FRASER ENGINEERING CO. v. Desmond

524 N.E.2d 110, 26 Mass. App. Ct. 99, 1988 Mass. App. LEXIS 387
CourtMassachusetts Appeals Court
DecidedJune 6, 1988
Docket87-1050
StatusPublished
Cited by18 cases

This text of 524 N.E.2d 110 (FRASER ENGINEERING CO. v. Desmond) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
FRASER ENGINEERING CO. v. Desmond, 524 N.E.2d 110, 26 Mass. App. Ct. 99, 1988 Mass. App. LEXIS 387 (Mass. Ct. App. 1988).

Opinion

Grant, J.

The defendant is a real estate developer who at all material times was engaged in the renovation of an elderly seaside mansion in Dartmouth and its conversion into individual apartments which would be sold to the public as condominium *100 units. To that end he entered into a general contract with Homar, Inc. (Homar), for the performance of most of the work which would be required in the course of the renovation and conversion. Homar entered into a subcontract with Denron Plumbing and Heating Co., Inc. (Denron), for the performance of the necessary heating work. Some time after Denron had undertaken the performance of its portion of the work, the basement of the mansion was flooded and substantial damage was done to the work and equipment supplied by Denron, as well as to the work and equipment supplied by other subcontractors engaged in various trades. The flooding may have resulted from the negligence of one Piva, who had been employed by the defendant directly to perform the necessary site preparation and landscaping.

At some point following the award of the heating subcontract to Denron but prior to the flooding, the principal of Denron, one Rowan, requested the principal of the plaintiff, one Fraser, to formulate and submit to Denron a proposal for the post-construction maintenance of the equipment which was to be installed by Denron. Fraser submitted such a proposal, but it was not accepted. After the flooding Rowan asked Fraser to examine the damage, to make recommendations as to what would be required to repair the damage, and to submit a proposal for whatever work and equipment might be required. Fraser revisited the site and examined the damage in the presence of Rowan, a representative of the mechanical engineer employed by the architect, and one Bettencourt, who was the defendant’s project manager and who had been directed by him to oversee the repair or replacement of all the damaged material and equipment. Fraser inquired as to who would be the other contracting party and as to who would be responsible for paying the plaintiff if its proposal were to be accepted. Rowan, in the presence of Bettencourt, responded that the plaintiff would be paid from the proceeds of the defendant’s claim under his builder’s risk insurance but that the actual *101 contract would be issued by Denron. Bettencourt remained silent throughout this portion of the conversation. 2

The plaintiff’s proposal was accepted, and it entered into a written agreement with Denron for the reconditioning of two existing boilers, the installation of two new oil burners, and the installation of various electronic controls. 3 This was the first time the plaintiff had entered into a contractual relationship with Denron. The plaintiff performed the agreement in workmanlike fashion and demanded payment from Denron, which put the plaintiff off on the ground that it (Denron) had not received payment from Homar. That was not a legitimate excuse because the plaintiff’s right to receive payment from Denron was not conditioned on the latter’s first receiving payment from Homar.

The plaintiff then demanded payment from the defendant. Unbeknownst to the plaintiff, the defendant had decided not to seek recovery of its losses from his builder’s risk insurer but to pursue Piva’s liability insurer instead. 4 Following the completion of the plaintiff’s work the defendant received from *102 Piva’s insurer a partial payment of his total claim in an amount which was in excess of what was owed the plaintiff. 5 The defendant pocketed the insurance proceeds and refused to make any part of them available to the plaintiff. Three reasons were given. The first was that the defendant was under no contractual obligation to the plaintiff, which was correct so far as it was based on the fact that the plaintiff was not included in the original structure of the general contract and the Denron subcontract (see note 3, supra) but ignored the defendant’s potential liability to the plaintiff arising out of the assurance that the plaintiff would be paid from the insurance recovery. The second reason for the refusal was that the defendant was by then engaged in a dispute with Homar and was entitled to retain the insurance proceeds because Homar had failed to perform the general contract, which also ignored the fact that the plaintiff was not part of the original contract structure. The third reason was that it would not be fair to pay the plaintiff at the expense of the other subcontractors, which ignored the facts (a) that the plaintiff was not one of the original subcontractors and (b) that it did not appear that the defendant had promised to pay any of the original subcontractors from any insurance proceeds which might be recovered.

