Friends of Mitchell Field v. Town of Harpswell
This text of Friends of Mitchell Field v. Town of Harpswell (Friends of Mitchell Field v. Town of Harpswell) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
STATE OF MAINE SUPERIOR COURT
Cumberland, ss . Civil Action
FRIENDS OF MITCHELL FIELD ) ) Plaintiff ) ) V. ) Docket No. PORSC-CV-18-0334 ) TOWN OF HARPSWELL ) STl'-TE OF MAl~~E ~ ) Cumberland, ss. Clerk's Of1,ce Defendant ) c;_;:-':> G5 2Di8 ) ~#-~ ' " " l \ '· \ '? E' I""' '
DECISION AND JUDGMENT RECE\VED
This case is about a municipal water tower that has become a lightning rod of
contention in the Town of Harpswell after five years of discussion and study about its
future. One viewpoint is that the tower represents the best prospect for improved
cellular telephone reception in many parts of the Town, and that it can repaired,
repurposed and maintained at a reasonable cost at little or no expense to the Town
The other viewpoint is that it is an unsafe structure, that it is beyond repair at a
reasonable cost, that it is not optimal for cellular telephone purposes, and it that should
be demolished.
At a Town meeting in March 2018, the proponents of demolition prevailed in a
vote and the tower is scheduled to come down in a couple of weeks. This case reflects
an effort by proponents of saving the tower to stop the demolition and get another
Town vote on the future of the tower.
1 The case came before the court for an evidentiary hearing August 28, 2018.
Plaintiff Friends of Mitchell Field and Defendant Town of Harpswell both
participated with counsel and presented evidence through witness testimony and
exhibits. The hearing was electronically recorded.
Prior to the hearing, the parties filed a written stipulation of facts, which is
reproduced below in the paragraphs numbered 1 through 95. In addition, the parties
stipulated to the admission of 73 exhibits. 1 Additional exhibits were admitted during
the hearing.
The August 28, 2018 hearing was initially scheduled for purposes of Plaintiff
Friends of Mitchell Field's Motion for Preliminary Injunction, but, as set forth below,
the parties stipulated to consolidate hearing on the Motion with a hearing on the
merits "provided that both parties are able to get substantially all of their evidence in
at the hearing." See Stipulations ef Fact ~ l, infra. At oral argument, both parties
confirmed that they were able to complete their presentation of evidence and rested at
the close of the hearing. Accordingly, this Decision represents a final, appealable
judgment in this case.
Oral argument was held August 31, 2018, at which point the court took the case
under advisement. Based on the entire record, the court makes the following findings
of fact and adopts the analysis and conclusions oflaw set forth below.
1. Exhibits 8, 9, 10, 11 and Ht were incorrectly labeled and located in the court's exhibit book. The exhibit numbers on those exhibits have been corrected to be consistent with the above index, and the exhibits have been placed behind the correct number tabs in the court's book. 2 Stipulated Facts
The parties stipulated to the facts set forth in the following paragraphs I
through 95, without stipulating to any particular fact's relevance or significance:
I. The parties agree to consolidate the hearing on Plaintiffs Motion for
Preliminary Injunction with a hearing on the merits of the Verified Complaint
pursuant to M.R. Civ. P. 65(b)(92), provided that both parties are able to get
substantially all of their evidence in at the hearing.
2. Mitchell Field is a 118.5-acre former U.S. Navy site m the Town of
Harpswell ("Town") that has been owned by the Town since 2001.
3. Mitchell Field is the site of some old buildings and other site improvements
built by the U.S. Navy when it owned the site, including a water tower constructed by
the U .S. Navy around 1950 that is no longer in use.
4. The Mitchell Field water tower is located on one of the highest points of
land in South Harpswell.
5. Cell phone coverage is limited or not available in the South Harpswell, Orr's
Island and Bailey Island sections of Town and is spotty in other parts of Town,
including areas near the Mitchell Field Water Tower.
6. The Town of Harpswell follows a town meeting form of government. It is
governed by a three-member Board of Selectmen ("Board"). I ts legislative body is the
town meeting.
3 7. Richard Daniel has been the Chair of the Board continuously since March
27, 2014. Kevin Johnson has been a Board member since March 15, 2014. David
Chipman was elected to the Board on March 11, 2017.
8. FMF was incorporated as a non-profit entity on February 23, 2018. FMF
has no members and 3 to 9 directors. Exhibit 45 (Articles oflncorporation).
9. At the March 9, 2013 Annual Town Meeting, the voters defeated Article 38.
Exhibit 2 (March 2013 Annual Town Meeting Warrant and Results).
10. On July 1, 2014, Utility Service Group ("USG") performed a Condition
Assessment on the water tower for the Town and submitted a Report. Exhibit 3 (USG
Report).
11. September 6, 2014 email sent from Scott Kelley of USG to the Town
Administrator. Exhibit 4 ( email).
12. September 19, 2014 email sent by the Town Administrator to Scott Kelley
of USG. Exhibit 5 (email).
13. September 22, 2014 email sent by Scott Kelley of USG to the Town
Administrator. Exhibit 6 ( email).
14. At its January 14, 2016 meeting, the Board initially proposed putting an
article on the 2016 Town Meeting Warrant to spend $22,000 to demolish the water
tower. Exhibit 8 (Board Meeting Minutes).
15. At the January 28, 2016 Board meeting, David Chipman (who was not on
the Board at the time) asked the Board to add an article to the 2016 Town Meeting
4 Warrant to keep the tower. He was advised to present a proposed article. See Exhibit
9 (Board Meeting Minutes).
16. On or about February 22, 2016, a citizen's petition with 323 valid
signatures was presented to Town Clerk Rosalind Knight to add an article to the 2016
Town Meeting Warrant. Exhibit 11 (Letter from Town Clerk to Board dated
February 22, 2016).
17. On February 23, 2016, Preferred Tank & Tower of Henderson, Kentucky
provided the Town Treasurer, Marguerite Kelly, with a $75,000 quote to dismantle
the water tower. Exhibit 10 (Letter from Preferred Tank & Tower to Marguerite
Kelly dated February 23, 2016).
18. In its February 23, 2016 letter, Preferred Tank & Tower also provided the
Town with a quote to repair and renovate the water tower. See Exhibit 10 (Letter
from Preferred Tank & Tower to Marguerite Kelly dated February 23, 2016).
19. On March 1, 2016, Preferred Tank & Tower provided the Town with a
quote to repair and renovate the water tower based on full encapsulation. See Exhibit
12 (Quote from Preferred Tank & Tower to Marguerite Kelly dated March 1, 2016).
20. On or about March 2, 2016, a meeting was held at the Town office with
Board Chair Rick Daniel, Town Administrator Kristi Eiane, David Chipman, and
Dorothy Rosenberg to discuss revision of articles dealing with the water tower for
2016 Town Meeting Warrant. As a result, in addition to the citizen's petition article,
which remained on the warrant as Article 35, the Board of Selectmen placed Article
34 on the warrant. Exhibit 14 (2016 Annual Town Meeting Warrant and Results).
5 21.
Free access — add to your briefcase to read the full text and ask questions with AI
STATE OF MAINE SUPERIOR COURT
Cumberland, ss . Civil Action
FRIENDS OF MITCHELL FIELD ) ) Plaintiff ) ) V. ) Docket No. PORSC-CV-18-0334 ) TOWN OF HARPSWELL ) STl'-TE OF MAl~~E ~ ) Cumberland, ss. Clerk's Of1,ce Defendant ) c;_;:-':> G5 2Di8 ) ~#-~ ' " " l \ '· \ '? E' I""' '
DECISION AND JUDGMENT RECE\VED
This case is about a municipal water tower that has become a lightning rod of
contention in the Town of Harpswell after five years of discussion and study about its
future. One viewpoint is that the tower represents the best prospect for improved
cellular telephone reception in many parts of the Town, and that it can repaired,
repurposed and maintained at a reasonable cost at little or no expense to the Town
The other viewpoint is that it is an unsafe structure, that it is beyond repair at a
reasonable cost, that it is not optimal for cellular telephone purposes, and it that should
be demolished.
