyond controversy that the item of $352 was for the hire of intervener’s teams and tools by the contractors after in-tervener had completed the work undertaken by him and had discharged his employés, and that during the time the contractors used the teams and tools under this contract of hiring plaintiff did. not work with them; nor did he furnish any one to do so.

The jury found that the contractors "paid intervener $1,092.58 for the work done by him on the spur track prior to the time he hired his teams to the contractors, leaving a balance of $1,072.93 owing upon that work, which became due intervener January 1, 1908; that out of the amount paid to inter-vener $714 was paid out to his employés in full for labor performed by them before they were discharged; and the evidence conclusively shows, with no finding of the jury to the contrary, that the items for tickets, freight, and groceries were in fact paid by the contractors and charged to intervener’s account as advancements while the work done by intervener was in progress. The jury further found that the balance owing by the contractors represents only reasonable wages earned by the intervener by the use of his teams and tools, and by his own personal labor in working on the spur track and in superintending the work of his men *1029 while they were working on the spur track; and that intervener realized no profit from the labor of his men in excess of the amount paid them for their services, nor from his own labor and the use of his teams and tools over and above the reasonable value thereof. The jury further found that, while said work was being done by his men and by the use of his teams and tools, intervener superintended the work as foreman and worked with his men, either by laboring thereon himself, or by working in the blacksmith shop and procuring supplies for the use of his men and teams, or by acting as foreman of his men and in superintending the work while they were engaged in constructing the grade; but the jury were unable to determine what portion of the time intervener worked with his men, teams, and tools directly upon the grade and how much of the time he devoted to working in his blacksmith shop, and in and about his camp and procuring necessary supplies for the use of his men and teams and for the repair of his tools. However, they further found that the work which intervener performed in and about the camp and while going after supplies for his men and teams, while they were engaged in working on the grade, was necessary for the proper prosecution of said work.

The trial court held that intervener was not entitled to a lien for the item of $352 for the hire of his teams, but deducted that item from $1,072.93, the balance found to be due, and rendered judgment in favor of the intervener for a lien on the spur track for $720.93, the difference between the two sums last named, with 6 per cent, interest thereon from January 1, 190S

[1] By its first assignment apellant insists that the evidence did not show such a state of facts as entitled intervener to a foreclosure of lien for any amount; and that the court erred in refusing a requested peremptory instruction directing a verdict for the defendant. Upon the former appeal the Court of Civil Appeals held, in effect, that, if appellee merely superintended the work and realized a profit from the work over and above the reasonable value of the labor employed and of the use of his teams and tools, he was a subcontractor, and not a laborer, within the meaning of the statute above referred to. Invoking that decision, appellant insists that it was conclusively shown that intervener was a subcontractor under Read Bros. & Montgomery, for that the evidence shows, without controversy, that plaintiff made a profit out of his work, which profit is included in the principal of the judgment rendered. The jury found that 42 days of work were performed upon the track from the time intervener began work until the time he hired his teams to the contractors; and that the reasonable market value of the use of the teams and tools used was $2.25 per day per team. The jury did not find how many teams were employed; but inter-vener testified, without contradiction, that he used eight teams during the entire time the work was in progress. Intervener also testified that he had on an average of ten men employed, and paid them $1.75 per day each; and that his own services were worth $4 per day.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southwestern Dredging Corp. v. Chicago, R. I. & P. R. Co.
1934 OK 257 (Supreme Court of Oklahoma, 1934)
McLendon Hardware Co. v. Black
264 S.W. 1011 (Court of Appeals of Texas, 1924)
Gerlach v. North Texas &. S. F. Ry. Co.
244 S.W. 662 (Court of Appeals of Texas, 1922)
Hales v. San Antonio, Uvalde & Gulf Railroad
238 S.W. 1106 (Texas Supreme Court, 1922)
San Antonio, U. & G. R. Co. v. Hales
196 S.W. 903 (Court of Appeals of Texas, 1917)
Kansas City Southern R. Co. v. Reinman
1917 OK 55 (Supreme Court of Oklahoma, 1917)
Texas Bldg. Co. v. Collins
187 S.W. 404 (Court of Appeals of Texas, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
154 S.W. 1027, 1913 Tex. App. LEXIS 329, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ft-worth-d-c-ry-co-v-read-bros-montgomery-texapp-1913.