The plaintiff brought suit against Denron and the defendant in the Superior Court. The first count of the amended complaint alleged a breach of the agreement between the plaintiff and Denron arising out of the latter’s failure to pay the plaintiff the agreed price for its work and equipment. The second count was directed to the defendant and proceeded on a theory that the defendant had been unjustly enriched at the expense of the plaintiff to the extent of the fair value of the labor, material and equipment supplied by the plaintiff. The plaintiff obtained a summary judgment against Denron for the full amount of its claim, which Denron paid. The plaintiff then went forward on the count against the defendant to recover from him the reason *103 able amount of the attorney’s fees expended by the plaintiff in pursuing Denron. The case against the defendant was tried on the theory that the attorney’s fees had necessarily been incurred as a result of the unfair and deceptive acts of the defendant (G. L. c. 93A, §§ 2[a] and 11) in assuring the plaintiff that it would be paid from insurance proceeds and then refusing to pay the plaintiff from that or any other source. An experienced judge of the Superior Court found and ruled that the defendant’s conduct had been both unfair and deceptive within the meaning of §§ 2(a) and 11 and caused the entry of judgment for the plaintiff in an amount which is not contested. The defendant appealed, urging error in so much of the judgment as determined liability.

Neither the provisions of G. L. c. 93A, § 2(a), nor those of G. L. c. 93A, § 11, contain a definition of an unfair act or practice. Both leave the possible existence of such to be determined on a case-by-case basis. See Commonwealth v. DeCotis, 366 Mass. 234, 241, 242 (1974); Purity Supreme, Inc. v. Attorney Gen., 380 Mass. 762, 771 (1980); Levings v. Forbes & Wallace, Inc., 8 Mass. App. Ct. 498, 504 (1979). The judge, in finding that the defendant had committed an unfair act within the meaning of § 2(a), relied on the general definition of unfairness which was first approved in PMP Associates, Inc. v. Globe Newspaper Co., 366 Mass. 593, 596 (1975), and later fleshed out in Purity Supreme, Inc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Porter
498 B.R. 609 (E.D. Louisiana, 2013)
Baker v. Goldman Sachs & Co.
949 F. Supp. 2d 298 (D. Massachusetts, 2013)
Newly Wed Foods, Inc. v. Superior Nut Co.
26 Mass. L. Rptr. 602 (Massachusetts Superior Court, 2010)
In Re Pharm. Industry Average Wholesale Price Lit.
582 F.3d 156 (First Circuit, 2009)
Markarian v. Connecticut Mutual Life Insurance
202 F.R.D. 60 (D. Massachusetts, 2001)
Mitchell v. Money Store Massachusetts, Inc.
12 Mass. L. Rptr. 348 (Massachusetts Superior Court, 2000)
Mulligan v. Choice Mortgage
D. New Hampshire, 1998
E.D.S. Federal Corp. v. System Development Corp.
8 Mass. L. Rptr. 691 (Massachusetts Superior Court, 1998)
Sebago, Inc. v. Beazer East, Inc.
18 F. Supp. 2d 70 (D. Massachusetts, 1998)
Grekin v. Baer
6 Mass. L. Rptr. 489 (Massachusetts Superior Court, 1997)
Moynihan-North Reading Lumber, Inc. v. Burke
1996 Mass. App. Div. 143 (Mass. Dist. Ct., App. Div., 1996)
Commonwealth v. Amcan Enterprises, Inc.
5 Mass. L. Rptr. 53 (Massachusetts Superior Court, 1996)
Hogan v. Riemer
619 N.E.2d 984 (Massachusetts Appeals Court, 1993)
Underwood v. Risman
605 N.E.2d 832 (Massachusetts Supreme Judicial Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
524 N.E.2d 110, 26 Mass. App. Ct. 99, 1988 Mass. App. LEXIS 387, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fraser-engineering-co-v-desmond-massappct-1988.