At a Town meeting in March 2018, the proponents of demolition prevailed in a
vote and the tower is scheduled to come down in a couple of weeks. This case reflects
an effort by proponents of saving the tower to stop the demolition and get another
Town vote on the future of the tower.
1 The case came before the court for an evidentiary hearing August 28, 2018.
Plaintiff Friends of Mitchell Field and Defendant Town of Harpswell both
participated with counsel and presented evidence through witness testimony and
exhibits. The hearing was electronically recorded.
Prior to the hearing, the parties filed a written stipulation of facts, which is
reproduced below in the paragraphs numbered 1 through 95. In addition, the parties
stipulated to the admission of 73 exhibits. 1 Additional exhibits were admitted during
the hearing.
The August 28, 2018 hearing was initially scheduled for purposes of Plaintiff
Friends of Mitchell Field's Motion for Preliminary Injunction, but, as set forth below,
the parties stipulated to consolidate hearing on the Motion with a hearing on the
merits "provided that both parties are able to get substantially all of their evidence in
at the hearing." See Stipulations ef Fact ~ l, infra. At oral argument, both parties
confirmed that they were able to complete their presentation of evidence and rested at
the close of the hearing. Accordingly, this Decision represents a final, appealable
judgment in this case.
Oral argument was held August 31, 2018, at which point the court took the case
under advisement. Based on the entire record, the court makes the following findings
of fact and adopts the analysis and conclusions oflaw set forth below.
1. Exhibits 8, 9, 10, 11 and Ht were incorrectly labeled and located in the court's exhibit book. The exhibit numbers on those exhibits have been corrected to be consistent with the above index, and the exhibits have been placed behind the correct number tabs in the court's book. 2 Stipulated Facts
The parties stipulated to the facts set forth in the following paragraphs I
through 95, without stipulating to any particular fact's relevance or significance:
I. The parties agree to consolidate the hearing on Plaintiffs Motion for
Preliminary Injunction with a hearing on the merits of the Verified Complaint
pursuant to M.R. Civ. P. 65(b)(92), provided that both parties are able to get
substantially all of their evidence in at the hearing.
2. Mitchell Field is a 118.5-acre former U.S. Navy site m the Town of
Harpswell ("Town") that has been owned by the Town since 2001.
3. Mitchell Field is the site of some old buildings and other site improvements
built by the U.S. Navy when it owned the site, including a water tower constructed by
the U .S. Navy around 1950 that is no longer in use.
4. The Mitchell Field water tower is located on one of the highest points of
land in South Harpswell.
5. Cell phone coverage is limited or not available in the South Harpswell, Orr's
Island and Bailey Island sections of Town and is spotty in other parts of Town,
including areas near the Mitchell Field Water Tower.
6. The Town of Harpswell follows a town meeting form of government. It is
governed by a three-member Board of Selectmen ("Board"). I ts legislative body is the
town meeting.
3 7. Richard Daniel has been the Chair of the Board continuously since March
27, 2014. Kevin Johnson has been a Board member since March 15, 2014. David
Chipman was elected to the Board on March 11, 2017.
8. FMF was incorporated as a non-profit entity on February 23, 2018. FMF
has no members and 3 to 9 directors. Exhibit 45 (Articles oflncorporation).
9. At the March 9, 2013 Annual Town Meeting, the voters defeated Article 38.
Exhibit 2 (March 2013 Annual Town Meeting Warrant and Results).
10. On July 1, 2014, Utility Service Group ("USG") performed a Condition
Assessment on the water tower for the Town and submitted a Report. Exhibit 3 (USG
Report).
11. September 6, 2014 email sent from Scott Kelley of USG to the Town
Administrator. Exhibit 4 ( email).
12. September 19, 2014 email sent by the Town Administrator to Scott Kelley
of USG. Exhibit 5 (email).
13. September 22, 2014 email sent by Scott Kelley of USG to the Town
Administrator. Exhibit 6 ( email).
14. At its January 14, 2016 meeting, the Board initially proposed putting an
article on the 2016 Town Meeting Warrant to spend $22,000 to demolish the water
tower. Exhibit 8 (Board Meeting Minutes).
15. At the January 28, 2016 Board meeting, David Chipman (who was not on
the Board at the time) asked the Board to add an article to the 2016 Town Meeting
4 Warrant to keep the tower. He was advised to present a proposed article. See Exhibit
9 (Board Meeting Minutes).
16. On or about February 22, 2016, a citizen's petition with 323 valid
signatures was presented to Town Clerk Rosalind Knight to add an article to the 2016
Town Meeting Warrant. Exhibit 11 (Letter from Town Clerk to Board dated
February 22, 2016).
17. On February 23, 2016, Preferred Tank & Tower of Henderson, Kentucky
provided the Town Treasurer, Marguerite Kelly, with a $75,000 quote to dismantle
the water tower. Exhibit 10 (Letter from Preferred Tank & Tower to Marguerite
Kelly dated February 23, 2016).
18. In its February 23, 2016 letter, Preferred Tank & Tower also provided the
Town with a quote to repair and renovate the water tower. See Exhibit 10 (Letter
from Preferred Tank & Tower to Marguerite Kelly dated February 23, 2016).
19. On March 1, 2016, Preferred Tank & Tower provided the Town with a
quote to repair and renovate the water tower based on full encapsulation. See Exhibit
12 (Quote from Preferred Tank & Tower to Marguerite Kelly dated March 1, 2016).
20. On or about March 2, 2016, a meeting was held at the Town office with
Board Chair Rick Daniel, Town Administrator Kristi Eiane, David Chipman, and
Dorothy Rosenberg to discuss revision of articles dealing with the water tower for
2016 Town Meeting Warrant. As a result, in addition to the citizen's petition article,
which remained on the warrant as Article 35, the Board of Selectmen placed Article
34 on the warrant. Exhibit 14 (2016 Annual Town Meeting Warrant and Results).
5 21. March 12, 2016: The 2016 Town Meeting approved Article 34, and
Article 35 was passed over. Exhibit 14 (2016 Annual Town Meeting Warrant and
Results).
22. On March 31, 2016, the Board voted to create a Water Tower Task Force
("WTTF") and adopted a specific charge for the WTTF's work. ("WTTF Charge").
Exhibit 15 (Board Meeting Minutes); Exhibit 16 (WTTF Charge).
23. On March 31, 2016, the Board appointed a WTTF Chair and four other
members to the WTTF. Exhibit 15 (Board Meeting Minutes).
24. The Chair of the WTTF was Board member Elinor Multer. The following
individuals were also appointed to the WTTF: Jim Knight, Nelson Barter, David
Chipman, and Dorothy Rosenberg. The Board also appointed two alternate members
of the WTTF: David Mercier and Donnette Goodenow. Exhibit 15 (Board Meeting
Minutes).
25. The WTTF held its first meeting on April 26, 2016. Exhibit 17 (WTTF
Meeting Minutes).
26. Steve Cox, Director of Engineering and Maine Water Company, attended
the May 17, 2016 WTTF meeting to provide information regarding the water tower.
Exhibit 18 (WTTF Meeting Minutes).
27. At a WTTF meeting held on September 6, 2016, David Libby, owner of
Communication Facilities, Inc. ("CFI"), made an informal presentation to the WTTF
on the possible use of the Mitchell Field water tower as a communications facility.
