Fred Weisheit v. Triple J Plumbing LLC (mem. dec.)

Indiana Court of Appeals·Decided August 31, 2018·No. 33A01-1709-SC-2098·Published

Opinion

MEMORANDUM DECISION Pursuant to Ind. Appellate Rule 65(D), this Memorandum Decision shall not be FILED regarded as precedent or cited before any Aug 31 2018, 8:35 am court except for the purpose of establishing CLERK

the defense of res judicata, collateral Indiana Supreme Court Court of Appeals

estoppel, or the law of the case. and Tax Court

APPELLANT PRO SE ATTORNEY FOR APPELLEE Fred Weisheit Joel E. Harvey New Castle, Indiana Hayes Copenhaver Crider Harvey, LLP

New Castle, Indiana

IN THE

COURT OF APPEALS OF INDIANA

Fred Weisheit, August 31, 2018 Appellant, Court of Appeals Case No.

33A01-1709-SC-2098

v. Appeal from the Henry Circuit Court

Triple J Plumbing LLC, The Honorable Bob A. Witham, Appellee. Judge Trial Court Cause No.

33C03-1606-SC-0462

Brown, Judge.

Court of Appeals of Indiana | Memorandum Decision 33A01-1709-SC-2098 | August 31, 2018 Page 1 of 9

[1] Fred Weisheit, pro se, appeals the judgment of the small claims court against him. We affirm.

Procedural History

[2] Triple J Plumbing, LLC (“Triple J”) was hired by Progress Rail in 2014 in connection with a sewer project to separate the sanitary sewer from the storm water system in Muncie, Indiana. Triple J hired Weisheit d/b/a Fred’s Excavating as a subcontractor to perform certain work related to the project for $51,078.14. In January 2015, Triple J paid Weisheit $43,078.14. Weisheit sent an invoice to Triple J dated July 30, 2015, in the amount of $20,613.55 which listed $8,000 for the balance on account and included interest and additional charges.1 Counsel for Triple J sent a letter dated August 10, 2015, to Weisheit stating that Triple J had paid $43,087.14 and that $8,000 was withheld pending completion of the project; that Weisheit abandoned the project with the work not yet completed on July 23, 2015; that, after Weisheit left the project, Triple J discovered the sewer line he had installed was too high in areas and as a result 250 feet of pipe had to be reinstalled; that Triple J never agreed to pay the additional charges listed in Weisheit’s invoice; that Triple J incurred expenses as a result of Weisheit’s abandonment of the project prior to its completion; and that Triple J wished to resolve the matter amicably and was willing to allow

1 The additional charges listed on Weisheit’s invoice included, among other items, training of pipe layers in the amount of $500, excavator fees for forty hours due to training and delays in the amount of $8,000, and skid-steer fees for forty hours in the amount of $3,000.

Court of Appeals of Indiana | Memorandum Decision 33A01-1709-SC-2098 | August 31, 2018 Page 2 of 9

Weisheit to perform the grading, backfill, asphalt repairs and other work within the original scope of the project work that remained to be completed.

[3] On June 22, 2016, Weisheit filed a Notice of Small Claim alleging that Triple J owed an outstanding balance to him. On July 13, 2016, Triple J filed a counterclaim against Weisheit.

[4] The small claims court held a trial over two days. Weisheit testified that he and Triple J entered into an agreement on a sewer separation project, most of the project was completed when he sent Triple J an invoice, Triple J did not pay the full invoice, that he understood “that some was being held back for retainage for the finish work,” that he “completed the finish work up to a certain extent,” and that he was told to leave the property. Transcript Volume II at 6. On cross-examination, when asked if he was responsible for ensuring the holes were dug to a proper elevation, Weisheit replied that he was never given the proper elevations on a blueprint. He indicated he was responsible for backfilling but not for the bedding of the pipe and that he performed all the work he was retained to perform except for grade work in one small area. The court asked if there was a written agreement between the parties, and Weisheit replied “[w]e did a lot it over text messages and just verbal over the phone.” Id. at 9. Weisheit also presented the testimony of his employee Sam Banta, who agreed that Weisheit’s scope of work included digging and backfilling only. When asked if Weisheit was required to do “anything pertaining to installation of the pipe or the elevation of the pipe,” Banta answered: “No. We wasn’t

Court of Appeals of Indiana | Memorandum Decision 33A01-1709-SC-2098 | August 31, 2018 Page 3 of 9 supposed to. We did the jump down in the hole and helped them do it because they didn’t know how to do it.” Id. at 13.

