Franklin v. Ram, Inc.(Of Arkansas)

576 So. 2d 546, 1991 WL 25799
CourtLouisiana Court of Appeal
DecidedFebruary 27, 1991
Docket22,022-CA
StatusPublished
Cited by7 cases

This text of 576 So. 2d 546 (Franklin v. Ram, Inc.(Of Arkansas)) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Franklin v. Ram, Inc.(Of Arkansas), 576 So. 2d 546, 1991 WL 25799 (La. Ct. App. 1991).

Opinion

576 So.2d 546 (1991)

Wayne FRANKLIN, Plaintiff-Appellee/Appellant,
v.
RAM, INC. (OF ARKANSAS), Defendant-Appellant.

No. 22,022-CA.

Court of Appeal of Louisiana, Second Circuit.

February 27, 1991.

*547 Anthony J. Bruscato, Bruscato, Loomis & Street, Monroe, for plaintiff-appellee/appellant.

John C. Laird, McLeod, Swearingen, Verlander, Price & Noah, Monroe, for defendant-appellant.

Before BAILES, FOOTE and SCOTT, JJ., Ad Hoc.

FOOTE, Judge.

This is an action brought by the plaintiff, Wayne Franklin, against Ram, Inc. to recover the balance allegedly due for unpaid wages and for penalties and attorney's fees due under the provisions of LSA-R.S. 23:631, 632. The trial court awarded plaintiff judgment in the amount of $6,247.36, with judicial interest from date of judicial demand and for costs. Plaintiff's claim for penalties and attorney's fees was denied. From this judgment defendant has appealed. Plaintiff has answered the appeal urging error of the trial court in denying his claim for penalties and attorney's fees.

The issues presented are the amount due plaintiff under basic contract and supplements thereto, and the application of LSA-R.S. 23:631, 632, penalties and attorney's fees.

At the conclusion of trial, the trial court analyzed the three contracts in light of evidence adduced and logically tabulated the gross amount to which plaintiff was entitled, deducted the amount admittedly paid, and rendered judgment for the sum of $6,247.36, with judicial interest and costs. The court denied plaintiff's claim for penalties and attorney's fees, stating that the defendant was not arbitrary or capricious

because admittedly, the whole thing is confused. The plaintiff obviously did not even understand and was confused about what it was ...

We affirm this result though for reasons somewhat different from the trial court.

STATEMENT

Plaintiff was a welding supervisor, specializing in boiler and power plant welding. He had worked for defendant, Ram, Inc., hereinafter "Ram," off and on for a period of thirteen to fifteen years. Ram had a contract for the technical assistance to repair boilers in a large paper mill in Jari, Brazil. This was specialty work requiring Ram to bring some of its specialists such as plaintiff from the United States to Brazil to supervise and instruct the Brazilian nationals who were to do the actual welding.

Plaintiff arrived in Brazil on May 15 or 16, 1988 and finished work on June 24, 1988.

During this time span plaintiff's wages were controlled by three written instruments; the basic contract dated May 2, 1988 (exhibit P-1), the first supplemental contract dated June 1, 1988 (exhibit P-2), and the second supplemental contract dated June 7, 1988 (exhibit P-3). All contracts were prepared by defendant, Ram, the first in the United States, a typewritten two *548 page instrument, and the second two handwritten in Brazil. The two supplemental contracts were necessitated by the unforeseen difficulty in getting production from the native welders. The American supervisors, including plaintiff, were asked to perform additional duties over and above the original assignment.