Exhibit 20 (WTTF Meeting Minutes).
6 28. On October 14, 2016, Town Planner Mark Eyerman prepared a
Communication Facilities Memo ("2016 CF Memo") and presented it to the WTTF
at their October 18, 2016 meeting. Exhibit 21 (Communications Facilities Memo,
dated October 14, 2016); Exhibit 22 (WTTF Meeting Minutes).
29. At its October 18, 2016 meeting and after discussion of the 2016
Communications Facilities Memo, the WTTF voted to issue an RFP for a water tower
communications site manager. Exhibit 22 (WTTF Meeting Minutes).
SO. At the October 18, 2016 WTTF meeting, the Task Force voted to
recommend to the Board that the Town contract with engineering firm Woodard and
Curran to, among other things, "assess the condition of the water tower to determine
if anything needs to be done on an interim basis to stabilize the tower for .3 to 5 years
while potential use of the tower as a communications facility is investigated further."
Exhibit 16 (WTTF Meeting Minutes) .
.31. On or about November 7, 2016, the Town issued an RFP to solicit
proposals for a water tower communications site manager ("2016 Town RFP").
Exhibit 24 (2016 Town RFP).
.32. On November 28, 2016, Northern Pride Communications, Inc. ("NPCI")
submitted its proposal for Water Tower Communications Site Manager in response
to the 2016 Town RFP. Exhibit 25 (NPCI response).
SS. On November 25, 2016, CFI submitted its proposal for Water Tower
Communications Site Manager in response to the 2016 Town RFP. Exhibit 26 (CFI
response).
7 34. At its December 6, 2016 meeting, the WTTF discussed scheduling
interviews for water tower communications site managers and reviewed a preliminary
list of questions to be asked of the two firms and reviewed a preliminary draft of the
Woodard & Curran report on cost comparison of options for water provision on
Mitchell Field. All Task Force members were given the opportunity to craft questions
for these interviews. See Exhibit 27 (WTTF Meeting Minutes).
3 5. March 20 1 7: Woodard & Curran prepared a Mitchell Field Water Tower
Assessment report for the Town. Exhibit 29 (Woodard & Curran Report).
36. March 11, 2017: The 2017 Town Meeting approved Article 35A. Exhibit
30 (Annual Town Meeting Warrant and Results).
37. The 2017 Town Meeting elected David Chipman to be on the Board to
replace retiring Elinor Multer. Exhibit 30 (Annual Town Meeting Warrant and
38. The Board appointed Board Chairman Richard Daniel to replace Elinor
Multer as the Chairman ofthe WTTF on March 15, 2017. Exhibit 31 (Board Meeting
39. At the March 29, 2017 WTTF meeting, the WTTF reviewed Woodard &
Curran's final report. Exhibit 33 (WTTF Meeting Minutes).
40. The water tower communication site manager interviews were scheduled
by Town Treasurer Marguerite Kelly. Exhibit 34 (Email exchange between
Marguerite Kelly and Dorothy Rosenberg dated March 30-31, 2017).
8 41. Interviews with CFI and NPCI applicants for the water tower
communications site manager were conducted on April 7, 2017. The interview
committee consisted of the WTTF Chair Richard Daniel, Town Administrator Kristi
Eiane, Town Treasurer Marguerite Kelly and Town Planner Mark Eyerman. Exhibit
27 (WTTF Meeting Minutes of Dec. 6, 2016); Exhibit 40 (WTTF Meeting Minutes
of April 18, 2017). David Chipman was present for a portion of the interviews.
42. On April 1.3, 2017, the Board appointed Ned Simmons to replace David
Mercier as an alternate member of the WTTF. Exhibit 36 (Board Meeting Minutes).
43. At a WTTF meeting on April 18, 2017, Town Treasurer Marguerite Kelly
and Town Planner Mark Eyerman reported on the interviews with communications
facility site managers. See Exhibit 37 (WTTF Meeting Minutes).
44. On or about April 10, 2017, NPCI revised its proposal by email. Exhibit
35 (Email to Marguerite Kelly).
45. On or about April 10, 2017, CFI withdrew its proposal after re-considering
the site, the recent engineering reports and potential carrier concerns. Exhibit 35
(Email to Marguerite Kelly).
46. The $10,000 approved in Article 35A at the 2017 Town Meeting was
never expended by the Town.
47. At the WTTF meeting held on May 23, 2017, Marguerite Kelly presented
the Task Force with a spreadsheet she had prepared laying out the various cost
estimates for the rehabilitation of the water tower. The Task Force agreed to
9 postpone making any recommendations until additional information could be
gathered. Exhibit .38 (WTTF Meeting Minutes, including attached spreadsheet).
48. At the September 12, 2017 meeting of the WTTF, Task Force member
David Chipman reported that he was "moving forward with the formation of a non
profit organization to raise money for renovation of the water tower. Exhibit .39
(WTTF Meeting Minutes).
49. The WTTF held its last substantive meeting on October 20, 2017. At the
request of Task Force Chair Richard Daniel, recommendations discussed by the Task
Force were drafted by Town Planner Mark Eyerman and read aloud at the meeting.
Exhibit 40 (WTTF Meeting Minutes).
50. At its last meeting held on October 20, 2017, the WTTF voted 5-0 to place
two articles on the warrant for March 2018 town meeting: one to seek proposals from
entities to rehabilitate and manage the water tower, and the other to move forward
with the demolition of the water tower and raise and appropriate not more than
$40,000 for that purpose if the first article did not pass. Exhibit 40 (WTTF Meeting
5 I. Town Planner Mark Eyerman made a brief presentation to the Board at
its December 14, 2017 meeting summarizing the WTTF recommendation of placing
two articles on the warrant for the March 2018 Town Meeting. See Exhibit 41 (Board
52. On January 2.3, 2018, the Board held a workshop with three members of
the WTTF (Jim Knight, Dorothy Rosenberg and Ned Simmons)-, to refine the details 10 of a draft of the Request for Expressions of Interest to maintain and manage the water
tower for future Town uses. Robert McIntyre attended as an observer.
53. On January 25, 2018, the WTTF held its last meeting to approve the
minutes of the October 20, 2017 meeting. On that same day, the Board voted 2-0 to
dissolve the WTTF (Daniel and Chipman participating). Exhibit 42 (Board Meeting
54. On January 25, 2018, the Board issued a public Request for Expressions of
Interest and/or Proposals to Lease the Water Tower ("2018 Town RFP") revised to
incorporate suggestions from the January 23, 2018 workshop meeting. Exhibit 43
(2018 Town RFP).
55. On February 8, 2018, the Board placed Articles 29 and 30 on the 2018
Town Meeting Warrant as recommended by the WTTF. Exhibit 44 (Annual Town
Meeting Warrant and Results); Exhibit 54 (Board Meeting Minutes).
56. Lincoln/Haney Engineering Associates, Inc. prepared a report on the
water tower for FMF dated February 23, 2018. Exhibit 46 (Lincoln/Haney Report).
57. On February 26, 2018 FMF submitted multiple copies the February 26,
2018 Expression of Interest ("FMF Original Proposal") to the Town in response to
the 2018 Town RFP. See Exhibit 47 (FMF Original Proposal).
58. The FMF Original Proposal was the only response to the 2018 Town RFP
received by the Town.
59. The Board held a public workshop on Tuesday, March 6, 2018. The
primary purpose of the workshop was for the Board and others to gain a better
11 understanding ofthe proposal submitted by FMF in response to the 2018 Town RFP.
The Town invited FMF representatives to attend to discuss and answer questions
about the FMF Proposal. The Town also invited the Mitchell Field Committee to
send a representative to the workshop. Exhibit 49 (Email from Kristi Eiane to Board
members and Town staff, dated March 2, 2018). Robert McIntyre and John Ott
attended the workshop on behalf of FMF.
