France v. Woolston

9 Del. 557
Superior Court of Delaware·Decided July 5, 1873·Published·Cited by 1 cases

Opinion

The claim, of a contractor to do the work and furnish the materials in painting, glazing and varnishing a house, is within the purview of the mechanic lien law or statute. And when they are to be paid for in gross, no bill of particulars of the kind and the amount of the materials furnished is required, nor is it necessary to state when the furnishing of them was commenced and finished in such a case, if the dates of commencing and completing the contract are stated.

“Two two-story brick houses (with mansard roof) adjoining each other on a lot at the southeasterly intersection of Delaware Avenue and Rodney Street in the City of Wilmington, with the number of feet on each of them and on the other two lines of it stated,” is a sufficient description of the several pieces of ground on which the houses are respectively situated.

In filing the claim of a partial contractor to do the work on, and furnish the materials for, a specific part of the building, begun after the commencement of it, and finished before the erection and completion of the entire building, the time of the commencement and of the completion of it, need not be stated, but only the times when the work done and the materials furnished by him were begun and finished .under his contract.

If judgment be entered, in the absence of an affidavit of defence by the owner of the building, on a claim the contractor has erroneously filed within sixty days after the completion of his contract, it will not be set aside on the application of a purchaser of the premises at sheriff’s sale on a mortgage executed by the owner to another and recorded after he had commenced, but before he had completed his contract on the building.

In these cases which were heard together, Houston, J., delivered the opinion of the court.

These cases arise under the mechanic lien law or statute passed March 29, 1871, on rules granted to show cause wherefore the judgments hereafter mentioned in favor of James France and Henry Evans respectively against Abram Woolston obtained under it in this court, should not be disallowed and stricken from the record, and which having been heard at the last, were held under advisement until the present term of the Court. In the first case the statement of the claim and affidavit of France *558 was filed in the office of the Prothonotary on the 3d day of May 1871, stating in substance, First, that James France was the party claimant, and Abram R. "Woolston was the owner and contractor, and that the contract was made with Abram R. Woolston, the owner and contractor; Secondly, that the amount claimed to be due to the said claimant was $725,31 being a debt contracted for work and labor and materials furnished upon the buildings owned by the said Abram R. Woolston, and for which the said Abram R. Woolston was the contractor, as by the said claimant’s bill of particulars hereunto annexed more fully appears, and which was as follows :

To James France, Dr.

1871.

April 24. For work done at and on, and material furnished for two new Houses on the south east corner of Delaware Avenue ' and Rodney Street in Wilmington, Delaware. The work begun on the 4th day of October 1870, and finished this day, to wit, April 24, 1871.

Painting and glazing and furnishing material for both said Houses by estimate and agreement ......$535.00

Painting and paint on 18 window shutters in addition to agreement - ■ - - 27.00

Reglazing windows broken by plasterers - 19.31

Graining and varnishing doors and shutters inside ......120.00

Painting and glazing second story of each House Back Building. - 34.00

That the sum of $362.65-|- was due him for work and *559 labor and materials furnished for each of the adjoining houses at the south-easterly corner of Delaware Avenue and Bodney Street respectively; Thirdly,that the claimant began to work and labor and furnish materials on the 4th day of October 1870, and finished on the 21st day of April 1871; Fourthly, that the buildings upon which the said claimant furnished work and labor and materials, were located as follows, to wit; two two-story brick houses (with mansard roof) adjoining each other on a lot at the south-easterly intersection of Delaware Avenue and Bodney Street in the City of Wilmington, the said lot being about 109 feet on Delaware Avenue by 142 feet on Bodney Street, 109 feet on the south-easterly line, and 60-j- feet on its south-easterly boundary line; Fifthly, that the said work was performed, and the said materials were furnished by said claimant on the credit of the said two buildings, houses or structures above described; Sixthly, that the amount of said claim exceeded twenty-five dollars, and the same had not been paid, or secured to be paid to the claimant. And upon which a writ of scire facias was issued returnable at the May Term 1871, and on which the claimant recovered judgment for $725.31 and costs, at that term.

Free access — add to your briefcase to read the full text and ask questions with AI

France v. Woolston, 9 Del. 557 (Del. Ct. App. 1873).

9 Del. 557 (France v. Woolston) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Mayor & Council v. Recony Sales & Engineering Corp.
185 A.2d 68 (Supreme Court of Delaware, 1962)