Fremont Community Digester LLC v. Demaria Building Company Inc

CourtMichigan Court of Appeals
DecidedJune 25, 2015
Docket320336
StatusUnpublished

This text of Fremont Community Digester LLC v. Demaria Building Company Inc (Fremont Community Digester LLC v. Demaria Building Company Inc) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fremont Community Digester LLC v. Demaria Building Company Inc, (Mich. Ct. App. 2015).

Opinion

STATE OF MICHIGAN

COURT OF APPEALS

FREMONT COMMUNITY DIGESTER, L.L.C., UNPUBLISHED June 25, 2015 Plaintiff-Appellant,

V No. 320336 Oakland Circuit Court DEMARIA BUILDING COMPANY, INC., LC No. 2013-134997-CZ

Defendant-Appellee.

Before: METER, P.J., and CAVANAGH and WILDER, JJ.

PER CURIAM.

Plaintiff, Fremont Community Digester, LLC, appeals as of right the trial court’s order granting summary disposition in favor of defendant, Demaria Building Company, Inc. We affirm.

In December 2010, plaintiff and defendant entered into an engineering procurement and construction contract for a construction project in Fremont, Michigan. The contract provided that all disputes were to be submitted to arbitration “in accordance with the Construction Industry Rules of Arbitration [(‘CIRA’)] of the American Arbitration Association [(‘AAA’)] (and with the procedural law of the State of Michigan in matters as to which such Rules of Arbitration are Silent).”

After various disputes arose, the parties entered into another agreement, referred to as the “Letter Agreement,” which specifically delineated the manner in which they would address their disputes through arbitration. The Letter Agreement provided that a single arbitrator, agreed to by the parties, would decide the parties’ disputes. The “Letter Agreement” provided, in relevant part:

This letter will set forth our agreement to arbitrate certain disputes now pending between DeMaria Building Company and Fremont Community Digester.

* * *

The parties have agreed that the arbitration will be conducted in accordance with the current version of the Construction Industry Arbitration Rules promulgated by the American Arbitration Association (the “Rules”) and in accordance with Michigan law. . . .

-1- The parties have agreed to submit certain defined disputes for resolution by the arbitrator and have agreed to be bound by the arbitrator’s decision in accordance with the Rules and the applicable law. . . . The arbitrator’s decision shall be conclusive only of the matters actually submitted to the arbitrator for decision and the parties will not be precluded from raising other issues in the future, so long as those issues were not previously presented to the arbitrator. Prior to the close of the hearings, the arbitrator shall identify the issues upon which he expects to render a decision and such list shall be dispositive of the issues actually presented to, and resolved by, this arbitration.

The arbitrator issued a decision resolving the parties’ disputes, and the award was satisfied. Defendant thereafter made a demand for arbitration of additional claims that were not previously decided by the arbitrator. Defendant argued that the newly disputed claims were subject to the Letter Agreement, whereas plaintiff maintained that the newly disputed claims were outside the scope of the Letter Agreement and should instead be governed by the terms of the parties’ original arbitration agreement (which required a three-member arbitration panel). The arbitrator decided the matter by concluding that the newly disputed claims were subject to the Letter Agreement.

Plaintiff filed this action in circuit court, contending that the arbitrator exceeded his authority, and acted contrary to law, by deciding, as a threshold question of arbitrability, whether the newly disputed claims were within the scope of the Letter Agreement. Plaintiff requested that the circuit court vacate the arbitrator’s order and issue a declaratory ruling stating the parties’ rights and duties under the Letter Agreement and declaring that the newly disputed claims were not within the scope of arbitration contemplated by the Letter Agreement.

The parties filed cross-motions for summary disposition. Plaintiff moved for summary disposition under MCR 2.116(C)(10), arguing that (1) as a matter of law, the arbitrator erred in ruling that he had jurisdiction to determine the threshold question regarding the scope of the Letter Agreement, and (2) even if the arbitrator had the authority to decide that question, he erred in ruling that defendant’s new claims were within the scope of the Letter Agreement. In response, defendant moved for summary disposition in its favor under MCR 2.116(C)(7), (8), and (10), arguing that the arbitrator’s June 19, 2013 decision was correct and enforceable, and that it was entitled to judgment in its favor based on principles of waiver and estoppel.

