Friends of the Earth, Inc. v. Coleman

518 F.2d 323, 8 ERC 1617
Court of Appeals for the Ninth Circuit·Decided May 28, 1975·No. No. 74-3490·Published·Cited by 42 cases

Opinion

OPINION

Before MERRILL, WRIGHT and TRASK, Circuit Judges.

EUGENE A. WRIGHT, Circuit Judge:

This is an appeal from an order denying in part appellants’ motion for preliminary injunction. On April 10, 1975, we issued an order affirming the district [326]*326court, and vacating the temporary injunction pending appeal granted by this court January 22, 1975. We now consider the facts and legal principles on which that order was based.

This suit began as one for injunctive and declaratory relief against alleged noneompliance with the environmental impact statement [EIS] requirements of § 102(2)(C) of the National Environmental Policy Act [NEPA] [42 U.S.C. § 4321 et seq. (1970)]. Appellants sought to halt further implementation of an expansion and development plan for constructing additional facilities and upgrading existing ones at the San Francisco International Airport until a satisfactory EIS was submitted.

On November 11, 1974, the district court granted in part and denied in part appellants’ request for preliminary injunction. We affirm that order.

FACTS:

In 1970, appellee Airports Commission approved a revised and enlarged expansion program for airport development. It was to proceed in phases, to double present airport passenger capacity by 1985, at an estimated cost of $398 million.

The FAA, with its regulatory authority over design and layout of the airport and over construction plans which alter the design and layout, had reviewed and approved layout plans for the expansion program from time to time since the program’s adoption, most recently in November of 1973. Such approval is required before federal funds for airport development and expansion may be granted. [Airport and Airway Development Act, 49 U.S.C. § 1716 (1970)].

When suit was filed, contracts had been let or work was under way on several expansion program projects. Those as to which no federal funds had been or could be allocated included a new north terminal, the first stage of which was under construction when suit was brought, and a five-story parking garage for which bids had been sought. Once the district court had ruled, appellee Airports Commission entered into additional contracts for construction of the garage foundation and the superstructure of the terminal.

Other expansion program projects had been approved for assistance under the federal Airport Development Aid Program (ADAP) or were awaiting approval. One of them, the expansion and reconstruction of the airport access road, had already been completed and others, involving various forms of runway improvement, were well under way. Federal funding was also anticipated at the time of this action for construction of additional aircraft aprons and a new control tower. In all, grants totaling $14 million had already been approved, and the total federal contribution might well be expected to reach $38 million by the time the development plan was completed.

In the district court, appellants sought to stop all work on expansion program projects until an EIS had been submitted. They claimed that the approved and anticipated federal assistance rendered the entire program a federal-state joint venture subject to NEPA evaluation.

The district court enjoined further approval or commitment of federal funds for eligible airport development projects “unless and until such request for aid is accompanied by a draft [EIS] on the overall development plan of the Airport.” The court refused to enjoin further awards of contracts or construction of the parking garage and north terminal projects. Since it found that “such projects do not involve significant adverse environmental effects, but merely are related to and necessary for maintenance of the present use of the Airport within its existing size and purpose,” the court did not consider whether their nonfederal funding would also insulate them from the requirements of NEPA.

Appellants contend that the district court’s finding on the environmental impact of the north terminal and parking garage projects is clearly erroneous, and [327]*327that an injunction should have been granted as to these projects as well. We agree that the finding lacks support in the record, but we uphold the denial of preliminary relief as to these projects because of the absence of federal participation in the challenged projects.

In reviewing the denial of interlocutory relief, we need only determine whether the district court abused its discretion. See Ross-Whitney Corp. v. Smith Kline & French Laboratories, 207 F.2d 190 (9th Cir. 1953).

Among the factors to be weighed in determining the propriety of a preliminary injunction are the probability of ultimate success on the merits, the relative importance of the rights asserted, the nature of the acts to be enjoined, the hardship to each party that would result pendente lite from granting or denying interlocutory relief, and the public interest. King v. Saddleback Jr. Coll. Dist., 425 F.2d 426 (9th Cir. 1970). We have considered all factors, and cannot say that the district court’s refusal to stop work on the north terminal and parking garage amounted to an abuse of discretion.

