Fraser Construction Co. v. United States

57 Fed. Cl. 56, 2003 U.S. Claims LEXIS 166, 2003 WL 21513046
CourtUnited States Court of Federal Claims
DecidedJune 25, 2003
DocketNo. 95-435C
StatusPublished
Cited by3 cases

This text of 57 Fed. Cl. 56 (Fraser Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fraser Construction Co. v. United States, 57 Fed. Cl. 56, 2003 U.S. Claims LEXIS 166, 2003 WL 21513046 (uscfc 2003).

Opinion

DECISION ON REMAND

WIESE, Judge.

This contract action is before the court following a trial, held in St. Paul, Minnesota, from April 30 to May 3, 2002, then resuming from October 8 to October 10, 2002.

The contract at issue was awarded to plaintiff, Fraser Construction Company, on February 17, 1993, by the Army Corps of Engineers (“the Corps”) for flood control [57]*57work involving a section of the South Fork Zumbro River in Rochester, Minnesota, referred to as Silver Lake. Plaintiff began work on the project on May 17, 1993, and the contract was scheduled to be completed by September 1, 1993. During the months of June, July, and August, however, plaintiff experienced adverse weather conditions and high water flows that impeded its progress.

In response to those conditions, plaintiff repeatedly sought both time extensions and additional contract compensation to complete the project. With regard to the time extensions sought for unusually severe weather, the Corps granted 33 of the days sought. With regard to the time extensions based on high water flows, however, the Corps denied all claims. The Corps additionally refused all requests for increased compensation.

Plaintiff brought suit in this court on June 29, 1995, seeking the additional days and funding it had been denied. In a May 12, 1998, decision, the court concluded that the high water flows of which plaintiff had complained did not result in an excusable delay since they constituted neither unusually severe weather nor a flood as those terms were used in the contract’s default clause (section 1.83). Fraser Constr. Co. v. United States, No. 95-435C (Ct.Fed.Cl. May 12, 1998) (granting defendant’s motion for summary judgment).

On appeal, the Federal Circuit rejected the trial court’s conclusion. Fraser Constr. Co. v. United States, No. 98-5136, 1999 WL 507148 (Fed.Cir. July 15, 1999). The court explained that the conditions listed in the contract’s default clause were illustrative rather than exclusive and, thus, that unusually high water flows could be found to constitute excusable delay even if they did not fall into the category of either a flood or unusually severe weather. Fraser, 1999 WL 507148, *2. The action was therefore remanded to this court for a determination of “whether Fraser established a right to excusable delay under section 1.83 based on an unforeseeable rate of water in the river leading to inundation of the lake bed for an extended time during the performance period.” Id. That determination, in the Federal Circuit’s view, rested on three issues to be considered on remand: (i) whether the high water flows experienced at the project site constituted an excusable delay under section 1.83; (ii) whether plaintiff submitted timely requests for relief; and (iii) whether plaintiffs design of its diversion system contributed to or caused the difficulties plaintiff encountered.

After carefully considering the evidence presented, we now conclude that: (i) plaintiff should have anticipated the instantaneous peak flows experienced at the project site based on the available hydrographic data and, thus, cannot rely on high water flows as a basis for an excusable delay; (ii) plaintiff is additionally ineligible for relief since it failed to give the Corps correct information about its dam capacity, a crucial aspect of its claim; and (iii) the Corps, although it frequently expressed concern about the progress of the work, always timely acknowledged and granted the contractor’s requests for weather-based time extensions, and thus its actions cannot support a claim of constructive acceleration. Accordingly, we hold that plaintiff is not entitled to recovery in this action.

FACTS

On December 11, 1992, the Corps issued a solicitation for the dredging and disposal of an estimated 109,000 cubic yards of material from Silver Lake. Although the solicitation did not specify the method by which the project site was to be excavated, it provided for the drawing down of Silver Lake from its normal elevation, no earlier than May 1, 1993, in order to facilitate the dredging.

In response to the solicitation, plaintiff submitted a proposal that called for the construction of a cofferdam to divert the river from its natural course, thereby allowing plaintiff to excavate the material on the land side of the dam “in the dry.” Toward that end, plaintiff proposed the use of bulldozers and backhoes to excavate the river-bottom material and trucks to haul the material to the disposal site. In total, plaintiff anticipated a 46-day excavation period, to run from May 31 through August 22, 1993 (including 13 anticipated adverse weather days) with a ten-hour-per-day, five-day work week and a project completion date of September 1, 1993.

[58]*58The Corps awarded plaintiff the contract on February 17, 1993, for a fixed price of $744,585. Pursuant to the contract schedule, the Corps commenced the drawing down of Silver Lake on May 1, 1993, and plaintiff began work on the project on May 17, 1993. On May 31, just after plaintiff had begun construction of the upstream section of its diversion dam, however, elevated river flows, on the order of 1,320 cubic feet per second (cfs), overtopped the yet-to-be completed diversion system and flooded the work site. As a result, plaintiff spent much of the next two weeks repairing the diversion system, a task made more difficult by sustained high river flows and the saturation of the material used to rebuild the cofferdam.1 Shortly after plaintiff completed the repair work on its diversion system, however, the project was again inundated, this time by peak flows of 3,170 cfs on June 17 and 3,680 cfs on June 18.

Seeking relief for the flooded site conditions, Rick Penz, plaintiffs president, sought permission to suspend operations until the waters had receded, a request that was orally denied at a June 24, 1993, meeting with the Corps. In a follow-up letter of that same date, Mr. Penz acknowledged that “the peaks of 1320 cfs [on May 31,1993] and 1610 cfs [on June 8, 1993] were within what has to be considered the usual nature inherent to this site,” but went on to note that “the 3680 cfs flow on 6-18-93 (which overtopped our dike by .88 ft) is considered by us to be in excess of what would ordinarily be encountered as determined by a point falling outside the 2000 cfs, 25th percentile on the monthly instantaneous peaks graph provided in the contract documents.” Plaintiff accordingly sought an equitable adjustment in both time and money for the extra work resulting from the June 18,1993, flow.

In a June 28, 1993, response to plaintiffs request, the Corps directed plaintiff to identify, inter alia, what it had anticipated by way of flows, how the flows it actually experienced differed from those it had expected, and what damages had resulted. By letter dated July 6, 1993, plaintiff replied that the normal range for flows were those occurring with more than a 25 percent probability and contended that there was a mere 4 percent chance that flows at the project site would meet or exceed 800 cfs. Plaintiff went on to itemize its damages, including increased labor costs and the costs of additional equipment.

A series of exchanges followed throughout July and August, with plaintiff maintaining that it was due additional time and money for difficulties it encountered at the work site, and with the Corps repeatedly asking for information to support plaintiffs claim.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Edge Construction Co. v. United States
95 Fed. Cl. 407 (Federal Claims, 2010)
Fraser Construction Company v. United States
384 F.3d 1354 (Federal Circuit, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
57 Fed. Cl. 56, 2003 U.S. Claims LEXIS 166, 2003 WL 21513046, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fraser-construction-co-v-united-states-uscfc-2003.