Frame v. The Ella

48 F. 569, 5 Hughes 125, 1880 U.S. Dist. LEXIS 276
CourtDistrict Court, E.D. Virginia
DecidedMarch 29, 1880
StatusPublished
Cited by6 cases

This text of 48 F. 569 (Frame v. The Ella) is published on Counsel Stack Legal Research, covering District Court, E.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Frame v. The Ella, 48 F. 569, 5 Hughes 125, 1880 U.S. Dist. LEXIS 276 (E.D. Va. 1880).

Opinion

Hughes, J.

By the'extraordinary storm of August, 1879, theschooner Ella, of Newcastle, Me., was carried 1,200 to 1,300 feet beyond the ordinary water’s edge, and beached high and dry on the shore of the Elizabeth river, near Norfolk, far beyond the reach of the tides. The own•er’s agent rejected the offers of the Bakers, of this city, experienced wreckers, to launch the vessel for $1,200; and contracted at $1,000 with a landsman, John Frame, the libelant in this suit, who had had some experience in moving houses. There was a written contract, at the price named, dated on the 1st of September, 1879, in which the libelant stipulated to “launch the schooner,’’and “to furnish all material, labor, and implements necessary to launch” her, and that the work of “launching” should be commenced as soon as practicable, and without unnecessary delay. The agent contracted to pajr for this service $1,000 as soon as the vessel should be placed in deep water; and that he should not be liable to pay any portion of the sum until the schooner was placed in deep water. No time was agreed upon for executing the work; the libel-ant stating in evidence that he was unwilling to bind himself to any limited time. The work was promptly begun about the 3d September, and the vessel was moved in a few weeks about the distance of twice her own length; she being a schooner of 160 tons. Then the plan of moving her over the ground seems to have been abandoned. It was determined, instead, to .dredge a canal from the channel up to the place where the vessel then lay. For this' purpose the dredge of one H. E. Culpepper 'was engaged,, which went to work at $50 a day, and worked on at intervals until she had earned $351. A good deal of delay seems to have been caused by the necessity of waiting for this dredge. On the 5th of December the dredge was again hired; Frame and Condon, the master of the Ella, uniting with Culpepper in a written contract, by which they pledged the lien of the vessel for the $351 already earned, and for the wages to be earned. Under this arrangement the dredge again went to work, and by the 22d of December had run. the canal up to the stern of the schooner where she then lay, and then knocked off from work,'though it seems that a canal was dredged further on along one side of the schooner at some time or other. Attempts were made to slide the vessel sideways into this lateral canal, but they did not succeed. Then it ivas attempted to drag the vessel astern into the main canal, but the hawser used by Frame broke more or less often, and that [571]*571effort failed. Nothing seems lo have been dono by Frame after' the 22(1 of December up to the 4th of January, 1880, which was probably dufe' to the holidays. On the last-named date, Condon told Frame that, if he' did not complete his job in a week from that time, he would 'terminate the contract. 'On the lltli January Condon gave Frame a written notice that he had employed other persons to finish the work." Condon, with' Ills new employes, the Bakers, went to work; and by cutting a canal on the other side of the vessel from that on which Frame' had cut one, and by the use of chains and other appliances, succeeded in launching the vessel on the 9th of March; that is, after the lapse of about tied months from the time when (Jondou took the work out of Frame’s hands. ' .Coii-' don paid the Bakers for the work done by them $600. A libel ,wa:s filed by Culpepper against the schooner for the dredging done by his' dredge, in which he claimed $750, including the amount of $851 due for the first service, which has beei! named. This claim and cost of Suit was' settled out of court by Condon, and the libel dismissed; the court costs in which being about 850. Frame contends that $200 of this $750 was not justly due, and that Condon should not have allowed it. Frame' now brings this libel, vouching his contract of September 1st, and claiming the $1,000 named therein, or else such just compensation for his services as may of right be adjudged to him. A note has been filed by counsel for Condon since the argument at bar, contending that, as this is a claim for salvage, the libelant barred bis right to sue in rem by entering into a special express contract for services.

There is nothing in the point made by the master’s counsel. In some old eases it has been held that a special or express contract with the owners, fixing the compensation to be paid for salvage, was a bar to a libel in rem-. But they have been overruled by more modem casos; and, except as to contracts for fixed sums payable “at all events,” such, is no longer the law. The point was settled by the United States supreme court in the case of The Camanche, 8 Wall. 448, and the ruling there lias been followed by several eases in the United States courts. Desty’s Shipping and Admiralty is not, and does not profess to be, an authority itself; it is an index of all decisions in admiralty, some of which are authority, and others of which are overruled cases. The contract in the case before me, as I have said, was in terms a contract for launching. It was so in fact. The repairer of a ship still on the docks may libel her, either while there, or after she has been launched. Benedict says that towing or “otherwise moving” a vessel of commerce is a maritime contract, within the cognizance of admiralty. A leading case on this subject, and an early American case, is Read v. The Hull of a New Brig, 1 Story, 244. The present case is indisputably within the admiralty jurisdiction.

I come, therefore, to consider it on the merits. The claim is resisted by the master of the schooner, Condon, on two grounds: (1) On the ground that the contract was forfeited by Frame by his failure to perform the job in a .reasonable timo; and (2) on the ground that Frame was without skill in the business he undertook, and, furthermore, was [572]*572not provided with the materials and implements necessary to the exe^ cution of his contract to furnish them. Condon also insists that he los^ at the rate of $300 a month for all the unnecessary time that was speni by Frame about the work he undertook to do. As to this last objection’ no cross-libel has been filed setting up this claim. It is not a matter put in issue by the pleadings in the case, and I do not think this specific claim is properly before the court for adjudication. But, even if it were, it would depend entirely upon, the decision of the question of unreasonable delay, which I am to pass upon.

Keturning to the more regular grounds of defense made by Condon, and first to that of Frame’s alleged dilatoriness in completing his work: It cannot be denied that Frame was bound to perform it in a reasonable time. The fact that no time was stipulated for, in a contract concerning the launching of a vessel of commerce, into which time always enters as a most important element of consideration, seems to indicate that neither party deemed it practicable to fix a time, and that the period to be allow’ed was left open to the determination of circumstances. I should have been disposed, nevertheless, to think the delay of four months quite unreasonable and fatal, but for what occurred after Condon discharged Frame, and undertook the job himself. Frame had effected the removal of the schooner over the ground some two lengths, and therebj7 shortened the distance necessary to be dredged, so as to save, according to Capt. Baker’s testimony, six or seven da3rs’ work of the dredge. He had also dredged a canal from the water channel some thousand feet to the stem of the schooner, and extended it along one side of the schooner.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Frances L. Skinner
248 F. 818 (W.D. Washington, 1917)
The Gulfport
243 F. 676 (S.D. Alabama, 1917)
Sobrinos de Ezquiaga v. Steamship Rochelie
8 P.R. Fed. 97 (D. Puerto Rico, 1915)
Hagerman v. Cowles
94 P. 946 (New Mexico Supreme Court, 1908)
Dailey v. City of New York
128 F. 796 (S.D. New York, 1904)
The Arthur B.
1 Alaska 353 (D. Alaska, 1901)

Cite This Page — Counsel Stack

Bluebook (online)
48 F. 569, 5 Hughes 125, 1880 U.S. Dist. LEXIS 276, Counsel Stack Legal Research, https://law.counselstack.com/opinion/frame-v-the-ella-vaed-1880.