[5] Triple J presented the testimony of Nathan Jones who testified that he worked for Progress Rail and that, on July 23, 2015, he was informed that Weisheit was not dressed properly in accordance with Progress Rail’s safety rules, he went out and asked Weisheit if he had pants in his truck that he could wear, and Weisheit responded that he did not and that, if he had to leave to obtain pants, he was not coming back.

[6] Terrence Whitehead, the principal of Triple J, testified that he gave a depiction of the project area to Weisheit at some point which showed the existing manholes and combined sewer, the new lines to be installed, and an area that contained soil contaminants which would be addressed by another company. Whitehead testified that he and Weisheit visited the site before Triple J submitted a quote to Progress Rail, they knew the “elevations were very critical” as the line to be installed needed to slope downward very gradually as it extended away from the building, and they used a laser and “shot elevations together.” Id. at 31. When asked to describe the specific work Weisheit was retained to perform, Whitehead explained that Weisheit was retained to excavate all soil, to provide shoring, to verify the trench was dug at the correct elevation and “his guy shot the elevation,” to backfill the trench, to provide all asphalt patching and curb work where necessary, and to provide final grade and seeding. Id. at 32.

Court of Appeals of Indiana | Memorandum Decision 33A01-1709-SC-2098 | August 31, 2018 Page 4 of 9

[7] Whitehead testified that, on July 23, 2015, Weisheit was asked to leave the site because he was not wearing long pants as required, did not return to the site, and demanded payment. He indicated that, at that time, over a hundred feet of sewer line remained to be installed and asphalt needed to be patched. Whitehead indicated that he discovered defects in Weisheit’s work, namely, that the trench line was approximately eighteen inches too high, which necessitated Triple J to “dig the pipe back up clear back to the manhole and re- core drill it and relay all the pipe.” Id. at 48. Whitehead referenced photographs of the site, noted that one of the pipes should have been flowing into a manhole, and testified that Triple J had to re-core drill a hole through the manhole at the correct elevation, dig the ditch approximately twelve to eighteen inches deeper, and lower all of the piping. Whitehead testified that Triple J incurred costs as a result of Weisheit leaving the job site in the amount of $9,792.50 as itemized in an account detail introduced as Defendant’s Exhibit 13. The account detail included itemized charges for equipment, labor to remove piping, install lines, backfill a trench, grade and seed, and legal fees. On cross-examination, Whitehead reiterated that Weisheit was responsible for “the shooting of the laser” and to “establish the bottom of the ditch.” Id. at 55. The court asked Weisheit if he had any further testimony he wished to offer, and Weisheit stated that he was contracted to perform digging and backfilling, that Triple J was to install the pipe and the bedding of the pipe, and that he believed Whitehead was blaming him for the incorrect installation of the pipe when that was not part of his job.

Court of Appeals of Indiana | Memorandum Decision 33A01-1709-SC-2098 | August 31, 2018 Page 5 of 9

Free access — add to your briefcase to read the full text and ask questions with AI

Fred Weisheit v. Triple J Plumbing LLC (mem. dec.), (Ind. Ct. App. 2018).

Fred Weisheit v. Triple J Plumbing LLC (mem. dec.) (Fred Weisheit v. Triple J Plumbing LLC (mem. dec.)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Conwell v. Gray Loon Outdoor Marketing Group, Inc.
906 N.E.2d 805 (Indiana Supreme Court, 2009)
Yanoff v. Muncy
688 N.E.2d 1259 (Indiana Supreme Court, 1997)
McLinden v. Coco
765 N.E.2d 606 (Indiana Court of Appeals, 2002)
Eagle Aircraft, Inc. v. Anthony Trojnar
983 N.E.2d 648 (Indiana Court of Appeals, 2013)
Wesley McDivitt v. Sue McDivitt
42 N.E.3d 115 (Indiana Court of Appeals, 2015)
Larry J. Jernas and R & R Horse Haven, Inc. v. Kevin J. Gumz
53 N.E.3d 434 (Indiana Court of Appeals, 2016)