60. The Board's March 6, 2018 workshop was open to the public and noticed
to the public in advance of the workshop. Exhibit 49 (Email from Kristi Eiane to
Board, dated March 2, 2018).
61. Immediately following the conclusion of the March 6th Board workshop,
Robert McIntyre approached Town Administrator and asked her ifFMF could bring
a document to the Town Meeting for review by voters. Exhibit 50 ("The March 6
FMF Document"). Ms. Eiane told Mr. McIntyre that she would check into it and let
FMF know if the document could be distributed.
62. Town Administrator Kristi Eiane placed a phone call to the
McIntyre/Rosenberg residence on Friday, March 9, 2018 and spoke to Dorothy
Rosenberg, confirming that the March 6 FMF Document could be distributed at the
63. On Wednesday, March 7, 2018, Robert McIntyre, came into the town
office, accompanied by Hope Hilton, and gave Ms. Eiane a thumb drive and asked that
the FMF Proposal, which FMF had revised slightly following the Board workshop,
be posted on the Town's website. The thumb drive contained a Word version of the
12 revised FMF Proposal, entitled "Expressiions [sic] oflnterest By Friends of Mitchell
Field 26 February 2018." ("Corrected FMF Proposal") which was posted by town staff
on the town website that day. Exhibit 51 (Corrected FMF Proposal). This document
was removed from the town website after the March 10, 2018 Town Meeting.
64. At the March 10, 2018 Town Meeting, FMF was not allowed to place
written materials on the table near the door where voters entered on which official
Town documents are distributed.
65. Town staff directed FMF to place its written materials at a different table
at the Town meeting.
66. At the March 10, 2018 Town Meeting, the Moderator read Articles 29 and
30 aloud to the meeting. After each Article was moved and seconded, the Moderator
opened the floor to discussion of both Articles at the same time. Exhibit 52
(Transcript 2018 Town Meeting Discussion).
67. The Moderator presided over an open floor debate and discussion of
Articles 29 and 30 which continued for approximately one hour and 10 minutes.
Exhibit 52 (Transcript 2018 Town Meeting Discussion). The Moderator limited no
one who wished to speak during the discussion of the two articles .
68 . During the discussion of Articles 29 and 30 at the 2018 Town Meeting,
Robert McIntyre pointed out to the Town Meeting that written material describing
who FMF is was available on the different table at the Town Meeting. Mr. McIntyre
asked the moderator ifhe could "simply read that one page and then sit down." After
13 the moderator gave him permission to do so, he read a prepared statement aloud.
Exhibit 62 (Transcript 2018 Town Meeting Discussion).
69. The March 10, 2018 Town Meeting rejected Article 29 and approved
Article 30, which authorized demolition of the water tower. Exhibit 62 (Transcript
2018 Town Meeting Discussion); Exhibit 63 (Annual Town Meeting Warrant and
70. In April 2018, the Town had Katahdin Analytical Services perform
additional lead testing of the water tower lower legs and surrounding soil to provide
a baseline prior to demolition of the water tower. Exhibit 64 (Katahdin Analytical
Services report).
71. At a Board meeting held on April 19, 2018, Dorothy Rosenberg informed
the Board that a citizens' petition was being circulated to overturn the March 10, 2018
Town Meeting vote. See Exhibit 66 (Board Meeting Minutes).
72. On or about April 20, 2018, the Town issued a Request for Proposals to
Demolish the Water Tower at Mitchell Field (the "Demolition RFP"). Exhibit 66
(Demolition RFP).
73. On April 23, 2018, Dorothy Rosenberg sent an email to the Board, Town
Planner, and Town Administrator, and on April 24, Town Administrator Kristi Eiane
sent an email reply. Exhibit 67 (Email D. Rosenberg to Board, K. Eiane, and M.
Eyerman with attachments); Exhibit 59 (Email K. Eiane to D. Rosenberg with
attachments).
14 74. On April 23, 2018, Dorothy Rosenberg sent an email to the Town
Administrator. Exhibit 58 (Email D. Rosenberg to K. Eiane).
75. On or about April 26, 2018, a citizens' petition signed by 351 registered
voters, including FMF board members ("Citizens"), was submitted to the Town
requesting a secret ballot vote to repeal the 2018 Town Meeting vote approving
Article 30 and to authorize the Board to enter into an agreement with FMF to manage,
maintain and repair the water tower (the "Citizens' Petition"). Exhibit 60 (Citizens'
Petition).
76. In a letter dated April 30, 2018, the Town Clerk certified to the Board that
the 351 valid signatures of registered voters on the Citizens' Petition exceeded the
307 signature requirement to call a Special Town Meeting. Exhibit 61 (Town Clerk
letter to Board).
77. The Board rejected the Citizens' Petition after considerable discussion at
its May 2, 2018 meeting. Exhibit 62 (Board Meeting Minutes).
78. At FMF's direction, Maine Environmental Laboratory on or about May
24, 2018 tested paint samples reported by Robert McIntyre to be from the water
tower. Exhibit 66 (FMF Request to Board with Maine Environmental Laboratory
Report) .
79. At its May 9, 2018 meeting, the Board adopted written findings of fact and
made a written decision supporting its rejection of the Citizens' Petition after
consulting with the Town attorney. Exhibit 64 (Board Findings and Decision).
15 80. At the May 9, 2018 Board meeting, Robert McIntyre, on behalf ofFMF,
submitted a written request to the Board asking the Town Attorney to meet with
FMF legal representative. Exhibit 63 (FMF Request to Board).
81. On July 26, 2018, the Board awarded the demolition contract to Iseler
Demolition, Inc. from Romeo, Michigan ("Iseler"). Exhibit 73 (Iseler Contract).
82. On or about June 6, 2018, FMF board members Dorothy Rosenberg and
John Ott met with Town Administrator Kristi Eiane and Town Planner Mark
Eyerman and provided a copy of the May 24, 2018 Maine Environmental Laboratory
report on the paint samples.
83. At the June 7, 2018 Board meeting, FMF submitted a written request to
the Board for reconsideration of its May 9, 2018 finding and decision. Exhibit 66
(FMF Request to Board with Maine Environmental Laboratory Report).
84. The Board took up FMF's reconsideration request at its June 14, 2018.
The Board declined to reconsider its decision. See Exhibit 68 (Board Meeting
85. June 14, 2018: Robert McIntyre, one of the Citizens, presented a copy of
the Citizen's Petition to a Notary Public.
86. On June 14, 2018, the Notary Public signed a "Warrant for a Special Town
Meeting of the Town of Harpswell for a special town meeting to take place on August
11, 2018. Exhibit 67 ("June 14, 2018 Warrant").
16 87. At the June 14, 2018 Board meeting, Dorothy Rosenberg presented the
June 14, 2018 Warrant to the Board. Exhibit 67 ("June 14, 2018 Warrant"); Exhibit
68 (Board Meeting Minutes).
88. Following an executive session with the Town Attorney, the Board met in
open session on June 28, 2018 and voted to declare the June 14, 2018 Warrant invalid
and to direct the Town Clerk not to expend any funds in support of holding the special
town meeting called for in the June 14, 2018 Warrant. Exhibit 68 (Board Meeting
89. On July 1.3, the Notary Public signed a "Warrant for a Special Town
Meeting of the Town of Harpswell" dated July 1.3, 2018 for a special town meeting to
be held on August 10, 2018. Exhibit 71 ("July 1.3, 20.18 Warrant").
