Francis v. Pennpower, Inc.

52 F. App'x 595
CourtCourt of Appeals for the Fourth Circuit
DecidedDecember 10, 2002
Docket02-1138
StatusUnpublished
Cited by1 cases

This text of 52 F. App'x 595 (Francis v. Pennpower, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Francis v. Pennpower, Inc., 52 F. App'x 595 (4th Cir. 2002).

Opinion

OPINION

PER CURIAM.

The plaintiffs brought this breach-of-contract action in state court, alleging that the defendants, PennPower, Inc. (formerly known as Sawco) and Tamrock Corporation (formerly known as Tampella Corporation), owed them $250,000 under the terms of a stock option agreement. The action was removed to federal court on the basis of diversity of citizenship. See 28 U.S.C.A. § 1332(a) (West 1993 & Supp. 2002). After a bench trial, the district court ruled in favor of the plaintiffs and awarded them $250,000, plus interest. The defendants appeal. We vacate the order of the district court and remand with instructions to enter judgment in favor of the defendants. 1

I.

In 1990, Piney Creek Limited Partnership (“Piney Creek”) was formed for the development, construction, and operation of a power plant in Pennsylvania. Piney Creek’s general partner was MidAtlantic Energy of Pennsylvania, Inc. (“MAE”); the plaintiffs were MAE’s sole shareholders at that time. Piney Creek’s limited partner was Tampella Power Corporation *597 (“TPC”), a subsidiary of Tampella Corporation. TPC was in the business of manufacturing industrial boilers, and its initial involvement in the Piney Creek project was to assist MAE with development costs and to provide MAE with standby credit in exchange for the exclusive right to supply the boiler for the project. After an equity infusion in May 1993, Sawco (now known as PennPower, Inc.), another subsidiary of Tampella Corporation, became the limited partner. MAE remained the general partner, but had only a 1% ownership interest in Piney Creek after the equity infusion. Sawco owned the remaining 99%, but, as a limited partner, had no say in the management of the partnership.

Construction of the plant began falling behind schedule, and MAE was unable to find an operations and maintenance contractor for the project. To protect the equity it had already invested in the project through Sawco, Tampella Corporation created Tampella Services, another subsidiary, to serve as the operations and maintenance (“0 & M”) contractor. Swiss Bank Corporation, the project’s primary lender, conditioned its approval of Tampella Services as the 0 & M contractor upon Tampella Corporation posting a letter of credit to support Tampella Corporation’s $2 million cost overrun guaranty. By its terms, the letter of credit was to expire on December 1,1994.

Meanwhile, Sawco and MAE had begun discussing the possibility of a realignment of their interests in Piney Creek, and they ultimately agreed to a sale of all MAE stock to Sawco. The terms of this agreement were set forth in a stock option agreement (the “Agreement”) executed on November 15, 1993. Under the terms of the Agreement, Sawco could initiate the transfer by “calling” MAE’s shares, or MAE could initiate the transfer by “putting” the shares. If Sawco called the shares, the purchase price was $1,355,000. If MAE opted to put the shares, it could require Sawco to purchase its shares for the same price, provided that three specified conditions were met at the time of the exercise of the put; if the conditions were not met when the put was exercised, the Agreement called for a total purchase price of $1,105,000. The Agreement, however, provided that, after the exercise of the put, “[a]n additional $250,000.00 shall be payable ... if and when all of the Conditions have thereafter been satisfied.” J.A. 345-46. The Agreement also included the following termination clause:

Except with respect to the representations and warranties set forth in Paragraphs 11 and 12 hereof and to covenants set forth in Paragraphs 6 and 7 hereof, all of which shall be without limitation, this Option Agreement, and the obligations of Sellers, Tampella and Sawco hereunder, shall automatically terminate upon June 30, 1994, at 5:00 p.m., EDT, unless such termination shall be sooner accomplished by closing on the Put or Call hereunder.

J.A. 360.

While the plant construction was falling behind schedule, problems were also developing with the general contractor, who eventually left the project. Tampella Services entered into a “remediation” agreement with the Piney Creek partnership through which Tampella Services agreed to complete the project. Swiss Bank made $1 million available for the remediation, but required that the letter of credit securing the cost overrun guarantee remain in place until the remediation was completed. The remediation, which for a time was projected to be completed by June 30, 1994, was not completed until December of that year. Although Swiss Bank initially sought an extension of the letter of credit, the bank allowed the letter of credit to *598 expire on December 1, 1994, with no draw having ever been made against it.

The power plant became operational and began earning revenues even before all construction was completed. Until construction was completed, however, Swiss Bank controlled the release of construction funds and the revenue earned through the operation of the plant. Swiss Bank authorized the use of the plant’s revenues to pay operating expenses beginning on January 1, 1994. However, because of a problem with the project’s 1993 budget, Swiss Bank refused to release funds to pay Tampella Services for 0 & M charges incurred from March 1993 through December 1993. By the end of 1993, the unpaid 0 & M charges amounted to approximately $1.5 million.

In 1994, Swiss Bank released approximately half of the unpaid 0 & M charges, but it refused to release the balance of the funds unless Sawco paid a fee of $450,000 to compensate Swiss Bank for what the bank perceived to be below market fees that it had earned for financing the project. Sawco refused to pay the fee, believing it unreasonable to pay $450,000 to receive $750,000 that it was entitled to receive and expected that it would receive. Swiss Bank never released the funds for the remaining O & M charges, and the receivable was “written off’ in late 1994 or early 1995.

On January 5, 1994, the plaintiffs exercised their right to put the shares of MAE. At the time of the exercise, two of the conditions upon which the payment of the additional $250,000 was dependent were not satisfied. Near the end of 1994, the plaintiffs became aware that Sawco was negotiating with a third party for the sale of Sawco’s interests in the power plant. Counsel for the plaintiffs then began asking Sawco whether the conditions set forth in the Agreement had yet been satisfied, to which Sawco responded in the negative. Sawco did not sell its interests in the Piney Creek project until 1997. Convinced that the conditions must have been satisfied by the time of the sale, the plaintiffs sought payment of the additional $250,000. The defendants refused, contending that under the Agreement, its obligation to make the $250,000 payment terminated on June 30, 1994, in accordance with the termination clause. The defendants also contended that even if the termination clause did not apply to the obligation to pay the $250,000, no payment was required because the conditions had never been satisfied. This action followed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

J.P. Morgan Trust Co. v. U.S. Bank, N.A.
446 F. Supp. 2d 956 (E.D. Wisconsin, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
52 F. App'x 595, Counsel Stack Legal Research, https://law.counselstack.com/opinion/francis-v-pennpower-inc-ca4-2002.