Francis M. Marley v. The United States

381 F.2d 738, 180 Ct. Cl. 898, 1967 U.S. Ct. Cl. LEXIS 102
CourtUnited States Court of Claims
DecidedJuly 20, 1967
Docket3-60
StatusPublished
Cited by17 cases

This text of 381 F.2d 738 (Francis M. Marley v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Francis M. Marley v. The United States, 381 F.2d 738, 180 Ct. Cl. 898, 1967 U.S. Ct. Cl. LEXIS 102 (cc 1967).

Opinion

COWEN, Chief Judge.

Plaintiff, Francis M. Marley, purchased the following at a bankruptcy sale authorized and approved by the United States District Court for the Northern District of Ohio:

Claim I — “Claim of bankrupt against the United States of America for *739 damages resulting from the termination of Department of Army Contract No. DA-36-038-507— ORD-1588, for which a claim in the sum of One Hundred Thousand Dollars ($100,000.00) has been filed;”
Claim, II — “Claim of bankrupt against the United States of America for money due the bankrupt in connection with the Department of Army Contract No. da-11-070ORD-8071, in the sum of Fifty-two Thousand and Fifty Dollars ($52,-050.00).”

Paralleling these claims are two of the causes of action contained in the petition before this court and the Government contract involved separately in each cause of action. Throughout this opinion, Claim I purchased by plaintiff Marley relates to Cause of Action I and the contract sued upon therein (which, for the sake of convenience, will be referred to as Contract I); likewise, Claim II purchased by plaintiff Marley relates to Cause of Action II and Contract II.

The Underlying Contracts

Contract I:

On April 6, 1956, Firth Machine & Tool, Inc. (the eventual bankrupt) entered into a contract with the Government for the manufacture of 17,874 initiators 1 at a unit price of $6.75. As a result of Firth’s alleged failure to meet a specified delivery schedule, the contracting officer issued a letter on February 18, 1957, terminating the contract for default. Firth was also notified that the initiators required to complete the contract would be procured on the open market and that Firth would be held liable for any excess costs incurred by the Government.

The Government thereafter awarded a contract for 17,007 initiators at a unit price of $16.71 to Federal Industries, Inc. Allowance having been made for a change in packaging requirements, a demand for excess reprocurement costs m the amount of $152,231.24 was made against Firth on July 30, 1957, and increased on November 29, 1957, to $159,-238.24.

Firth appealed to the Armed Services Board of Contract Appeals which, on July 30, 1959, upheld the termination for default but reversed the assessment of excess reprocurement costs, holding that the Government had failed to mitigate damages. Although the Board did not direct him to do so, the contracting officer thereafter reassessed damages in the amount of $93,029.76. By letter of January 29, 1960, demand was made for this amount.

Contract II:

On or about June 30, 1952, Firth was awarded Contract No. DA-11-070-ORD8071 by the Department of the Army. In September of 1957 and after complete performance of the contract, the parties agreed to an equitable adjustment, increasing the price payable to Firth by $59,500 (subject to certain offsets by the Government, leaving a net amount of $45,434.33).

The modification agreement giving rise to the equitable adjustment contained this paragraph:

The Government and the Contractor agree that the Government shall have a prior lien for the said sum of $59,-500.00 referred to above on account of a claim or claims by the Government against the Contractor on this or other contracts; and the Contractor waives any right of assignment hereof.

Firth’s Bankruptcy and the Commencement of Suit in the Court of Claims

On December 4, 1957, an involuntary petition in bankruptcy against Firth was filed in the United States District Court for the Northern District of Ohio. This occurred: (1) nearly 10 months after the contracting officer had terminated Contract I for default and shortly after the assessment of excess reprocurement *740 costs in the amount of $159,238.24; (2) while appeal proceedings relative to the contracting officer’s decision were pending before the Armed Services Board of Contract Appeals; and (3) approximately 3 months after the execution of the modification agreement fixing the equitable adjustment under Contract II.

On April 14, 1958, while the appeal before the Armed Services Board of Contract Appeals was still pending, the Government filed a priority proof of claim in the bankruptcy proceedings for the full amount of the excess reprocurement costs on Contract I.

Then, on July 30, 1959, the Armed Services Board of Contract Appeals rendered its decision affirming the termination for default of Contract I, but reversing the assessment of reprocurement costs as being excessive.

Approximately 6 months after this decision, Firth’s receiver (who was also appointed trustee in bankruptcy) filed a petition in this court, alleging, among other things:

Cause of Action I — That “the decision of the Board holding that the termination for default was proper was not supported by the evidence and was arbitrary, capricious and disregarded substantial evidence which established that Firth’s failure to meet its delivery schedule was due to factors beyond its control and without its fault or negligence * * *.”
That the termination “should have been considered to have been for the convenience of the defendant,” and that the receiver is entitled to relief of not more than $100,000, representing Firth’s costs in performing Contract I.
Cause of Action II — That, pursuant to the modification agreement of. September 9, 1957, the Government withheld the $45,434.33 owing Firth under Contract II as a setoff against the excessive reprocurement costs allegedly due under Contract I.
That Firth’s receiver should recover this money since the Government is not legally entitled to retain it.

In its answer' 2 "the' Government alleged that the termination of Firth’s contract for default in failing to meet the contract delivery schedules “was supported by substantial evidence and was in no way arbitrary or capricious and that Firth’s failure to meet the mandatory delivery schedules was not due to factors beyond its control or without its fault or negligence.” Relative to Cause of Action II, the Government alleged that “it was legally and equitably justified in setting off the sum of $45,434.33 due under [Contract II] against the claim which the Government had for excess costs of re-procurement resulting from Firth’s default of [Contract I].”

The Government also interposed a counterclaim against the receiver, claiming excess reprocurement costs of $93,-029.06 and alleging that the withholding of $45,434.33 due Firth under Contract II was proper. 3

Plaintiff Marley’s Purchase of Firth’s Claims

On June 16, 1964, Firth’s trustee filed an application to the district court for the marshaling of liens and sale of the bankrupt’s claims against the United States.

*741

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lennar Multifamily Builders, Llc, V. Saxum Stone, Llc
492 P.3d 175 (Court of Appeals of Washington, 2021)
Schneider National, Inc. v. Bridgestone/Firestone, Inc.
200 F. Supp. 2d 1006 (E.D. Wisconsin, 2001)
In Re Holder
182 B.R. 770 (M.D. Tennessee, 1995)
Americold Corp. v. United States
28 Fed. Cl. 747 (Federal Claims, 1993)
Feldman v. Philadelphia National Bank
408 F. Supp. 24 (E.D. Pennsylvania, 1976)
Mater v. Boese
518 P.2d 482 (Supreme Court of Kansas, 1974)
Marley v. United States
423 F.2d 324 (First Circuit, 1970)
Marley v. United States
423 F.2d 324 (Court of Claims, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
381 F.2d 738, 180 Ct. Cl. 898, 1967 U.S. Ct. Cl. LEXIS 102, Counsel Stack Legal Research, https://law.counselstack.com/opinion/francis-m-marley-v-the-united-states-cc-1967.