Fretz v. Pennsylvania Public Utility Commission
This text of 666 A.2d 372 (Fretz v. Pennsylvania Public Utility Commission) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Henry S. Fretz appeals from an order of the Pennsylvania Public Utility Commission (Commission) adopting the decision of an Administrative Law Judge (ALJ) which approved a letter of notification filed by Pennsylvania Power & Light Company (PP & L), denying Exceptions to the ALJ’s decision filed by Fretz and granting Reply Exceptions filed by PP & L. We affirm.
On February 7,1992, PP & L filed a letter of notification pursuant to 52 Pa.Code § 57.72 requesting Commission approval of PP & L’s plan to replace existing 69 KV single circuit transmission lines connecting PP & L’s Hosensack and Upper Hanover sub-stations with double circuit 138 KV lines with higher capacity conductors.1 The pro[374]*374ject consists of two sections, Section A and Section B. With respect to Section B, PP & L proposes to replace the existing 50-foot two-pole wooden “H-frame” towers with 85-foot single-shaft steel poles.
A portion of Section B runs through property owned by Fretz. With respect to that property, PP & L has a 50-foot strip right-of-way with 50-foot “no-build” restrictions on either side, for a total encumbrance of 150 feet.2 There are currently six structures and 12 wooden poles on the Fretz property. PP & L’s proposal is to replace them with only four structures and four steel poles, all within the existing right-of-way. PP & L proposes to configure the taller steel poles in such a way as to reduce the electro-magnetic field generated by the lines.
On March 6, 1992, Fretz filed a letter of protest which the Commission addressed at a public meeting on August 20, 1992. After some discussion, the Commission decided that the protest raised a question, i.e., whether PP & L’s replacement of existing wood towers with taller steel poles would constitute a substantial alteration of the existing PP & L right-of-way. The Commission stated that the resolution of this issue would determine whether PP & L may proceed with certification of the project by letter of notification in lieu of formal application. The Commission referred this matter to an ALJ for hearings and a decision.3
After two hearings, upon consideration of the necessity, safety and impact of the project, the ALJ found, in addition to the facts as stated above, that (1) PP & L has a policy requiring a minimum 100-foot right-of-way to maintain safety code clearances with respect to electro-magnetic fields; (2) PP & L can physically place the towers on the 50-foot right-of-way over the Fretz property; and (3) the 50-foot “no-build” strips on each side of the 50-foot right-of-way provide enough of a restriction so that the new tow7 ers will fit safely on the overall right-of-way. The ALJ thus concluded that Section B of PP & L’s project would not substantially alter the existing right-of-way and approved the project. Fretz filed Exceptions to the decision with the Commission, and PP & L filed Reply Exceptions.
[375]*375The Commission adopted the decision of the ALJ and, in addition, found that the taller structures and reverse phasing proposed by PP & L would reduce the electromagnetic field at the edge of the 50-foot right-of-way over the Fretz property by more than seventy per cent. The Commission thus denied Fretz’s Exceptions, granted PP & L’s Reply Exceptions and approved PP & L’s plan to reconstruct or modify Section B of the Hosensaek-Upper Hanover transmission line.
On appeal to this court,4 Fretz first argues that the Commission and ALJ erred as a matter of law in considering the 50-foot “no-build” strips as part of PP & L’s overall right-of-way and concluding, as a result, that PP & L could safely fit its project within the 50-foot right-of-way. We agree that the ALJ’s decision seems to suggest that PP & L’s right-of-way includes the 50-foot “no-build” strips; however, we believe that the Commission has adequately addressed this problem.
The ALJ found that PP & L could “physically place the towers on the 50-foot right-of-way which it holds over [Fretz’s] land.” (R.R. at 6a.) However, the ALJ, in considering whether PP & L could meet electromagnetic field safety requirements within the 50-foot right-of-way, stated:
[With respect to the question of need for a wider right-of-way to provide for safe operation,] I conclude that the 50-foot “no-build” strips on each side of the right-of-way do provide enough of a restriction so that the towers appropriately fit on the overall right-of-way.
(R.R. at 6a.) (Emphasis added.) We believe that the ALJ’s use of the phrase “overall right-of-way” improperly suggests that the 50-foot “no-build” strips are part of the , right-of-way.5
The Commission adopted the ALJ’s decision but made an additional finding, i.e., that the taller structures and reverse phasing proposed by PP & L will reduce the electromagnetic field at the edge of the 50-foot right-of-way over Fretz’s property by more than seventy per cent. Thus, the Commission determined that the 50-foot “no-build” strips were irrelevant to the issue of safety. We agree with the Commission. If PP & L can reduce the electro-magnetic field by seventy per cent within the 50-foot right-of-way, then that portion of the ALJ’s decision implying that PP & L possesses a 150-foot right-of-way over Fretz’s property is harmless error.6
Fretz, however, contends that the record does not contain substantial evidence to support the Commission’s finding that PP & L will reduce the electro-magnetic field by seventy per cent at the edge of the 50-foot right-of-way; indeed, Fretz maintains that the record shows that PP & L must have a 100-foot right-of-way to comply with the safety code. We disagree.
[376]*376PP & L witness Gary P. Billman testified credibly as follows:
[T]he addition of the second circuit, along with reverse phasing of the line, will substantially reduce electromagnetic fields emanating from the line. Specifically, at the edge of the 50-foot strip right-of-way, EMF will be reduced from 27.02 mG to 7.26 mG, a reduction of over 70%. Reverse phasing is an important part of PP & L’s EMF Management Plan.
(R.R. at 16a.) We believe that such testimony constitutes substantial evidence to support the Commission’s finding that PP & L will reduce the electro-magnetic field by seventy per cent at the edge of the 50-foot right-of-way.7
Fretz next argues that evidence in the record demonstrates that the safety code requires that PP & L have a 100-foot right-of-way in this case. Again, we disagree. PP & L submitted into evidence a document entitled “Field Management at Pennsylvania Power & Light Company,” which states in pertinent part:
Transmission Engineering will continue to use long-span “LONG” construction for 138 kV double circuit lines_ This construction requires a minimum 100’ right-of-way to maintain safety code clearances. Transmission Engineering will evaluate existing narrower rights-of-way to determine if either a wider right-of-way should be obtained or if different construction should be used to optimize line design and magnetic field reduction.
(R.R.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
666 A.2d 372, 1995 Pa. Commw. LEXIS 448, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fretz-v-pennsylvania-public-utility-commission-pacommwct-1995.