Fraser, George & Beth v. George Williams D/B/A Baybrook Building Co.,Inc.
This text of Fraser, George & Beth v. George Williams D/B/A Baybrook Building Co.,Inc. (Fraser, George & Beth v. George Williams D/B/A Baybrook Building Co.,Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Court of Appeals
For The
First District of Texas
____________
NO. 01-02-00290-CV
GEORGE AND BETH FRASER, Appellants
V.
BAYBROOK BUILDING CO., INC., Appellee
On Appeal from the 212th District Court
Galveston County, Texas
Trial Court Cause No. 99CV0688
Appellants George and Beth Fraser (the Frasers) sued Baybrook Building Company, Inc. (Baybrook) for breach of contract, fraud, conversion, trespass, violations of the Texas Residential Construction Disclosure Statement, and violations of the Texas Deceptive Trade Practices Act (DTPA) (1) in connection with a contract to construct a house. Baybrook counterclaimed for breach of contract, breach of the duty of good faith and fair dealing, unjust enrichment, and tortious interference with the construction contract. Baybrook also claimed a lien on the house and sought judicial foreclosure. A jury found in favor of Baybrook and awarded $81,551 in actual damages and $35,000 in attorney's fees, and the trial court ordered judicial foreclosure on Baybrook's lien to satisfy the judgment.
In seven issues, the Frasers contend that the evidence was factually insufficient to support two of the jury's findings and that the trial court erred by declining to submit a proper jury instruction on damages, ordering a judicial foreclosure on an invalid lien, allowing the proceeds of the foreclosure sale to secure attorney's fees awarded to Baybrook, and declining to award attorney's fees to the Frasers. We modify the judgment and affirm as modified.
Factual & Procedural Background
On June 11, 1998, the Frasers entered into an agreement with Baybrook to have a house built in Galveston County. The plans for the house were drawn up by the Frasers and called for a construction material known as "Rastra" and for steel wall supports, trusses, and roofing shingles. The Frasers hired Saaduddin Ahmed to engineer the plans. Under the proposal, Baybrook agreed to furnish the materials and labor necessary to complete the contemplated construction. Thereafter, on August 7, 1998, Baybrook entered into a mechanic's and materialman's lien contract with the Frasers by which Baybrook agreed to complete construction by July 31, 1999. The Frasers negotiated a loan with Colonial Savings (Colonial) in the amount of $259,500 to secure Baybrook's services.
After experiencing several delays, Baybrook was unable to complete construction by the July 1999 deadline. The Frasers sued Baybrook, seeking damages for the loss of a loan commitment at a favorable interest rate, the cost of completing the construction in a good and workmanlike manner, mental anguish, diminished market-value of the property, and attorney's fees. Baybrook counterclaimed, seeking damages for the unpaid balance due under the contract, interest on the unpaid balance, and attorney's fees. The case was tried to a jury.
The jury found that (1) Baybrook complied with its proposal with the Frasers, (2) Baybrook did not complete construction of the house in a good and workmanlike manner, (3) Baybrook's failure to complete construction in a good and workmanlike manner was not the proximate cause of the Frasers' damages, (4) the Frasers were not entitled to recover attorney's fees, (5) Baybrook substantially performed under the June 11, 1998 proposal, (6) Baybrook was entitled to recover $81, 551 under the June 11, 1998 proposal, and (7) Baybrook was entitled to recover $35,000 in attorney's fees. The trial court entered judgment in accordance with the jury's findings and ordered judicial foreclosure of Baybrook's mechanic's and materialman's lien to satisfy the judgment. The Frasers subsequently filed this appeal.
Factual Sufficiency
In their sixth and seventh issues, the Frasers argue that the judgment should be reversed because the evidence was factually insufficient to support the jury's findings that (1) Baybrook complied with the June 11, 1998 proposal and (2) Baybrook's failure to complete construction in a good and workmanlike manner was not the proximate cause of the Frasers' damages.
We will sustain a factual sufficiency challenge only if, after viewing all the evidence, the evidence is so weak or the verdict so contrary to the overwhelming weight of the evidence as to be clearly wrong and unjust. Cain v. Bain, 709 S.W.2d 175, 176 (Tex. 1986). As we examine the evidence, we remain mindful that the jury is the sole judge of witness credibility and the weight to be given testimony. McGalliard v. Kuhlmann, 722 S.W.2d 694, 697 (Tex. 1986). The jury may believe one witness and disbelieve another and resolve inconsistencies in any testimony. Id. This Court cannot substitute its opinion for that of the trier of fact or determine that it would have weighed the evidence differently or reached a different conclusion. Hollander v. Capon, 853 S.W.2d 723, 726 (Tex. App.--Houston [1st Dist.] 1993, writ denied).
A. Compliance Under the June 11, 1998 Proposal
Seventeen witnesses testified at trial. There was some testimony that (1) the house was not completed in a timely manner, (2) the house failed inspection, (3) the house had various construction problems, and (4) the Frasers were forced to hire additional contractors to correct and complete Baybrook's faulty work. The Frasers contend that this testimony established that Baybrook did not comply with the June 11, 1998 proposal.
Other testimony, however, reflects that (1) the Frasers prevented Baybrook from obtaining a final inspection on the house, (2) the Frasers would not allow Baybrook to install a water heater in accordance with the Frasers' design, (3) the Frasers prevented Baybrook from obtaining a gas permit, (4) the Frasers discharged Baybrook before it could complete construction, (5) the Frasers prevented Baybrook from passing the final inspection of the house, (6) Baybrook "basically finished" construction on the house, and (7) problems existed with the Frasers' house design calling for "Rastra" in combination with a steel truss system. Baybrook contends that this testimony established that any faulty construction resulted from the Frasers' substandard plans and their interference with Baybrook's completing the house.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
Fraser, George & Beth v. George Williams D/B/A Baybrook Building Co.,Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/fraser-george-beth-v-george-williams-dba-baybrook--texapp-2003.