Frank Martz Coach Company v. WCAB (Avila)

CourtCommonwealth Court of Pennsylvania
DecidedApril 13, 2017
DocketFrank Martz Coach Company v. WCAB (Avila) - 1555 C.D. 2015
StatusUnpublished

This text of Frank Martz Coach Company v. WCAB (Avila) (Frank Martz Coach Company v. WCAB (Avila)) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Frank Martz Coach Company v. WCAB (Avila), (Pa. Ct. App. 2017).

Opinion

IN THE COMMONWEALTH COURT OF PENNSYLVANIA

Frank Martz Coach Company, : Petitioner : : v. : No. 1555 C.D. 2015 : Submitted: March 24, 2016 Workers’ Compensation Appeal : Board (Avila), : Respondent :

BEFORE: HONORABLE MARY HANNAH LEAVITT, President Judge HONORABLE ANNE E. COVEY, Judge HONORABLE DAN PELLEGRINI, Senior Judge

OPINION NOT REPORTED

MEMORANDUM OPINION BY PRESIDENT JUDGE LEAVITT FILED: April 13, 2017

Frank Martz Coach Company (Employer) petitions for review of an adjudication of the Workers’ Compensation Appeal Board (Board) that granted penalties to Julio Avila (Claimant). In doing so, the Board affirmed the decision of the Workers’ Compensation Judge (WCJ) that a Supplemental Agreement by which Employer agreed to pay Claimant total disability benefits, unless or until modified by order of a WCJ, precluded Employer from thereafter issuing a Notice of Compensation Denial. Holding that Employer’s unilateral termination of compensation benefits violated the Workers’ Compensation Act, 1 the Board affirmed the WCJ’s decision to award penalties. Concluding that the record is inadequate to conduct appellate review, we vacate and remand. On January 19, 2013, Claimant sustained a work injury. On February 5, 2013, Employer issued a Notice of Temporary Compensation Payable (NTCP)

1 Act of June 2, 1915, P.L. 736, as amended, 77 P.S. §§1-1041.4, 2501-2708. that described Claimant’s work injury of January 19, 2013, as a lumbar strain that occurred when “[Claimant] went to pull the latch for the engine compartment panel and strained his lower back.” Reproduced Record at 3a (R.R. __).2 Employer began paying Claimant compensation benefits at the rate of $824.84 per week. Employer’s NTCP stated that the 90-day temporary compensation period began on January 24, 2013, and would end on April 23, 2013. On March 12, 2013, Claimant and Employer entered into a “Supplemental Agreement for Compensation for Disability as Permanent Injury,” which contained several terms relevant to this appeal. R.R. 5a-6a. First, Claimant agreed to a reduction of disability benefits from February 11, 2013, through February 25, 2013, during which period he worked in a light duty position. Second, Employer agreed to resume the payment of total disability on February 28, 2013, when his work injury recurred. Finally, Employer agreed to pay total disability benefits into the future for an “uncertain” number of weeks. R.R. 6a. On April 22, 2013, Employer issued a Notice Stopping Temporary Compensation (NSTC) and a Notice of Compensation Denial (NCD). Employer did so for the stated reason that the medical information provided by Claimant was inadequate to establish a work injury. In response, on April 26, 2013, Claimant filed a penalty petition, contending that Employer violated the Act by unilaterally terminating his disability compensation. The penalty petition asserted that the 90- day-period of temporary compensation expired on April 19, 2013, because Claimant was injured on January 19, 2013. Thus, Employer’s NTCP converted

2 Because this case turned entirely on the legal significance of Employer’s agreement to pay Claimant disability compensation in a Supplemental Agreement, there is no evidentiary record on Claimant’s job title, or when the injury was reported.

2 automatically to an NCP on April 19, 2013, making Employer’s NCD of April 22, 2013, untimely. Claimant sought an immediate reinstatement of disability compensation and an award of penalties. The WCJ convened a hearing on May 28, 2013. The WCJ began the hearing by marking as exhibits filings that had been made with the Bureau of Workers’ Compensation (Bureau). Exhibit No. 2 was the Supplemental Agreement, signed by Claimant and Employer’s claims representative.3 R.R. 5a- 6a. Both Claimant’s counsel and Employer’s counsel stated they did not know about the Supplemental Agreement. Claimant then amended his penalty petition to add the contention that the Supplemental Agreement precluded Employer from unilaterally terminating compensation. Employer’s counsel responded with two points. First, Employer argued that although Claimant was injured on January 19, 2013, he continued to work. On January 24, 2013, Claimant took a vacation day.4 Employer argued that the 90-day duration of the NTCP did not begin until January 24, 2013. Second, Employer stated that because it had just learned of the Supplemental Agreement, its significance was unclear. Employer asked for time to research the issue. The WCJ gave the parties two weeks to brief the significance of the Supplemental Agreement. The WCJ stated that should the Supplemental Agreement be found to be controlling, then he would grant the penalty petition. If

3 Other exhibits included the NTCP, Bureau Exhibit No. 1; the NSTC, Bureau Exhibit No. 3; and the NCD, Bureau Exhibit No. 4. 4 These recitals cannot be confirmed or refuted because there is no evidentiary record. This is true for both Employer and Claimant.

