Francis v. Domino

64 S.W.2d 571, 251 Ky. 255, 1933 Ky. LEXIS 835
CourtCourt of Appeals of Kentucky (pre-1976)
DecidedOctober 6, 1933
StatusPublished
Cited by5 cases

This text of 64 S.W.2d 571 (Francis v. Domino) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky (pre-1976) primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Francis v. Domino, 64 S.W.2d 571, 251 Ky. 255, 1933 Ky. LEXIS 835 (Ky. 1933).

Opinion

Opinion of the Court by

Judge Dietzman

Reversing.

In the spring of 1928, the appellant, Carr Creek Community Center, a private corporation engaged in educational work in Eastern Kentucky, and hereinafter called the Community Center, decided to build a schoolhouse and a teachers’ cottage on the Flax Patch Branch in Knott county. It entered into a contract with Marion Francis, one of its directors and its coappellant herein, to construct these buildings for the contract price of $7,500. The buildings were to be constructed in the main with stone quarried from a nearby quarry. Francis later entered into a subcontract with the appellee, Joe Domino, to do the stone work, the exact extent of which being in dispute in this case. This subcontract *256 provided that Domino was to prepare the stone at the quarry, transport it to the site of the buildings, and there set it. However, it developed that Francis could transport the stone and furnish the cement and sand necessary to set it cheaper than Domino could, so this subcontract was abandoned and a new subcontract was entered into. Domino had started his work before this last subcontract was reduced to writing. It was prepared by Will Francis, a brother of Marion Francis, and also a director of the Community Center. After it had been prepared, Marion Francis left it with Domino to look over, as the latter admits. Domino did read it over, although, as he says, hurriedly. After Domino had had the contract for some time, Marion Francis came one day to the place where Domino was working and had Domino sign the contract. The portions of this contract material to this controversy are articles 1, 4, and part of article 6. They read:

Article 1. “The contractor (Domino) agrees to build the main walls and the basement walls of a school house and cottage on the Flax Patch Branch of split stone according to the plans and specifications hereto attached. Pie further agrees to imbed in the top layer of stone and cement on top of the walls a sufficient number of bolts to bolt the foundations of the roofs down good and to level and smooth the top of the walls with cement and to leave the walls ready for the woodwork in first class workmanlike order.”
' Article 4. “Both parties agree that the plans and specifications furnished by the Carr Creek Community Center and its executives shall be and are a part of this contract as if they were herein specified. ’ ’
Article 6. “The owner agrees to pay the contractor Ten Dollars ($10.00) for each net cubic yard of stone laid in the walls of the said two buildings . ” (Italics ours.)'

Domino not only built the main walls and basement walls of the schoolhouse and cottage, but he also did a lot of other work on these buildings with the full knowledge, consent, acquiescence, and indeed the insistence of the appellant Francis and the executive officers of the Community Centeh who were to a large degree *257 supervising the job. On the schoolhonse he laid the stone window sills, bnilt a fine for the furnace, constructed a front porch, set the steel window frames, constructed 81 lineal feet of dressed stone steps, and set 8 19/29 cubic yards of stone masonry for those steps. On the teachers’ cottage, he built two fire places and chimneys, installed a flue ring, built some stone piers, installed four steel window frames, and prepared and laid 52 lineal feet of window sills. There is no substantial dispute in the record as to all of this ^vork, in addition to the main walls of the buildings and basements being done by Domino, and although there is. some intimation that the work was not done in a workmanlike manner, no insistence is put upon that in the' briefs on this appeal. Indeed, there scarcely could bo in view of the evidence as to the excellent character and. quality of the work which Domino did. After Domino’s, work was completed, the dispute which is the cause of the present litigation arose. It is the method by which. Domino’s compensation under the contract is to be computed and whether all the work Domino did was covered by the contract or just the main and basement; walls of the buildings, the rest being extra work. Domino first claimed that the contract itself provides that in accordance with the usual and general custom in the. stone trade prevailing in this locality, he is to be paid), for the stone work done by him in the main walls and basements of these buildings on gross measurements,, that is to say, there are to be no deductions from the measurements of these walls for openings in them caused by doors, windows or otherwise less than 6 foot, square and all corners of the buildings are to be measured double. Francis, and later the Community Center, contended that the contract specifically provides that Domino is to be paid for the net cubic yards of stone laid; that whatever may be the custom in the trade as to compensation being grounded on gross measurements, such custom, if any, must yield to the express terms of the contract, and that the term “net” in article 6 clearly means that the openings in walls are to be deducted and corners are to be measured but once. Indeed, the appellants at first insisted that even the mortar between the stone should be deducted.

As to the work done in addition to the erection of the main and basement walls in these buildings, Domino *258 contended that his contract does not call for snch work, and that he is entitled to be paid for it on a quantum meruit basis. The appellants insisted that all this work is covered by the contract and should be paid for at the contract rate of $10 per net cubic yard of stone laid, but that if in error as to the work being included in the contract, still it should be paid for at the same unit price as the contract provides for the regular work. The parties not being able to agree, Domino brought the instant suit to recover from the appellants for the work he had done in accordance with his theory of the way the dispute should be decided, asking further that a mechanic’s lien he had filed against the property on which these buildings had been erected should be enforced. The appellants defended according to their theory of the way the dispute should be resolved. After the parties had taken proof in support of their respective contentions, Domino filed an amended petition in which he alleged that if his interpretation of the contract as to how the measurements were to be made, gross or net, be wrong, then the contract did not express the true agreement of,the parties -and should be reformed on the ground of mutual mistake or mistake on his part and fraud on that of Marion Francis in the drafting.. The allegations of the amended petition being put in issue by the appellants, the parties then took proof on the issues raised by it. The case was then submitted for judgment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Untitled Case
E.D. Kentucky, 2026
Carr Creek Community Center, Inc. v. Home Lumber Co.
125 S.W.2d 777 (Court of Appeals of Kentucky (pre-1976), 1939)
Bennett v. Madison Sales Co.
95 S.W.2d 604 (Court of Appeals of Kentucky (pre-1976), 1936)
Redford v. Thompson's Administrator
82 S.W.2d 796 (Court of Appeals of Kentucky (pre-1976), 1935)

Cite This Page — Counsel Stack

Bluebook (online)
64 S.W.2d 571, 251 Ky. 255, 1933 Ky. LEXIS 835, Counsel Stack Legal Research, https://law.counselstack.com/opinion/francis-v-domino-kyctapphigh-1933.