A. LIKELIHOOD OF SUCCESS ON THE MERITS.

NEPA requires federal agencies to provide a detailed environmental impact statement on “major Federal actions significantly affecting the quality of the human environment.” [42 U.S.C. § 4332(2)(C)]. The statement should be prepared at the earliest time prior to implementation of the proposed action, so that alternative courses of action with less severe environmental consequences can be considered. [Council on Environmental Quality, Guidelines for Preparation of Environmental Impact Stateaments, 40 C.F.R. § 1500.2(a) (1974).]

Appellees have not challenged the district court’s determination that environmental impact statements were required for the federally funded projects in the airport expansion program. Nor have they pointed to any facts to support the finding that the state-funded north terminal and parking garage projects will have no significant environmental effect. Instead, they concede, and we agree, that the uncontradicted evidence at trial indicates the outgrowth of the Airport Development Plan involves a substantial increase in air passenger and vehicular traffic at the airport. Thus the denial of an interlocutory injunction as to these projects was based on an unsubstantiated and erroneous finding of fact.

For an action to be subject to NEPA, however, it must be shown to be “federal.” Nothing in this record indicates that either the terminal or parking garage projects would be eligible for federal funds. We also conclude that the state-funded projects are not so closely interwoven with those receiving federal funds to make the entire airport development program the relevant “action” for NEPA purposes.

Free access — add to your briefcase to read the full text and ask questions with AI

Friends of the Earth, Inc. v. Coleman, 518 F.2d 323, 8 ERC 1617 (9th Cir. 1975).

518 F.2d 323 (Friends of the Earth, Inc. v. Coleman) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Cascadia Wildlands v. Williams
251 F. Supp. 3d 1349 (D. Oregon, 2017)
Sancho v. U.S. Department of Energy
578 F. Supp. 2d 1258 (D. Hawaii, 2008)
Don Laub Debbie Jacobsen Ted Sheely California Farm Bureau Federation v. United States Department of the Interior Gale A. Norton, Secretary, Department of the Interior United States Environmental Protection Agency Marianne Horinko, in Her Official Capacity as Acting Administrator of the U.S. Epa Department of the Army, (Civil Works) Joseph W. Westphal, Dr., in His Official Capacity as Assistant Secretary of the Army (Civil Works) Donald Evans, in His Official Capacity as Secretary, U.S. Department of Commerce United States Department of Commerce U.S. Department of Agriculture Ann M. Veneman, in Her Official Capacity as Secretary, U.S. Department of Agriculture U.S. Army Corps of Engineers Peter T. Madsen, Brigadier General, in His Official Capacity as Commander, South Pacific Division, U.S. Army Corps of Engineers Natural Resources Conservation Service Charles Bell, in His Capacity as California State Conservationist, U.S. Department of Agriculture, Natural Resources Conservation Service National Marine Fisheries Service Rebecca Lent, Dr., Regional Administrator, National Marine Fisheries Service U.S. Fish & Wildlife Service Stephen Thompson, in His Official Capacity as Manager of California-Nevada Operations of the U.S. Fish & Wildlife Service United States Bureau of Reclamation Kirk C. Rodgers, in His Official Capacity as Director, Mid-Pacific Region of the U.S. Bureau of Reclamation Gray Davis, Governor of the State of California California Resources Agency Mary D. Nichols, in Her Official Capacity as Secretary of the California Resources Agency California Environmental Protection Agency Winston Hickox, in His Official Capacity as Secretary of the California Environmental Protection Agency
342 F.3d 1080 (Ninth Circuit, 2003)
Ka Makani `O Kohala Ohana Inc. v. Water Supply
295 F.3d 955 (Ninth Circuit, 2002)
Churchill County v. Gale A. Norton
276 F.3d 1060 (Ninth Circuit, 2001)
Michaels v. Internet Entertainment Group, Inc.
5 F. Supp. 2d 823 (C.D. California, 1998)
Berecart of. Department of Trans.
133 F.3d 926 (Ninth Circuit, 1998)
Lakes Region Legal Defense Fund, Inc. v. Slater
986 F. Supp. 1169 (N.D. Iowa, 1997)
The Fund For Animals, Inc. v. Lujan
962 F.2d 1391 (Ninth Circuit, 1992)
CENTRAL ARIZONA IRR. AND DRAINAGE DIST. v. Lujan
764 F. Supp. 582 (D. Arizona, 1991)
Sylvester v. U.S. Army Corps Of Engineers
882 F.2d 407 (Ninth Circuit, 1989)
MacHt v. Skinner
715 F. Supp. 1131 (District of Columbia, 1989)
Sierra Club v. Hodel
675 F. Supp. 594 (D. Utah, 1987)