Franks v. City of Aurora

362 P.2d 561, 147 Colo. 25, 1961 Colo. LEXIS 465
CourtSupreme Court of Colorado
DecidedJune 5, 1961
Docket19492
StatusPublished
Cited by19 cases

This text of 362 P.2d 561 (Franks v. City of Aurora) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Franks v. City of Aurora, 362 P.2d 561, 147 Colo. 25, 1961 Colo. LEXIS 465 (Colo. 1961).

Opinion

Opinion by

Mr. Justice Doyle.

The controversy before us arises from an action in which three plaintiffs, landowners, claimed damages for flooding from the plaintiffs in error and the City of Aurora, named as a co-defendant. In that cause the City of Aurora (here referred to as Aurora or City) filed a cross claim against the plaintiffs in error (here referred to as defendants). All issues in the case were settled except those between Aurora and the defendants. This latter litigation resulted in a judgment in favor of Aurora and against defendants in the amount of $4,000.

The facts are not disputed. Aurora owned a parcel of unimproved property which is here called “the lots.” *27 Abutting such lots at opposite boundaries was a city-owned and maintained drainage culvert underground in the form of a 6 foot by 9 foot oval-shaped arch, through which drainage waters were conveyed. Connecting this corrugated pipe and crossing the lots involved in this litigation was an open ditch “link.”

In April, 1955, defendants, who were desirous of purchasing the lots, wrote a letter to the City Council proposing to purchase them under terms and conditions as follows:

“We propose to offer $5500.00 for Lots 1-10 and 12-15, Block 36, City of Aurora, Colorado. We plan to build doubles on these lots and we will also connect the two culverts the same as is.” (Underscoring ours.)

On April 18, 1955, the City Council accepted the offer. This is expressed in a resolution which appears in the minutes of the City Council and reads:

“* * * that offer be accepted. Purchaser to place culvert (across Lots 1-3) of the same size as now in Beeler Street.”

Deed of conveyance was issued by the City to the purchasers, and they proceeded to carry out their obligations. They first sought out the City Manager for instructions and approval of their proposed plans and specifications for the culvert to be installed across their lots. The City Manager referred them to the City Engineer. The city engineer after examination rejected their plans and himself designed the pipe which was installed by them. This consisted of a five-foot circular concrete pipe, about sixty-four feet in length. Connection was made at each end with the existing metal arch pipes by inserting the circular concrete pipe into the arch openings, and pouring concrete into the void thus left at the connections, so forming an unbroken, continuing tube. All this was done at the direction and by dictate of the city engineer. The result, of course, was a 64 foot connection between two metal culverts by a smaller tube. Following these procedures, and before covering up the *28 new installation with earth fill, the Engineer made an inspection, found “some minor difficulties” and suggested corrections which, according to the only evidence in the case, were carried out by defendants.

The end result, following heavy rains, was a flooding of the neighborhood, due allegedly to the failure of the smaller connecting link to adequately convey the runoff from the larger pipe, because of accumulation of debris, trash, automobile tires, lumber and litter at the junction of the larger and smaller pipes.

By its cross claim, Aurora alleges that the defendants failed and refused, in a wanton, reckless disregard of the rights and interests of such City, to construct a culvert of the same size as then existed on abutting and adjacent property, and have wantonly and recklessly constructed and installed a culvert of inadequate size and improper design under and across said property; and that if not compelled to do so, the City will suffer great and irreparable injury and damage and a multiplicity of suits. Judgment was asked for $1000 exemplary damages, that the defendants be required to perform their agreement by reconstructing the culvert, or for damages of $7500.00.

Briefly stated, the finding of the trial court was that a contract resulted from the acceptance of the original offer by Aurora which obligated these defendants to place a culvert of the same size as the two connecting ends; that while the defendants may have relied upon authorization or approval in change of specifications by the City Engineer, he, neither in fact nor in law, was shown to have power or authority to vary the specifications, and that if he did the authorization was verbal and not recognizable under the Statute of Frauds. Pursuant to such findings the court adjudged that the defendants proceed to specific performance of the contract as the court found it to be or suffer judgment against them in the amount of $4000. In this the trial court erred.