90. On or about July 13, 2018, the Town received the July 13, 2018 Warrant".
91. At the direction of the Notary Public, FMF placed ads in the Harpswell
Anchor and Brunswick Times Record for the August 10, 2018 special town meeting
and a "public hearing" to discuss the secret ballot referendum question on July 28,
2018. Exhibit 72 (Published notices of July 28 hearing).
92 . The Board received a letter from the Town Attorney, dated July 12, 2018,
concerning the validity of the June 14, 2018 Warrant. Exhibit 70 (Letter from
Attorney Tchao to Board).
93. The Board did not call a public hearing on the article contained in the July
13, 2018 Warrant.
17 94. No notice of the July 28, 2018 public hearing provided the language of the
article to be voted on by secret ballot.
95. On July 26, 2018, FMF cancelled its August 10th Special Town Meeting.
FMF also cancelled its July 28, 2018 Public Hearing and instead held a public
informational meeting to discuss the water tower on that same date.
The Court's Additional Findings of Fact
This section sets forth the additional findings made by the court based on the
entire record:
96. The Town of Harpswell acquired Mitchell Field, including the water
tower at issue in this case, from the United States Navy in 2001. See Stip. Ex. 1.
97. The Mitchell Field water tower was constructed in about 1950 and consists
of an elevated water tank sitting on four legs, with struts or braces between the legs.
The tank has a capacity of 100,000 gallons. The tank is 28 feet across and the tower
is 104 feet high. Stip. Ex. 3, at 2.
98. Although the evidence is unclear as to when the water tower ceased being
used to store water, the tank has been empty for many years.
99. As indicated in paragraph 5 above, cellular telephone coverage is limited,
spotty or unavailable in many parts of Harpswell. Plaintiff Friends of Mitchell Field
seek to preserve the Mitchell Field water tower largely, if not primarily, because they
view the top of the tower as the highest and best-suited location in the area for
installation of cellular telephone equipment that could significantly improve reception.
18 100. There is an actively used private air field near Mitchell Field, and the
Friends are concerned that Federal Aviation Administration standards would limit or
prohibit the erection of an adequate cellular communications tower in the vicinity.
However, there is no evidence that an adequate cellular communications tower could
not be constructed in parts of Harpswell farther from the air field.
101. The members and directors of Plaintiff include registered voters in the
Town of Harpswell, a point relevant to Plaintiffs standing, as discussed further below.
102. Article 38 on the warrant for the 2013 annual Town meeting proposed
the demolition of the Mitchell Field water tower. The defeat of that article indicated
that a majority of those voting wanted to explore alternatives to demolition.
103. In response, the Town retained Utility Service Group (USG) to evaluate
the condition of the water tower. USG's July 2014 report (Stip. Ex. 3). That report
presented a detailed assessment of the water tower's condition, and concluded that
"[o]verall the tank is in good sanitary and structural condition ... [and] [t]here are
no significant deficiencies that could not be rectified if the tank were to be returned to
active service." Stip. Ex. 3. The report identified a substantial number of repairs that
would be needed to restore the tank, but contained no estimates of cost.
104. Also, the report presented the results of a laboratory analysis of three
samples taken the tower to be tested for lead and chromium. See Stip. Ex. 3 (Eastern
Analytical laboratory report). Two of the samples tested at low levels oflead (180 and
690 mg/kg) but the third sample-taken from the exterior shell of the tank-tested
well above the safety limit for lead (47,000 mg/kg). Id.
19 105. The 47,000 mg/kg test was so high as to indicate that a repair of the tank
could require sealing or encapsulation of the exterior of the tank. On the other hand,
the result was so much higher than the other lead test results as to raise· the question
whether it was an outlier or aberration.
106. In a follow-up email to Town representatives on September 6, 2014,
Scott Kelley of USG provided the Town with estimates of the cost to "bring your tank
up to best level of service as a water storage tank." Stip. Ex. 4. The total estimated
cost was $332,500.
107. In the same e-mail message, Mr. Kelley issued a strong safety warning.
He wrote that allowing the water tower to remain standing without water in the tank
was "extremely risky," and recommended "that action be taken immediately. Severe
weather may lead to failure of the structure." Id. In a later e-mail to the Town
administrator, Mr. Kelley elaborated on his warning by writing, "This steel structure
was designed to have water in it. Without water it is a liability. With severe weather,
the structure may fall over without the designed weight of having water in it." Stip.
Ex. 6.
108. The three quotes that the Town later obtained from Preferred Tank &
Tower (Stip. Ex. 10, 12) were to help the Town understand what costs were associated
with demolishing and repairing the water tower. Preferred Tank quoted the
following costs:
$75,000 to demolish the water tower
$138,625 to repair it without sealing or encapsulating exterior surfaces
20 $337,125 to seal/encapsulate all exterior surfaces, to eliminate any risk from
high lead levels in the exterior coating
109. The Town's March 2016 annual meeting warrant included two articles
relating to the water tower. They were similar in wording. Article 34 was sponsored
by the Select Board and it would create a reserve fund of $22,000 to be used to fund
further analyses of the Town's options for the water tower. Article 35 resulted from
a voter petition and it would have committed the Town to spend $22,000 on repairing
and maintaining the tower. Article 34 was adopted by the voters and Article 35 was
passed over. See paragraph 21, supra.
110. As a result of the Town meeting vote, the Select Board at its March 31,
2016 meeting created the Water Tower Task Force (WTTF). The WTTF was
structured to include four Town residents as primary members, two more as
alternates, and a Select Board member to serve as chair. The Select Board decided to
appoint residents with differing viewpoints to the WTTF.
111. The WTTF met regularly during the middle months of 2016, gathering
information from people with expertise in the fields of public water supply, cellular
communications and cell tower construction and leasing. See Stip. Exs. 1 7-20 (WTTF
112. At its October 2016 meeting, the WTTF voted to ask the Town to issue
an RFP for a water tower site communications manager, and to ask the Town to
contract with the Woodard and Curran consulting engineers to focus on water supply
issues relating to the existing well and water tower. See Stip. Ex. 22. At the same
21 meeting, there was discussion about the availability of funding for the repair and
maintenance of the tower from private sources, but it was agreed that no commitments
should be made based on private funds without assurance that the funds would be
available when needed. See id.
113 . The Town Select Board granted both requests, issuing the RFP in
November and delegating to the WTTF the responsibility for evaluating proposals
submitted in response to the RFP. See Stip. Ex. 24. The Town also contracted with
the Woodard and Curran firm as the WTTF had recommended.
114. At the Town's annual meeting March 11, 2017, the voters adopted
Article 35A on the warrant, authorizing $10,000 in Town funds to be spent on
determining "the feasibility of placing wireless communications equipment on the
Mitchell Field Water Tower by obtaining information that includes the number of
interested carriers, what potential payments the Town may derive from equipment
placement, and a detailed description of the work required and associated costs to place
the Tower in service as a communications site." Stip. Ex. SO at 14.
115. Presumably the goal was for the Town to retain a water tower site
communications manager who, working with the WTTF, would compile the
information described in Article S5A. Things did not work out that way.
116. The WTTF designated an interview committee to meet with NPCI and
CFI, the two companies that submitted proposals in response to the RFP. Due to
member unavailability, however, the group that actually met with NPCI and CFI was
limited to Town staff and the chair of the Select Board. ' 22 117. After meeting with the interview committee, CFI withdrew its proposal
and NPCI revised its proposal. See Stip. Ex. 35. The email messages sent by CFI and
NPCI indi~ated that they were backing away because they had realized that the Town
anticipated that the costs of repairing and maintaining the tower would be covered by
the income from leasing the tower to cellular communications providers. Neither CFI
nor NPCI considered that expectation to be a reasonable one. In fact, CFI's email
message flatly indicated that the tower was not a viable option for placement ofcellular
communications equipment and "a new and separate freestanding tower is the only
viable option for the property." Id.