3 not, he would schedule a hearing to take evidence on the question of when the 90- day period of temporary compensation began. On June 17, 2013, the WCJ issued a decision granting Claimant’s penalty petition; striking Employer’s NSTC and the NCD; and reinstating total disability compensation to Claimant. The WCJ acknowledged that Employer’s NTCP accepted liability for Claimant’s back injury only on a temporary basis. However, by executing the Supplemental Agreement, Employer fully accepted liability as of March 12, 2013. At that point, Claimant’s benefits could not be terminated unilaterally by Employer but only by agreement of the parties or order of a WCJ. Accordingly, the WCJ awarded a penalty equal to 30% percent of the outstanding compensation benefits as of the date of the order. Employer appealed to the Board. It argued that the Supplemental Agreement was not controlling, as held by the WCJ. In support, Employer offered a notice from the Bureau stating that the Supplemental Agreement was an “Improperly Filed Form.” R.R. 7a. The notice stated as follows:

Claim is in a temporary status. A Supplemental Agreement (LIBC-337) cannot be used to correct/amend a Notice of Temporary Compensation Payable (LIBC-501). A corrected/amended LIBC-501 must be submitted.

Id. The Board refused to consider the Bureau’s notice for the stated reason that it had not been presented to the WCJ and, thus, was not part of the certified record.5 In any case, the Board found the notice irrelevant. The Board

5 The dissent argues that in “fairness,” the Board should have considered the Bureau’s notice. However, Employer did not appeal this ruling of the Board to this Court.

4 held that Employer could not disavow the terms of the Supplemental Agreement simply because it filed the “wrong form.” The Board held that the Supplemental Agreement was binding unless and until it was modified by agreement of the parties or by an order of the WCJ. Because the Supplemental Agreement provided compensation “for uncertain weeks” into the future, Employer had admitted ongoing liability for Claimant’s back injury. The Board noted that the Supplemental Agreement should have been captioned as an Agreement for Compensation, but this had no bearing on the meaning and enforceability of the parties’ agreement.6 Employer petitioned for this Court’s review. On appeal,7 it raises one issue. It contends the Board erred as a matter of law in concluding that the Supplemental Agreement altered the provisional nature of Employer’s acceptance of liability for Claimant’s injury. Employer argues that the Supplemental Agreement did not have the legal effect of an Agreement for Compensation. Under Section 406.1(d) of the Act,8 77 P.S. §717.1(d), an employer may pay compensation payments for 90 days

6 Notably, the form for a “Supplemental Agreement” is identical to that for an “Agreement for Compensation,” except for the caption.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McClellan v. Health Maintenace Organization
686 A.2d 801 (Supreme Court of Pennsylvania, 1996)
Gereyes v. Workers' Compensation Appeal Board
793 A.2d 1017 (Commonwealth Court of Pennsylvania, 2002)
Beissel v. Workmen's Compensation Appeal Board
465 A.2d 969 (Supreme Court of Pennsylvania, 1983)
City of Philadelphia v. Workers' Compensation Appeal Board
830 A.2d 649 (Commonwealth Court of Pennsylvania, 2003)
Velocity Express v. Pennsylvania Human Relations Commission
853 A.2d 1182 (Commonwealth Court of Pennsylvania, 2004)
Rosen v. Bureau of Professional and Occupational Affairs
763 A.2d 962 (Commonwealth Court of Pennsylvania, 2000)
Shuster v. Workers' Compensation Appeal Board
745 A.2d 1282 (Commonwealth Court of Pennsylvania, 2000)
Eastwood Nursing & Rehabilitation Center v. Department of Public Welfare
910 A.2d 134 (Commonwealth Court of Pennsylvania, 2006)
Dixon v. Workers' Compensation Appeal Board
134 A.3d 518 (Commonwealth Court of Pennsylvania, 2016)
Sharon Tube Co. v. Workers' Compensation Appeal Board
908 A.2d 929 (Commonwealth Court of Pennsylvania, 2006)
Commonwealth, Department of Transportation v. Workers' Compensation Appeal Board
38 A.3d 1037 (Commonwealth Court of Pennsylvania, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Frank Martz Coach Company v. WCAB (Avila), Counsel Stack Legal Research, https://law.counselstack.com/opinion/frank-martz-coach-company-v-wcab-avila-pacommwct-2017.