AMOUNT OF WAGES DUE

The basic contract, P-1, provides for four phases of work, that is pre shut-down, shut-down or agreed fee, post shut-down, and completion delayed payment. The pertinent paragraphs of this contract are as follows:

Dear Employees:

Ram, Inc. ("Ram") is setting forth its understanding of your proposed employment. Please review, sign below and return if you agree with all terms. You will be paid $8,160.00 ("Agreed Fee") for seventeen working days during shutdown of a B & W boiler located in Jari, Brazil. You will be considered a salaried employee of Ram at the executive level employed to instruct and supervise Brazilizn (sic) nationals. You will receive an additional fee of $1,200.00 per week for pre or post shutdown times. If you request Ram will send up to $500.00 per week to your dependants (sic) in the USA; which sum will be deducted from the Agreed Fee.
If completion of this job is delayed in any way by the client, due to circumstances beyond our control or because of additional work that extends the critical path, you will receive an additional fee of $180.00 per day until completion.
All transportation from Monroe, Louisiana to Belem, Brazil and from Belem, Brazil to Monroe, Louisiana will be paid by Ram. Travel pay of $240.00 each way will be paid by Ram....
You will supervise and instruct Brazilian nationals in the replacement of boiler tubes and the installation of smelt spouts with wall panels. Ram will be working two twelve hour shifts for seven days a week during the shutdown....

The trial court found that under this contract plaintiff is entitled to the following: 1) $1,542.86 ($1,200.00 per week) for pre shut-down work done from May 16, 1988, through May 24, 1988 (9 days); 2) $8,160.00 (agreed fee) for work performed from May 25, 1988, through June 10, 1988; 3) $2,340.00 ($180.00 per day) for work performed because completion was delayed, from June 11, 1988 through June 23, 1988 (13 days); and 4) $480.00 for travel expenses to and from Brazil.

The first supplemental contract, P-2, entered into on June 1, 1988, provides as follows:

This is a supplement to original contract for Jari Boiler Repair Job Ram Cont. No. 9380.
Supplement agreement as stated below We Ram, Inc.
Does here by (sic) agree to pay in addition to the original contract $35.00 per hour or $75.00 total per hour for the installation of 4 smelt spout tube panels and smelt spouts, not to exceed 60 hours per man or a total of $2,100.00 per man.

It is agreed by both parties that the 60 hours was worked and that the $2,100.00 was earned by the plaintiff. No dispute exists over P-2.

The second supplemental agreement, entered into on June 7, 1988, states:

Amendment to employee contract for Ram, Inc....
This amendment is to provide for "handson" work to be performed on subject project in addition to supervisory duties being performed. In return for these additional duties, Ram will reimburse employees at the rate of $75 per hour for every hour worked in this capacity.
This amendment is to begin on 6-7-88 and to continue until project is completed or employee is advised that "hands on" duties will no longer be required.

Plaintiff testified that he worked every day performing "hands on" work from the date of this contract, June 7, 1988, through June 23, 1988. Defendant's time sheet corroborates this. Thus, under this contract the trial court found plaintiff to earn $12,750.00. The trial court also awarded *549 $180.00, apparently for the two hours plaintiff worked on June 24, 1988.

A total of the above wages earned is the sum of $27,552.86, less the $21,305.50 previously paid, or $6,247.36.

Defendant, Ram, argues that the trial court should not have awarded plaintiff $750.00 per day ($75.00 an hour for ten hours a day) from June 7 to June 10, 1988, pointing out that the first contract (P-1) compensated plaintiff $480.00 per day for this period. We find, as did the trial court, that plaintiff was entitled to this $750.00 per day because of the wording of the June 7, 1988 supplement (P-3), which states,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Burch v. Madcon Corporation
E.D. Louisiana, 2021
Smith v. Coffman
87 So. 3d 137 (Louisiana Court of Appeal, 2012)
Stockmon v. Van Alstyne
976 So. 2d 336 (Louisiana Court of Appeal, 2008)
Smith v. Superior Court
137 P.3d 218 (California Supreme Court, 2006)
Smith v. Dishman & Bennett Speciality Co., Inc.
805 So. 2d 1220 (Louisiana Court of Appeal, 2002)
Chautin v. St. Landry Parish School Board
649 So. 2d 734 (Louisiana Court of Appeal, 1994)
Blanton v. Malkem International Corp.
628 So. 2d 178 (Louisiana Court of Appeal, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
576 So. 2d 546, 1991 WL 25799, Counsel Stack Legal Research, https://law.counselstack.com/opinion/franklin-v-ram-incof-arkansas-lactapp-1991.