118. It appears that the interview committee led CFI and NPCI to think the
cost of repairing and maintaining the water tower would have to be covered by income
from leasing the tower for placement of cellular communications equipment, even
though no such decision had been made by the Town.
119. The interview committee presumably did not set out to scare away the
two companies that responded, but that is what the Friends of Mitchell Field appear
to claim happened. On the other hand, the Friends' claims of bias on the part of the
Town are largely refuted by the fact that, over a period of years, the Town, through
the voters at annual meeting and the Selectmen, readily agreed to many of the steps
that those who favored keeping the water tower had asked. Moreover, the Town staff
continued to investigate options for using the water tower for purposes of cellular
communications. See Stip. Ex. 40 (memoranda attached to minutes ofWTTF meeting
October 20, 201 7).
23 120. By the fall of 2017, it had become obvious that the WTTF process was
not going to generate a consensus report and recommendation on the future of the
water tower. The members of the WTTF were themselves divided, with two regular
members in favor of keeping the tower and the other two in favor of demolishing it.
121. The WTTF's mandate required the WTTF to issue a report and
recommendations at the end of its work, and the WTTF's report recommending that
two competing articles to be placed on the Town meeting warrant was likely as close
the only consensus report and recommendation the WTTF could have reached. See
Stip. Ex. 40.
122. The Select Board followed the WTTF's recommendation and also began
to set in motion processes to enable either alternative to be implemented. To enable
the "keep" article to be implemented should the voters favor it, the Select Board issued
a Request for Expressions of Interest and/or Proposals in January 2018, specifically
to enable outside groups within the community to submit proposals to lease and
maintain the water tower.
123. In response, some of the Harpswell residents who favored keeping the
water tower, including at least one member ofthe WTTF, formed the Plaintiff Friends
ofMitchell Field as a Maine nonprofit corporation in February 2018. See Stip. Ex. 45.
The Friends submitted their proposal to the Town February 26, 2018. Stip. Ex. 47.
The proposal included an assessment of the condition of the water tower performed at
Plaintiffs request by a structural engineer. Stip. Ex. 46. The assessment concluded
24 that "the effort to stabilize the condition of the water tower amounts to little more
than addressing some deferred maintenance issues." Id. at 2.
124. At the March 1, 2018 Select Board meeting, the Town administrator
informed the Board of the Friends' proposal and raised a couple of questions about the
insurance and financial components of the proposal. See Stip. Ex. 48. The Board
discussed the proposal at a workshop March 6. One question raised at the workshop
was whether the Friends' response that several of the Town's requirements were "Not
a Problem" meant that the requirements were agreed to.
125. The Friends decided to clarify their proposal by replacing the "Not a
Problem" phrase with the word "Agreed," and delivered a revised version of the
proposal to the Town on March 7, 2018. The Town posted the Friends' proposal on
its website later that day.
126. Meanwhile, representatives of the Friends were in touch with the Town
administrator regarding the March 10, 2018 annual Town meeting. A Friends
representative, Robert McIntyre, asked the Town administrator whether the Friends
could hand out copies of their proposal at the meeting. At the August 28, 2018 court
hearing, Mr. McIntyre testified that the Town administrator told him that the
proposal could not be distributed at Town meeting because it related to an article on
the Town meeting warrant. Whether this was in fact what was said is not clear,
because it is agreed that the Town administrator also said that the Friends could bring
a summary of their proposal to the meeting-which would also have related to an
article-if the summary were reviewed in advance with the Town's attorney. It would
25 make little sense for the proposal to be barred but a summary of it to be allowed. In
any event, the Town administrator later denied telling the Friends their proposal
could not be brought to Town meeting. See Stip. Ex. 62, at 8. 2
127. The Friends prepared a summary of their proposal and it was reviewed
by the Town's attorney as requested by the Town. See Stip. Ex. 50. However, the
Friends were told they could not hand out copies during the meeting, and instead
should leave copies on the table set aside for groups in the community to place
materials for Town meeting participants to pick up.
128. During the Town meeting, five of the six directors of the Friends of
Mitchell Field listed in the Friends' revised proposal spoke in favor of the "keep
article." See Stip. Ex. 52 at 6, 8-9, 10-11, 13-16, 20-21, 21-22. During his remarks
on behalf of the Friends, Mr. McIntyre directed the voters' attention to the Plaintiff's
materials. Id. at 11. Other speakers advocated for the "remove" article. There is no
indication that anyone was precluded from speaking until debate on the two articles
was closed.
129. After debate was closed, the vote at Town meeting was not to approve
the "keep" article, Article 29 but to approve the "remove" article, Article 30. See Stip.
Ex. 53, at 15 (annual Town meeting results).
2 A possible explanation for what seems to be a misunderstanding is that the Town administrator said that the Friends could not hand out their proposal at the meeting, and the Friends interpreted her statement to mean they could not bring the proposal to the meeting at all. 26 ISO. At some point around this time, the Town decided to commission further
testing of lead levels on and around the tower, along with testing for asbestos. It
appears that the primary purpose of the testing was in connection with the Town's
development of a request for proposals for the demolition of the tower. The only
testing for lead done to date had been in connection with USG's July 2014 report.
IS 1. In April 2018, the Town received the results of the additional laboratory
tests it had commissioned. See Stip. Ex. 54. The test results indicated that four
samples-two of paint chips and two of soil taken from under or around the tower
had lead levels well below the health safety limits for lead, and the 47,000 mg/kg level
reflected in the 2014 USG report. Id.
132. At the Select Board's April 19, -2018 meeting, the Board reviewed and
approved a request for proposals to demolish the Tower. Stip. Ex. 55, at 2. Also, the
Town administrator informed the Board of the new test results, which indicated that
the soil around the tower was within acceptable limits for lead and would not need to
be excavated as part of the demolition project. Id.
lSS. The Town's RFP for demolishing the water tower was issued April 20,
2018. See Stip. Ex. 56.
134. At the April 19 Select Board meeting, representatives of the Friends
advised the Board that a petition for the Board to revisit and undo the Town meeting
vote, based on new information, was in the works and would be submitted to the
Board. Id.
27 135. After the Select Board's April 19, 2018 meeting, representatives of the
Friends and the Town engaged in a dialogue about the significance of the new lead
test results. See Stip. Exs. 57-59.
1.36. For the Friends, the new lead test results confirmed that the 47,000
mg/kg test result obtained by USG in 2014 was not valid, in light of the fact that all
six of the other samples in the 2014 and 2018 tests had tested at lead levels well below
federal and state standards. The Friends were convinced that the "keep" or "remove"
issue had to be revisited because the Town's March 10, 2018 vote was based on
incomplete and misleading information. See Stip. Exs. 57, 58.
1.37. Following the April 19, 2018 Select Board meeting, Dorothy Rosenberg,
sent an email message to Town officials and staff pointing out that the new lead test
results showed that the "least expensive justification for demolition of the water tower
collapses. Without lead contamination, the water tower turns out to be the least
expensive option for providing cell phone service to the Neck, Bailey and Orr's
Islands." Stip. Ex. 57. The email said that the WTTF report contained "errors of
such magnitude as to invalidate its core conclusions," with the r~sult that the Select
Board had presented "incorrect and misleading information to the citizens of
Harpswell prior to the vote at Town meeting." The email called on the Select Board
to apologize to the citizens and correct the mistake. Id.
1.38. The Town Administrator responded in an April 24, 2018 email that
included a memorandum from the Town planner discussing the previous and new lead
test results. Stip. Ex. 59. The Town's view of the new lead test results was that the
28 disparity between the 47,000 mg/kg lead test result obtained by USG and the far
lower results in the other six samples tested simply reflected the presence of different
lead levels on different parts of the tower structure. See id.
