Friends of the Payette v. Horseshoe Bend Hydroelectric Co.

811 F. Supp. 524, 1992 U.S. Dist. LEXIS 20619, 1992 WL 420809
CourtDistrict Court, D. Idaho
DecidedJune 25, 1992
DocketNo. CIV 92-0135-S-MJC
StatusPublished

This text of 811 F. Supp. 524 (Friends of the Payette v. Horseshoe Bend Hydroelectric Co.) is published on Counsel Stack Legal Research, covering District Court, D. Idaho primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Friends of the Payette v. Horseshoe Bend Hydroelectric Co., 811 F. Supp. 524, 1992 U.S. Dist. LEXIS 20619, 1992 WL 420809 (D. Idaho 1992).

Opinion

MEMORANDUM DECISION

CALLISTER, Senior District Judge.

INTRODUCTION

Clean energy and wilderness preservation are typically harmonious goals. To preserve lakes and forests, we reduce the acid rain produced by coal-fired power plants; to protect the land and future generations from radioactive waste, we ban nuclear power. Unfortunately, however, there are times when the production of clean energy compromises wilderness values, and this case presents such a circumstance: By borrowing the power of a river, a hydroelectric facility runs clean, but inevitably affects the sweep of water within its reach. Are we forced by this circumstance to trade one environmental goal for another, to “choose” between pollution-free energy and river habitat? We need both. Can we get there?

Clean energy is not free. If we want to depend on charitable efforts to reduce pollution, our patience would outlast our existence. Utilities and developers must be allowed a financial return to solve these pollution problems. But a developer must be prepared to give up some of that financial return to eliminate or mitigate environmental damage caused by the clean energy project. How large should the financial reparation be? That decision has been taken away from the developer and handed over to various state and federal agencies for resolution. In some cases the damage to the environment is so great, and the required mitigation so expensive, that the project is rightly doomed. But in the case now before the Court, the project owners have absorbed substantial extra costs imposed by the governmental agencies to ameliorate environmental damage. These federal and state agencies have now fully examined the project and given their approval.

The plaintiffs basically assert that the governmental agencies have not gone far enough in requiring the project owners to mitigate environmental damage. In this lawsuit, the Court is called upon to determine whether the decision of the agencies allowing the project to go forward is reasonable.

OVERVIEW OF THIS CASE

The plaintiffs — Friends of the Payette and Idaho Rivers United, Inc. — brought this action to challenge a decision by the Army Corps of Engineers (Corps) to issue a permit under § 404 of the Clean Water Act (CWA), 33 U.S.C. § 1344. This § 404 permit was the last of a string of permits the defendant Horseshoe Bend Hydroelectric Company (HBHC) was required to obtain to construct a hydroelectric power project on the Payette River. The project will divert water from the Payette River through a power house before returning the water to the river. The § 404 permit allows HBHC to place dredged or fill material in the river.

To determine whether the § 404 permit was properly issued, this Court is guided by two important considerations. First, although the Corps itself did not hold a public hearing, it did solicit and receive a large volume of written public comments on the project which are part of the record reviewed by this Court. Second, this is an appeal from a decision by the Corps, and this Court has no authority to independently review the facts or re-open the case for [526]*526public comment except under limited circumstances not present here.

With these considerations in mind, the Court will turn to the facts of this case, followed by a procedural history of the litigation and a discussion of the governing legal principles.

FACTS

The North and South Forks of the Payette River charge out of narrow, boulder-choked canyons to come together a few miles above the town of Horseshoe Bend. As it enters town, the river calms and forms a lazy curve that gives the town its name.

A scenic river like the Payette needs protection, and the Idaho legislature provided a measure of it in 1991 by ratifying the Comprehensive State Water Plan for the Payette River Reaches adopted by the Idaho Water Resource Board. Idaho Session Laws, ch. 221 (1991). This plan offers substantial protection for the North and South Forks, and the Main Fork to a section just upstream from Horseshoe Bend. The one stretch of river left unprotected is the section this hydropower facility will affect. But the give-and-take that brought life to the Payette River Plan, and allowed HBHC’s project to remain, did not affect the many regulatory approvals HBHC had to secure before it could proceed with construction.

This regulatory approval process began in 1983 when HBHC’s predecessor-in-interest, Boise Cascade Corporation, first applied for the necessary permits from both federal and state agencies. The project as proposed then, and as it still exists today, will divert water from the Payette River by means of an inflatable bladder diversion dam, and send the water down a three-and-one-half mile diversion canal to a power house. After passing over the power house turbines, the water will be returned to the Payette River via a tailrace. The project is being built at the location of a similar hydropower plant operated from 1902 until 1954. This has lessened the environmental impacts of the project because HBHC did not need to cut a new swath for the canal but could simply widen the existing one.

During operation, the project will divert up to 3,500 cubic feet per second (cfs) of water through the power canal, bypassing a four-and-one-half mile stretch of river. The diversion dam will be operated to maintain at least 400 cfs in the bypassed stretch. On the basis of historical data, it is expected that the flows will greatly exceed 400 cfs in the bypassed stretch between April and July, but will be lowered to 400 cfs between August and March. Record at 187.

The de-watering of the bypassed stretch forms the core of plaintiffs’ complaint. It is projected that flows in, say, August and September, that might normally measure 3,500 cfs, will drop to 400 cfs in the bypassed stretch. These complaints will be discussed in more detail later in this opinion.

To build the diversion dam, HBHC needed a permit from the Federal Energy Regulatory Commission (FERC). FERC completed an Environmental Assessment on August 7, 1984, and a supplemental Environmental Assessment on April 1, 1986. These Environmental Assessments concluded that the project would have no significant impact on the environment. FERC approved the project on June 30, 1986, and issued its license, which included thirty-nine specific conditions designed to reduce environmental harm. Record at 49. Idaho Power Company appealed FERC’s decision to the D.C. Court of Appeals on the ground that Idaho Power Company was being improperly required to purchase the electricity generated by the project. No other party appealed. The D.C. Court of Appeals disagreed with Idaho Power Company’s complaints and affirmed FERC's decision to grant a license for the project. Idaho Power Company v. FERC, 865 F.2d 1313 (D.C.Cir.1989).

HBHC thereafter obtained the necessary state permits. On May 21, 1991, the Idaho Department of Water Resources granted a water rights permit; on March 13, 1992, the Idaho Department of Environmental Quality issued a water quality certificate; [527]*527and on January 13, 1992, the Idaho Department of Lands issued a permit granting HBHC access to submerged state lands for construction purposes.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thomas v. Peterson
753 F.2d 754 (Ninth Circuit, 1985)
Conner v. Burford
848 F.2d 1441 (Ninth Circuit, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
811 F. Supp. 524, 1992 U.S. Dist. LEXIS 20619, 1992 WL 420809, Counsel Stack Legal Research, https://law.counselstack.com/opinion/friends-of-the-payette-v-horseshoe-bend-hydroelectric-co-idd-1992.