Francisco & Ellington, Inc. v. Pasadena Tournament of Roses Ass'n

252 P. 652, 80 Cal. App. 450, 1926 Cal. App. LEXIS 40
CourtCalifornia Court of Appeal
DecidedDecember 27, 1926
DocketDocket No. 3146.
StatusPublished

This text of 252 P. 652 (Francisco & Ellington, Inc. v. Pasadena Tournament of Roses Ass'n) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Francisco & Ellington, Inc. v. Pasadena Tournament of Roses Ass'n, 252 P. 652, 80 Cal. App. 450, 1926 Cal. App. LEXIS 40 (Cal. Ct. App. 1926).

Opinion

FINCH, P. J.

Plaintiff was given judgment for the sum of $834.90 as the balance due upon a contract for making certain excavations in the construction of a stadium for defendant and has appealed therefrom, contending that a much larger balance is due. Appellant’s principal contention is that the findings are not supported by the evidence in that no “binding contract between the parties” was proved and that, even assuming that there was a binding contract, “yet the plans of construction were so materially deviated from ... on matters not contemplated within the terms of the contract that appellant is entitled to recover upon a quantum meruit.” It is conceded that the judgment is for the correct amount if the contract which the defendant attempted to prove is the measure of plaintiff’s right of recovery. Since the findings of the trial court from *452 conflicting evidence are conclusive on appeal, the evidence will be stated in the light most favorable to the support of the judgment, omitting contradictory evidence. Plaintiff was paid for certain extra work which was not within the terms of the agreement upon which the defendant relies. Compensation for such extra work is not involved in this action.

About February 15, 1922, the defendant undertook the construction of a stadium in the shape of a horseshoe with the open end to the south, the surrounding embankment to be raised approximately 50 feet above the finished floor level with earth taken from within the inner line of the embankment, the floor to be about 250 feet wide by 850 feet long. W. A. Taylor was the authorized representative of the defendant and Myron Hunt was the architect of the structure. W. T. Ellington represented the plaintiff in most of the transactions between the parties, he and Herbert Francisco then being copartners, but subsequently forming the plaintiff corporation. He offered, in behalf of the copartnership, to do the contemplated excavating at 30 cents a cubic yard and Taylor agreed to that price, but stated that he “wanted him (Ellington) to make an accurate figure and submit a lump sum bid.” Ellington “said he had not figured it accurately enough,” that “it would require somewhere from two to three weeks for him to do it, and he didn’t have time to do it right then.” No “lump sum bid” was ever submitted, but it was agreed that plaintiff would “move on the job and go to it,” and work was commenced about February 20th with a small force. Plaintiff had a large force at work by March 20th and continuously thereafter until the excavations were completed. After the work was commenced Taylor received such instructions from defendant as to prevent the execution of a “lump sum” contract with plaintiff. It does not appear that either party thereafter expressed a desire to enter into such a contract, and it is a fair inference that the original understanding in that respect was abandoned by mutual consent. April 3, 1922, Taylor presented to Ellington for signature a proposed written contract, binding the plaintiff to “do all the excavation necessary in the construction of said stadium” for 30 cents per cubic yard, the yardage to be computed from the map of the premises provided by the architect “and the *453 finished grades as shown in the plans furnished by the architect.” The last clause of the proposed contract was as follows: “It is further agreed that first parties may terminate this agreement upon three days notice to second parties by paying to them all money owed them to date, and in addition thereto the actual cost of removing their equipment from the premises. ’ ’ Ellington refused to sign the contract, objecting particularly to the clause providing for its termination. “It was agreed by both parties that . . . the rest of the document was substantially all right.” Both parties then agreed that in the event of a termination of the contract, the amount to be paid to plaintiff would be left to the decision of Hunt. Hunt delivered to each party a letter accepting the proposal that he act as arbitrator between them, attaching thereto a copy of the proposed contract. The parties, however, never signed the contract, but the plaintiff continued the work. The plans were changed in certain particulars after plaintiff had first offered to do the excavating at 30 cents a yard. Among other changes, the tunnels were lengthened and the floor level was lowered two feet. The plaintiff made claim for extra compensation on account of the changes in the plans and on the 5th of July the parties met together in an effort to agree upon the amount of such extra compensation to which plaintiff was entitled. The conference resulted in the execution of the following document by the parties whose signatures are attached thereto:

“To W. A. Taylor and Rea P. Taylor: Copy to—M. J. J.
Mitchell, President Tournament of Roses Assn.
“Mr. W. F. Creller, Chairman Building Committee.
“Francisco and Ellington, Architects’ Superintendent.
“Referring to our memorandum A. 4216, Contract B. 3801, dated June 26th, 1922, regarding your settlement of extra items under your contract with Francisco and Ellington.
“After consultations with the Building Committee by both yourself and this office, we, in that memorandum, approved your allowing Francisco and Ellington a total added charge for various items as therein set forth, amounting to $9,000.00.
“The bill which they put in totaled something over $14,000.00. Other items in the bill were not allowed. After a further consultation today they convinced you and con *454 vinced me that there was a proper charge coming from them as the result of the change back to the original level of the bottom of the Bowl, from a level 2' higher, which latter level was contemplated at the time you made your agreement with them.
“You are authorized to make a settlement with them in full for all items not covered by the flat agreement to move dirt at 30/ per yard, providing they will accept, as they have agreed to accept, an additional $3,000.00, bringing their total bill exclusive of the 30/ figuring, up to $12,000.00.
“Our contract A 4210, dated June 22, 1922, authorized you to pay Francisco and Ellington the sum of $6,000.00 on account of extra charges as definitely set forth in this memorandum. You are hereby authorized to pay Francisco and Ellington the further sum of . . . $8,000.00 which, together with the $8,000.00 payment referred to above, brings the total payments on account of extra charges to $12,000.00 as set forth above.
“As stated to you in our Order of July 6th, being Memorandum A 4233, Contract B 3801, it is left to you to determine the rapidity with which you can afford to pay out these moneys and still protect yourself in the matter of the cash bond which you have put up with the Owner.
“It should be definitely understood and agreed between you and Francisco and Ellington, that the acceptance of this additional $12,000.00 binds Francisco and Ellington to the completion of all excavating as required or directed in connection with the Stadium, under their unit price of 30/ per cubic yard, plus only the additional, $12,000.00 authorized by this memorandum.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

North Confidence Mining & Development Co. v. Morrice
204 P. 851 (California Court of Appeal, 1922)
Marin Water & Power Co. v. Town of Sausalito
143 P. 767 (California Supreme Court, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
252 P. 652, 80 Cal. App. 450, 1926 Cal. App. LEXIS 40, Counsel Stack Legal Research, https://law.counselstack.com/opinion/francisco-ellington-inc-v-pasadena-tournament-of-roses-assn-calctapp-1926.