139. On April 26, 2018, the Friends of Mitchell Field and other supporters of
keeping the water tower submitted petitions for the Select Board to convene a secret
ballot vote on whether to "repeal the decision of the Harpswell Town Meeting on
March 10, 2018 on Warrant Item #so and authorize the Select Board to enter into an
agreement with the non-profit corporation Friends of Mitchell Field ..." to repair,
manage and maintain the water tower. Stip. Ex. 60.
140. The wording of the petition was somewhat different than the wording of
Article 29, the "keep" article that the voters rejected at the March Town meeting.
Article 29. Article 29 asked the voters to decide whether to authorize the Town to
enter into an agreement for up to 20 years (and possible further extensions) with an
unspecified for-profit, non-profit or other entity. See Stip. Ex. 53. The question
advanced in the petition was whether the Town should enter into an agreement with
the Friends of Mitchell Field for five years. See Stip. Ex. 60.
141. The Town Clerk determined that the petition included 351 valid voter
signatures, well over the amount required for such a petition (and well over the
number of voters who had participated in the March 10, 2018 Town meeting) . See
Stip. Ex. 61.
142. The Select Board took up the petition at its May 2, 2018 meeting. After
a lengthy debate, the Board voted 2-1 to reject the petition. See Stip. Ex. 62. During
29 the discussion, the Friends told the Board that the Town administrator had refused to
permit them to distribute their proposal at the Town meeting, but the Town
administrator denied that she had done so. See id. at 8.
143. At its May 9, 2018 meeting, the Board adopted its Findings of Fact and
Decision Concerning Citizens' Petition Regarding Mitchell Field Water Tower. Stip.
Ex. 64.
144. At the Board's May 17, 2018 meeting, the Town administrator presented
to the Board the three bids that had been submitted in response to the Town's RFP
for demolition of the water tower. See Stip. Ex. 65, at 2.
145. The Friends and other proponents of keeping the water tower decided to
pursue their concerns in two different directions. First, they submitted to a notary
public the same petition they had submitted to the Board, for purposes of having the
notary convene a special town meeting pursuant to SO-A M.R.S. § 2521(4). They also
filed a request for reconsideration with the Select Board. See Stip. Ex. 66. The request
was based mainly on the new lead test results the Town had obtained in April, but
also on "allegations ofimpropriety on the part of town officials before, during and after
Town meeting." Id. at 2.
146. The notary to whom the Friends and other proponents of keeping the
water tower had presented the petition that the Select Board had rejected issued a
Warrant for a Special Town Meeting on June 14, 2018. See Stip. Exs. 67. The
Warrant called for a special Town meeting to be held at the Merriconeag Grange hall
August 11, 2018. Stip. Ex. 67. It was later determined that the hall was not available
30 that day, so the notary issued an amended warrant calling for a meeting on August
10, 2018. Stip. Ex. 71.
147. On the same day, June 14, 2018, the Board held a meeting at which a
lengthy debate about the request for reconsideration ensued. Stip. Ex. 68, at 2-3.
Accusations of bias and conflict of interest were made by both sides in the dispute
about the future of the tower. Id. The request for reconsideration was effectively
denied because neither of the two members of the Select Board who had voted to reject
the petition moved to reconsider. Id. at 3. The June 14, 2018 Board meeting also
included further discussion of the bids for demolishing the tower. Id. at 3-4.
148. At the Board's June 28, 2018 meeting, based on advice from the Town
attorney, the Board voted "to deem [the notary's] warrant invalid and to direct the
Clerk not to expend any funds on this effort." Stip. Ex. 69, at 2. The Board also voted
to enter into a contract with the low bidder in response to the RFP for the demolition
of the water tower, with a contingency relieving the Town of responsibility if the
demolition were enjoined. See id. at 2-3. The contract was executed effective July 26,
2018. See Stip. Ex. 73.
149. Meanwhile, the Friends placed advertisements in the Brunswick Times
Record for a July 28, 2018 hearing and an August 10, 2018 Town meeting on the
notary's amended warrant. See Stip. Ex. 72.
Ana"/ysis and Conclusions efLaw
150. Based on the Town's rejection of the notary warrant, the court
recommended that the hearing and Town meeting called by the notary not be held,
31 until the court could decide whether the petition to the notary was valid. The Friends
agreed to the recommendation, on the understanding that the court retained the
ability to order the Town to convene a hearing and vote on the notary's warrant.
151. The Plaintiff Friends' complaint seeks a declaratory judgment and
mandatory injunction to the effect that the Town is required to convene a hearing and
vote by secret ballot on the notary's warrant. The Friends also ask the court to enjoin
the Town from demolishing the water tower until and unless the Town holds the vote
that the Friends are seeking.
152. The Town has raised a variety of objections to the Friends' cause of
action, only some of which require extended discussion. The Town questions the
Friends' standing to sue. However, the court is prepared to assume, without deciding,
that the Friends have standing, based on the doctrine of associational standing. See
Warth v. Seldin, 422 U.S. 490,511 (1975). Plainly some of the directors of the Friends
actively participated in the proceedings at issue, and may have had standing had they
brought this case in their own names.
153. The Town also asserts that the Friends cannot challenge the May 9,
2018 Findings ofFact and Decision Concerning Citizens' Petition Regarding Mitchell
Field Water Tower under M. R. Civ. P. BOB because the complaint was not filed within
the deadline set by that rule. At oral argument, the Friends did not disagree that any
direct Rule BOB appeal from the Board's May 9, 2018 Findings of Fact and Decision
is time-barred. However, the Friends assert instead that the question before the court
is whether the petition submitted to the notary public was valid for purposes of
32 declaratory and injunctive relief in the nature of a writ of mandamus requiring the
Town to convene another Town meeting and vote on the question framed in the
petition. See 14 M.R.S. § 5301. 3
154. The Friends contend that the Town is required to call a Town meeting
and vote under the Maine statute allowing voters to petition a notary to call a town
meeting when town selectmen unreasonably reject a petition of the voters. See SO-A
M.R.S. § 2521(4), 2522. The statutes read as follows:
Petition for article in warrant: On the written petition of a number of voters equal to at least 10% of the number of votes cast in the town at the last gubernatorial election, but in no case less than 10, the municipal officers shall either insert a particular article in the next warrant issued or shall within 60 days call a special town meeting for its consideration.
so-A M.R.S. § 2522. Petition by voters, if selectmen refuse. If the selectmen unreasonably refuse to call a town meeting, a notary public may call the meeting on the written petition of a number of voters equal to at least 10% of the number of votes cast in the town at the last gubernatorial election, but in no case less than 10.
so-A M.R.S. § 2521(4). 155. The Maine Law Court has interpreted both of these statutes in its
decision in Dunston v. Town oJYork, 590 A.2d 526 (Me. 1991). Despite the seemingly
mandatory "shall either insert ... or call" terminology within section 2522, the court
decided that the alternative petition remedy established in section 2521( 4) recognizes
"the authority of the selectmen to exercise their sound discretion in determining
3 The writ of mandamus has been abolished in Maine but mandatory injunctive relief in the nature of a writ of mandamus remains available. See Dunston v. Town of York, 590 A.2d 526, 528 (Me. 1991). 33 whether the written petition required compliance with the provisions of section 2522."
Id. at 527.
156. At oral argument, the parties appeared to agree that the PlaintiffFriends
has the burden to establish their right to relief in this case, and that the burden has
two elements:
a. To prove that the Town Select Board's refusal to call a town meeting in
response to the petition submitted to the Board was unreasonable, i.e. an
abuse of their discretionary authority
b. To prove that the petition submitted to the notary public was valid.
See SO-A M.R.S. § 2521(4 ).