The part of the contract before us relating to the cul *29 vert construction provided for installation of the pipe “as is” and of the same size as the abutting culverts. Defendants, plainly with a conscious desire to strictly comply, sought out the authorized agent of the other party to the contract, and displayed their plans. That agent did not accept them, rather substituted others. Defendants then proceeded with construction according to the substituted plans of the agent, and having done so, sought again the approval of the other contracting party, the beneficiary of the work. Again, minor repairs were suggested and made, thus completing the project.

In considering whether the undisputed facts result in defendants’ liability, it may be assumed that the engineer had no actual authority to modify the terms of this contract. The council and not the engineer was the contracting authority; the latter could not have entered into the contract in the first instance, hence he was not expressly empowered to materially modify it. Aurora then operated a council-manager form of government. The manager was responsible to council for the administration of all affairs of the city. His duties required him to supervise the carrying out of policies previously set by the council. C.R.S. ’53, 139-6-11, 13. Assuming, therefore, that neither the manager nor the engineer had authority to change the terms of this contract, it is reasonable nevertheless to conclude that the defendants were justified in relying on the authority of the manager and engineer to instruct and supervise the engineering detail incident to the carrying out of this project.

It seems inconceivable that a municipal corporation can virtually supervise every detail of performance of an entire project and can long thereafter repudiate the supervisory authority of its own engineer adopting in retrospect the position that a contracting party should have disregarded the instructions, of its own agent and should have adhered to the original specifications notwithstanding the engineer’s disapproval. As we view it, the undisputed facts support a conclusion of justifiable *30 reliance on the appearance of authority which was exhibited to these defendants.

Does the doctrine of apparent authority or the corrollary principle of equitable estoppel bar a municipal corporation from enforcing an obligation by taking a position contrary to a previous representation relied on by the contracting party to his detriment? City and County of Denver v. Stackhouse, 135 Colo. 289, 310 P. (2d) 296, holds that it does.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carl's Italian Restaurant v. Truck Insurance Exchange
183 P.3d 636 (Colorado Court of Appeals, 2007)
Cherry Creek Aviation, Inc. v. City of Steamboat Springs
958 P.2d 515 (Colorado Court of Appeals, 1998)
Berg v. State Board of Agriculture
919 P.2d 254 (Supreme Court of Colorado, 1996)
Olsen and Brown v. City of Englewood
867 P.2d 96 (Colorado Court of Appeals, 1994)
Jafay v. Board of County Commissioners
848 P.2d 892 (Supreme Court of Colorado, 1993)
Lehman v. City of Louisville
857 P.2d 455 (Colorado Court of Appeals, 1993)
Orsinger Outdoor Advertising, Inc. v. Department of Highways
752 P.2d 55 (Supreme Court of Colorado, 1988)
Ellis v. City of Arvada
695 P.2d 784 (Colorado Court of Appeals, 1984)
Coady v. Worrell
686 P.2d 1375 (Colorado Court of Appeals, 1984)
P-W Investments, Inc. v. City of Westminster
655 P.2d 1365 (Supreme Court of Colorado, 1982)
Kuehn v. Kuehn
642 P.2d 524 (Colorado Court of Appeals, 1981)
Farmers Insurance v. Hopson
631 P.2d 342 (Court of Appeals of Oregon, 1981)
Gray v. Regional Transportation District
602 P.2d 879 (Colorado Court of Appeals, 1979)
Roderick v. City of Colorado Springs
563 P.2d 3 (Supreme Court of Colorado, 1977)
Silverman v. University of Colorado
541 P.2d 93 (Colorado Court of Appeals, 1975)
City of Sheridan v. Keen
524 P.2d 1390 (Colorado Court of Appeals, 1974)
Crawford v. McLaughlin
473 P.2d 725 (Supreme Court of Colorado, 1970)
Wilson v. City and County of Denver
449 P.2d 822 (Supreme Court of Colorado, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
362 P.2d 561, 147 Colo. 25, 1961 Colo. LEXIS 465, Counsel Stack Legal Research, https://law.counselstack.com/opinion/franks-v-city-of-aurora-colo-1961.