Francis Bros. & Jellett v. Heine Safety-Boiler Co.

109 F. 838, 48 C.C.A. 687, 1901 U.S. App. LEXIS 4252
CourtCourt of Appeals for the Third Circuit
DecidedJune 10, 1901
DocketNo. 29
StatusPublished
Cited by1 cases

This text of 109 F. 838 (Francis Bros. & Jellett v. Heine Safety-Boiler Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Francis Bros. & Jellett v. Heine Safety-Boiler Co., 109 F. 838, 48 C.C.A. 687, 1901 U.S. App. LEXIS 4252 (3d Cir. 1901).

Opinion

ACHESON, Circuit Judge.

Francis Bros. & Jellett, Incorporated (here the plaintiff in error), had entered into a contract with Henry C. Lea, the owner of the Bittenhouse Building, on Arch street, Philadelphia, to .do certain work required in the reconstruction of that building; the same to be done in accordance with plans and specifications which had been prepared by Francis Bros. & Jellett, and [839]*839adopted by the owner of the building. That contract Included tlie furnishing and setting up of two water-tube boilers in conformity with the above-mentioned specifications. These specifications contained, among other things, the following provisions under the heading “Boilers”:

“There will be two (2) new boilers erected in boiler room of new building, set singly as shown; each boiler having a capacity of one hundred and forty (140) nominal horse power, and must be capable of evaporating forty-two hundred (4.200) pounds of water from and at 212“ Fahrenheit, per hour, with ordinary firing.
“Proposals for water-tube boilers of the makes named only will be considered. Bidders are to furnish with their proposal detailed figures, plans for the boilers and setting and flue connections, including working drawings of the boilers, setting, and foundations, together with detailed specifications describing- the particular boiler they propose to furnish, '.the general description of the boilers and their accompaniments must include the kind and quality of material to be used in the various .parts of the boilers and their setting. They must also guaranty the number of pounds of water the boilers will evaporate per hour per pound of dry red ash anthracite pea coal, containing- not over sixteen per cent. (16%) refuse, and when developing their normal horse power.”

These specifications also contained the following provision under the beading “Tests”:

“The boilers, when completed and ready for use, must stand a steam pressure of at least 125 pounds per square inch, and all local rules and ordinances affecting construction conformed to, after which they shall be operated for ten (10) consecutive hours to determine their maximum capacity, under the direction of the contractor furnishing the boilers. During the ton hóurs’ test for maximum capacity, each boiler must show an equivalent evaporation of not less than 5,200 pounds of water per hour, from and at 212° Fahrenheit, with not to exceed 1%% of moisture in the steam.
“The test of the boilers to determine their economy shall be made during a second run of ten (10) consecutive hours. The test for economy must show an equivalent evaporation of not less than 10% pounds of water per pound of combustible from and at 212“ Fahrenheit; the boilers evaporating not less than 4,200 pounds of water per hour from and at 2.12° Fahrenheit.
“The tests for both economy and capacity will be made by the engineers, and their fees for making the test will be paid by the owner. Contractor for furnishing- boilers must bear all other expenses, including coal, hauling of ashes, etc., for testing the boilers, both for maximum capacity and economy.
“Contractor must also guaranty to keep the boilers in repair, at his own expense, for a period of one (1) year from date of acceptance, when the necessity of such repairs is directly duo to imperfect material or poor workmanship put upon said boilers, and must give bond, with approved corporate security, for the faithful performance of his contract and guaranty.”

Francis Bros. & Jellett invited bids for these boilers from several boiler makers, including the Heine Safety-Boiler Company (here the defendant in error), referring the company to- the plans and specifications above mentioned, and stating- where they could be seen. The Heine Safety-Boiler Company, having first examined these plans and specifications, submitted a proposal with detailed specifications of the boilers they proposed to furnish inclosed in a letter dated April 10, 1899. Afterwards Francis Bros. & Jellett, Incorporated, signed a formal contract, and forwarded it to the Heine Safety-Boiler Company, to be executed by that company. To this contract were annexed the aforementioned specifications, upon which [840]*840the original contract between the owner of the building and Francis Bros. & Jellett, Incorporated, was based, parts of which specifications have been quoted above, and the first two paragraphs of the contract were as follows:

“This agreement entered into this first day of May, A. D. eighteen hundred and ninety-nine, by and between the Heine Boiler Company, of St. Louis, Missouri, party of the first part, and Francis Brothers & Jellett, Incorporated, a corporation of the state of Pennsylvania, party of the second part,
“Witnesseth, that for and in consideration of the payments and covenants herein mentioned, to be made and performed by the said party of the second part, the said party of the first part doth hereby agree and covenant to furnish all materials and apparatus for, and to build, construct, and finish complete, ready for use, two (2)., water-tube boilers, with their setting, damper regulator, etc., called for in specifications prepared by Francis Brothers & Jellett, Incorporated, consulting engineers, dated March 15th, 1899, to be erected in the Rittenhouse Building, 707 & 709 Arch St., Philadelphia. The whole of said work is to be erected, constructed, and finished in conformity with the plans and specifications above referred to; both plans and specifications above referred to being understood as forming part of this agreement. All work called for by these plans and specifications is to be erected under the direction and supervision of Mr. Oliver Earnshaw, engineer for Mr. Henry O. Lea, owner of the building.”

This contract was executed by the Heine Safety-Boiler Company, but in the paragraph just quoted an asterisk was placed at the word “agreement” where it last occurs, and another asterisk was put at the foot of the contract, where were added, just above the Heine Company’s signature, these words: “Except the changes in details of - construction covered by our proposition and specification dated 4/10/99 and attached hereto;” and the company attached to the contract and annexed specifications its proposal and specifications already referred to. Upon receipt of these papers, Francis Bros. & Jellett, Incorporated, under date of May 9, 1899, wrote to the Heine Safety-Boiler Company, requesting the -latter to “specify what these changes in details of construction' are,” and in reply the Heine Safety-Boiler Company wrote thus:

“Answering your, favor of the 9th, in which you ask what W'e mean by ‘except the ¿hanges in details of construction covered by our proposition and specifications dated 4/10/99 and attached hereto,’ would say that we refer simply to the minor details in which the construction of the Heine boiler differs from your general specifications, and these details are set forth in our specification sheet dated 4/10/99. -For instance, especially in regard to the testing and inspecting of the metal, the punching and reaming of the rivet and tube holes, and the calking of the seams; also the guaranties which we make, and the amount of work which we include in our bid.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Francis Bros. & Jellett v. Heine Safety-Boiler Co.
112 F. 899 (U.S. Circuit Court for the District of Eastern Pennsylvania, 1902)

Cite This Page — Counsel Stack

Bluebook (online)
109 F. 838, 48 C.C.A. 687, 1901 U.S. App. LEXIS 4252, Counsel Stack Legal Research, https://law.counselstack.com/opinion/francis-bros-jellett-v-heine-safety-boiler-co-ca3-1901.