157. For the reasons set forth as follows, the court concludes, based on the
entire record, that the Friends have not proved either element of their burden.
158. With regard to the unreasonableness of the Select Board's refusal of the
petition, the Friends assert three grounds: that the petition presented a different
question than the question voted upon at Town meeting; that the petition was based
on new information that should have been presented to the voters at Town meeting,
and that there were improprieties before and at the Town meeting that justify a new
vote.
159. Although the wording of the petition was somewhat different than the
wording of article 29 on the Town meeting warrant, compare Stip. Exs. 5S and 60, the
Select Board could reasonably have decided at their May 9, 2018 meeting that the
34 petition was asking for a revote on the essentially the same question that had been
decided at the Town meeting-should the water tower be demolished or not?
160. The petition identified the Friends specifically as the entity with which
the Town would have an agreement whereas Article 29 did not. Still, the Select Board
could reasonably have decided that the voters were aware at the Town meeting that
the Friends were hoping to be the entity that contracted with the Town to repair and
161. Maine law does not compel either a municipal board or a school board to
schedule a revote upon petition by voters on an issue that has already been acted on
by the electorate. See Heald v. School Administrative District No. 74, 387 A.2d 1, 4 (Me.
1978); Town if Vassalboro v. Denico, 1990 Me. Super. LEXIS 61. Under the Dunston
standard, the Harpswell Select Board's view that the fundamental question raised in
the petition had already been decided by the voters was a reasonable one.
162. As to the contention based on new lead test information, the Select Board
could reasonably have decided that the new lead test results were not the "game
changer" for voters that the Friends thought they were. The Town meeting vote to
demolish the tower did not hinge on the validity of the 2014 lead test results. Also,
the new test results did not prove that the high 47,000 mg/kg result was wrong,
particularly since the new results were from samples taken from other locations than
the exterior of the tank, where the sample that yielded the high test was taken.
163. As to alleged improprieties, the Friends failed to prove anything rising
to the level of an impropriety by Town officials or staff The Friends' allegations of
35 impropriety fall into three different categories. First, the allegation that the Select
Board Chairs who also chaired the WTTF were biased and prevented the WTTF from
meaningful exploration of the potential for saving the water tower. Second,
allegations that the Town staff was "biased" in favor of demolishing the tower. Third,
allegations that the Friends were prevented from bringing their proposal at the Town
meeting and were required to leave their summary on a table instead of being allowed
to pass it out.
164. The first chair of the WTTF was Select Board Member Elinor Multer.
When she left the Select Board, the current Select Board chair, Richard Daniel, took
her place as WTTF chair. Mr. Daniel testified at the August 28, 2018 hearing that he
favored demolishing the water tower for safety reasons.
165. The fact that Mr. Daniel had a viewpoint on the future of the tower does
not, in and of itself, prove anything. Select Board members can and should develop
positions on issues affecting the Town. The question is whether Mr. Daniel imposed
his viewpoint in an inappropriate manner while chairing the WTTF, and the record
does not show that he did.
166. Given that the other four members of the WTTF were divided on the
tower issue-two favoring saving the tower, two favoring demolishing it-Chair
Daniel plainly could have imposed his personal viewpoint upon the WTTF by
breaking the impasse and calling for a vote on whether to recommend demolition or
not. Had he done so, the WTTF would likely have issued a report by vote of .3-2 with
a specific recommendation in favor of demolition. But he did not force the issue in
36 that fashion. Instead, he voted, along with the others, to recommend the "keep" option,
even though he disagreed with it, along with the "remove" option.
167. Another allegation against Chair Daniel is that he did not support all of
the suggestions and recommendations made by WTTF member Dorothy Rosenberg,
who is a director of the Friends. This accusation as well does not prove any
impropriety-no member of any committee is entitled to have all her or his
suggestions and recommendations adopted by the committee or supported by the
committee chair.
168. The allegation that the Town staff was biased against saving the tower
is similarly not supported in the record. The record shows that Town staff continued
to support the WTTF and respond to WTTF members' requests until the WTTF
ceased to function after October 2017.
169. Likewise, the allegation that there were improprieties before and during
the 2018 Town meeting was not borne out in the evidence. The Friends' claim that
the Town administrator forbade them from bringing their proposal to the Town
meeting because it related to a Town meeting warrant article was not only denied by
the Town administrator, but also makes little sense given that the Friends were
admittedly allowed to place a summary of their proposal for distribution, which related
to Articles 29 and 30 as much as their proposal did. The Town's requirements that
the summary be reviewed by the Town attorney and that it be placed on a table of
materials rather than handed out likewise were not improper. There is no evidence
that the Friends were treated differently than other groups .
37 170. The Friends also appear to complain that the Town did not post their
proposal on the Town website for a sufficient length of time, and did not allow them
to put their summary on the table of Town materials. This argument overlooks the
fact that the Town was not required to endorse or support the Friends' proposal. The
Town's willingness to post the Friends' revised proposal on the Town website from
March 7 to March 10, 2018 was in fact more than the Friends were entitled to.
171. For the foregoing reasons, Plaintiff Friends has not proved that the
Harpswell Select Board unreasonably refused to grant their petition for purposes of
so-A M.R.S. § 2522 and 2521(4). 172. Even had the Friends met their burden of persuasion on the issue of
whether the Select Board unreasonably rejected their petition for purposes of .30-A
M.R.S. §§ 2521(4), their petition to the notary was defective because it was the same
petition addressed to the Select Board, and not a separate petition addressed to the
notary.
17.3. Section 2521(4) could have provided that the same petition that was
presented to the selectmen can be presented to a notary if the selectmen refuse it, but
it does not. Instead, section 2521(4) requires a different written petition to be
submitted to the notary, and there is a good reason for that. A petition addressed to
one entity for one purpose cannot simply be redirected to a different entity for a
different purpose. Here, it cannot be assumed that the signers of the petition to the
Select Board would necessarily support a petition addressed to a notary after the Select
38 Board had declined to act upon the petition. Some signers might accept the Select
Board decision and not want to take the next step.
For all of the foregoing reasons, the court finds and concludes that the
Plaintiff Friends of Mitchell Field has not proved that the Town is obligated to
schedule and hold a vote on the Friends' petition.
IT IS ORDERED AND ADJUDGED AS FOLLOWS:
1. Plaintiffs prayer for declaratory relief is granted in part and otherwise
denied. The court declares as follows:
(a) For purposes of 30-A M.R.S. § 2522, the Harpswell Select Board did not unreasonably refuse to call a town meeting in response to the Plaintiff Friends of Mitchell Field's petition submitted to the Board April 26, 2018,
(b) The petition submitted by Plaintiff Friends of Mitchell Field to a notary public did not comply with 30-A M.R.S. § 2521(4) and therefore was not a valid basis for convening town meeting under that section.
2. Plaintiffs prayer for injunctive relief is denied.
3. Except for the limited grant of declaratory relief in subparagraphs (a) and
(b), the Defendant Town of Harpswell is granted judgment on the Plaintiffs
complaint.
Pursuant to M.R. Civ. P . 79( a), the Clerk is hereby directed to incorporate
this Decision and Judgment by reference in the docket.
Dated September 5, 2018 A. M. Horton, Justice
Entered on the Docket: 9 . s. \~ 39 Friends of Mitchell Field vs. Town of Harpswell, PORSC-CV-18-334
Plaintiff's Counsel:
Christopher Neagle, Esq . Troubh Heisler
Defendant's Counsel:
Amy Tchao, Esq. Drummond Woodsum
Related
Cite This Page — Counsel Stack
Friends of Mitchell Field v. Town of Harpswell, Counsel Stack Legal Research, https://law.counselstack.com/opinion/friends-of-mitchell-field-v-town-of-harpswell-mesuperct-2018.