The circuit court granted summary disposition in favor of defendant, holding that the arbitrator acted within his authority to determine the scope and application of the parties’ Letter Agreement, and that plaintiff failed to demonstrate that the arbitrator legally erred in ruling that the newly disputed claims were within the scope of the parties’ Letter Agreement. The circuit court first concluded that plaintiff was not disputing that the new claims were subject to arbitration, but, instead, was only contesting the procedure for resolving those claims in arbitration, which the circuit court determined was a matter for the arbitrator to decide. The circuit court noted that both the parties’ original agreement and the Letter Agreement stated that arbitration was to be governed by the CIRA, which authorized the arbitrator to decide matters regarding his jurisdiction and objections regarding the scope or validity of the arbitration agreement. Second, the circuit court declined to disturb the arbitrator’s substantive decision

-2- regarding the scope of the Letter Agreement on the basis that plaintiff had not shown that the arbitrator’s decision was legally erroneous.

This Court reviews de novo a trial court’s decision regarding a motion for summary disposition. Jesperson v Auto Club Ins Ass’n, 306 Mich App 632, 639; 858 NW2d 105 (2014). The circuit court did not specify under which subrule it granted summary disposition, but it appears that it granted summary disposition in favor of defendant under MCR 2.116(C)(7), which provides that summary disposition is appropriate where a claim is barred because of an agreement to arbitrate. A motion under MCR 2.116(C)(7) is reviewed under the following standards:

A defendant who files a motion for summary disposition under MCR 2.116(C)(7) may (but is not required to) file supportive material such as affidavits, depositions, admissions, or other documentary evidence. MCR 2.116(G)(3); Patterson v Kleiman, 447 Mich 429, 432; 526 NW2d 879 (1994). If such documentation is submitted, the court must consider it. MCR 2.116(G)(5). If no such documentation is submitted, the court must review the plaintiff ’s complaint, accepting its well-pleaded allegations as true and construing them in a light most favorable to the plaintiff. [Turner v Mercy Hosps & Health Servs of Detroit, 210 Mich App 345, 348; 533 NW2d 365 (1995); see also Linton v Arenac Co Rd Comm, 273 Mich App 107, 111-12; 729 NW2d 883 (2006).]

If the pleadings or other documentary evidence reveal that there is no genuine issue of material fact, the court must decide as a matter of law whether the claim is barred. Linton, 273 Mich App at 111-112. The existence and enforceability of an arbitration agreement is a question of law that this Court reviews de novo. Michelson v Voison, 254 Mich App 691, 693-694; 658 NW2d 188 (2003).

Plaintiff argues that the arbitrator exceeded his powers by determining whether the newly disputed claims were subject to the parties’ Letter Agreement. “Arbitrators exceed their powers whenever they act beyond the material terms of the contract from which they draw their authority or in contravention of controlling law.” Miller v Miller, 474 Mich 27, 30; 707 NW2d 341 (2005). Arbitration is a matter of contract, and the terms of the parties’ agreement dictate the arbitrator’s authority. Id. at 32.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Miller v. Miller
707 N.W.2d 341 (Michigan Supreme Court, 2005)
Madison District Public Schools v. Myers
637 N.W.2d 526 (Michigan Court of Appeals, 2001)
Fromm v. Meemic Insurance
690 N.W.2d 528 (Michigan Court of Appeals, 2005)
Michelson v. Voison
658 N.W.2d 188 (Michigan Court of Appeals, 2003)
Bennett v. Shearson Lehman-American Express, Inc
423 N.W.2d 911 (Michigan Court of Appeals, 1987)
Patterson v. Kleiman
526 N.W.2d 879 (Michigan Supreme Court, 1994)
Linton v. Arenac County Road Commission
729 N.W.2d 883 (Michigan Court of Appeals, 2006)
Turner v. Mercy Hospitals & Health Services
533 N.W.2d 365 (Michigan Court of Appeals, 1995)
Beattie v. Autostyle Plastics, Inc
552 N.W.2d 181 (Michigan Court of Appeals, 1996)
Arrow Overall Supply Company v. Peloquin Enterprises
323 N.W.2d 1 (Michigan Supreme Court, 1982)
Bayati v. Bayati
691 N.W.2d 812 (Michigan Court of Appeals, 2005)
Washington v. Washington
770 N.W.2d 908 (Michigan Court of Appeals, 2009)
Michigan State Employees Ass'n v. Department of Mental Health
444 N.W.2d 207 (Michigan Court of Appeals, 1989)
City of Ann Arbor v. American Federation of State Employees Local 369
771 N.W.2d 843 (Michigan Court of Appeals, 2009)
Jesperson v. Auto Club Insurance
858 N.W.2d 105 (Michigan Court of Appeals, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
Fremont Community Digester LLC v. Demaria Building Company Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fremont-community-digester-llc-v-demaria-building-company-inc-michctapp-2015.