Fresh & Oliveira v. City of New Orleans

126 So. 214, 169 La. 852, 1930 La. LEXIS 1607
CourtSupreme Court of Louisiana
DecidedJanuary 6, 1930
DocketNo. 30203.
StatusPublished

This text of 126 So. 214 (Fresh & Oliveira v. City of New Orleans) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fresh & Oliveira v. City of New Orleans, 126 So. 214, 169 La. 852, 1930 La. LEXIS 1607 (La. 1930).

Opinion

OVERTON, J.

This is a suit to recover $5,4S6.20, retained by defendant, pursuant to the terms of certain contracts, entered into by it with plaintiff for the construction of subsurface drains, gutters, curbings, and ■sidewalks on sections of three streets in the city of New Orleans. The amount, sued for, was retained out of the contract price, due under each contract, for the work done, and is held, under the terms of the contracts, to guarantee plaintiff’s obligation, for a period of two years, to maintain in good repair the work done in accordance with the maintenance provision of the contracts and specifications.

■ The period, during which the amount was to be held as a guaranty has expired, but defendant refuses to pay plaintiff the amount retained, because of the alleged defective condition of some of the work done, which defendant alleges plaintiff refuses to remedy. Defendant has reconvened for $7,617.90, the estimated cost of repairing the defective work.

After trial had, there was judgment in fa-: vor of plaintiff for $4,792.90, with legal interest on the amounts going to make up the sum allowed from various dates until paid, and dismissing defendant’s reconventional demand.

The reason why the trial court did not render judgment in favor of plaintiff, for the full amount prayed for, is because plaintiff admitted on the trial of the case that there were certain defects in the work, which it had failed to remedy during the maintenance period, which, under its guaranty, it should correct. The trial court, instead of allowing the cost of making those repairs in reconvention, deducted the cost thereof from the amount sued for by plaintiff. Plaintiff does not complain of this deduction.

Plaintiff alleges in its petition, and defendant admits the truth of the allegation, that it did the work, called for by the contracts, in accordance with the plans and specifications, and defendant, at the opening of its argument, makes the same admission, in its brief, by saying that there is no issue, and that it has made no contention, that plaintiff is liable because of any defects due to workmanship or to material used.

The sole question at issue is whether plaintiff is liable, under the maintenance clause of the contracts, to repair defects in the work, executed by it, which have arisen during the period of maintenance, and which are due to subsidence of the foundation, and not to defects in the material used, or to inferior workmanship. ■ • ■ ....

*855 The solution of the issue, presented, therefore involves an interpretation of the maintenance clause and of such clauses in the specifications, which are made part of the contracts, as bear upon the question before us.

Under the title of “Familiarity with Plans and Proposed Work,” the specifications contain a provision, reading as follows, to wit: “The bidder should personally examine carefully the site of, and the proposal, plans, specifications, and contract form for the proposed work, and the city engineer will assume that he has satisfied himself as far as it is practicable to do so, both by personal investigation and inquiry from informed sources, as to the conditions to be encountered, as to the character, quality and quantities of work .to be performed and materials to be furnished and as to the requirements of these specifications and contract. No additional compensation will -be granted because of any unusual difficulties which may be encountered in the execution, or maintenance of any part of the work.”

Under the title of “Maintenance,” the specifications, which form part of the contracts involved herein, contain a provision, which reads: “The contractor, at his expense, shall maintain in good order and condition, all the work included in his contract and executed by him, in addition to all extra work that may have been ordered by the'city engineer to the satisfaction of the commissioner of public property, from the date of acceptance of the same by the city engineer and the said commissioner, for such period of time as is hereinafter prescribed for each kind and character of work, or as may be otherwise stipulated in the proposal form furnished by the city engineer.”

Under the title of “Maintenance Requirements,” the specifications read as follows, to wit: “During the maintenance period and before final acceptance the contractor ‘ shall promptly and properly repair any defects in the work executed by him under his contract. Cracks in the wearing surface more than three (3) feet in length, or cracks or other defects which indicate disintegration of the wearing surface, and all irregularities of the surface and places where the material is defective or improperly laid shall be promptly and properly repaired. Any surface irregularities which are due to defects in the foundation shall be taken up and a new foundation and wearing surface provided for such areas. None but new material of the same quality as the original material shall be used in making repairs, and all work shall be executed in accordance with the specifications governing the original work.”

Each of the three contracts entered into between plaintiff and defendant contains two principal obligations, due by the former to the latter. The first of these is the obligation to perform the work strictly in accord-anee with the plans and specifications found in the contracts to which the plans and specifications are attached. It is conceded that plaintiff discharged that obligation. The second is the obligation, found in the specifications under the title of “Maintenance,” to the effect that: “The contractor, at his expense, shall maintain in good order and condition, all the work included in his contract and executed by him, in addition to all extra work that may have been ordered by the city engineer to the satisfaction of the commissioner of public property” for the period prescribed by the contracts, which was two years, dating from the acceptance of the work. This provision is broader than a mere guaranty to remedy defects, resulting from inferior workmanship or the use of defective *857 material, appearing within the two year period. It goes beyond this and includes the obligation to maintain the work in good repair for the required period, whether or not the repairs are required because of defects in the workmanship or because of the use of inferior material. This provision, however, does not stand alone, and must therefore be interpreted in connection with other provisions bearing on the subject.

So interpreting that provision, we fail to find that the remaining provisions modify it so as to confine it to defects arising from improper workmanship or the use of defective material. The first sentence in the provision, quoted above, relative to “Maintenance Requirements,” reading that, “During the maintenance period and before final acceptance, the contractor shall promptly and properly repair any defects in the work executed by him,” does not so restrict the obligation, under the title of “Maintenance,” as to confine it to defects arising from improper workmanship or the use of defective material. The defects referred to in that sentence are defects arising whether because there was a failure to comply properly with the specifications or not.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Riley v. . the City of Brooklyn
46 N.Y. 444 (New York Court of Appeals, 1871)
Cameron-Hawn Realty Co. v. . City of Albany
101 N.E. 162 (New York Court of Appeals, 1913)
Barber Asphalt Paving Co. v. City of Louisville
97 S.W. 31 (Court of Appeals of Kentucky, 1906)
Barber Asphalt Paving Co. v. Watt
26 So. 70 (Supreme Court of Louisiana, 1899)
Barber Asphalt Paving Co. v. City of St. Paul
224 F. 842 (Eighth Circuit, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
126 So. 214, 169 La. 852, 1930 La. LEXIS 1607, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fresh-oliveira-v-city-of-new-orleans-la-1930.