Foye v. Lilley Coal & Coke Co.

96 A. 987, 251 Pa. 409, 1916 Pa. LEXIS 479
CourtSupreme Court of Pennsylvania
DecidedJanuary 3, 1916
DocketAppeal, No. 75
StatusPublished
Cited by11 cases

This text of 96 A. 987 (Foye v. Lilley Coal & Coke Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Foye v. Lilley Coal & Coke Co., 96 A. 987, 251 Pa. 409, 1916 Pa. LEXIS 479 (Pa. 1916).

Opinion

Opinion by

Mr. Justice Stewart,

The Lilley Coal & Coke Company, appellant, with a view' to the development of its coal mines determined upon the construction of two slopes from the surface to the coal, and to this end caused plans and specifications to be made of the proposed work, and invited bids therefor. A copy of these plans and specifications was furnished to appellee, whose business was that of general [412]*412contractor. Basing his estimate on the plans furnished him, the appellee submitted a bid for the work in the sum of $51,800.00, which was accepted. Later on, and before the execution of any formal contract between the parties, at the suggestion or perhaps requirement of the mine inspector, the appellant company, without notice to the appellee, decided to supplement its plan by adding to them some sixteen shelter or manholes in the slopes, and had its engineer prepare a correct blueprint showing their character and location. On the 1st day of May, 1913, the parties met and entered into a formal written contract for the performance of the work on the basis of the accepted bid, and the plans and specifications submitted which were attached to and made part of the contract, as was also the corrected blueprint showing the sixteen manholes. The contract provides, among other things, “that the contractor must be prepared to undertake any extra work that may be required by the engineer arising out of a modification of the plans and details that may appear necessary, or from any unforeseen or unlooked for circumstances, and for such work will be paid at the contract rates for work of a similar character, or, if the extra work is of a class on which no rate is fixed in the contract, the engineer shall fix such a price or prices as he shall deem just and equitable, and the contractor shall abide by such price or prices, provided he commence work with a full knowledge of the same.” The appellee completed his contract and has been paid the amount of his original bid; but, insisting that extra work had been required of him, he demanded compensation therefor. To enforce this demand he brought his action at law, and the present appeal is from the judgment he recovered therein.

On the trial of the case the defendant submitted the following point, “Under the terms of the contract entered into May 1,1913, between F. J. Foye, plaintiff, and the Lilley Coal & Ooke Company, defendant, the blue print attached to said contract was a part thereof, and [413]*413the said blue print so attached to said contract showing that shelter holes were required to be placed on each side of the slope every forty-five feet, the plaintiff, F. J. Foye, was, under the terms of said contract, required to construct said shelter holes, and is therefore entitled to receive no additional compensation by reason of any work done or materials furnished in or about the construction of any shelter holes in the slopes referred to in said contract.” The refusal of the court so to instruct is the subject of the first assignment of error. It was the plaintiff’s contention that- notwithstanding the blue print was attached to and made part of the written contract, it had not been so attached with a view to require of him the construction of the manholes without other compensation than his original bid, but that its only purpose was to define and locate these manholes should the company conclude to construct them, or have them constructed. The evidence in the case largely supported this contention, and as we view the case, it was convincing. It does not rest alone on the testimony of the plaintiff. Supported as that is by the general facts and circumstances of the case, more particularly the dealings between the parties, strongly evidencing a mutual understanding of the. contract conforming to the plaintiff’s contention, it would have been quite sufficient to carry the question to the jury. But there was far more. The defendant’s engineer who drew the plans and specifications for the work, including the amended blue print showing the manholes, that was attached to the written agreement, and who was in charge of the work, was called as a witness by the defendant. He testified that it was not until after the slope had been driven in for a considerable distance that he first spoke to the plaintiff in regard to the manholes; that his purpose in speaking with him was to learn at what price the plaintiff would be willing to do this additional work; that they disagreed as to what would be a fair price, he, the engineer, offering $10.00 for each hole and the plain[414]*414tiff demanding $25; that later, after plaintiff had completed several of the manholes, he proposed to allow plaintiff at the rate of $13.00 for each, that price being based, as he said, upon the clause of the contract that specified that work of a similar nature is to be paid for at the proportionate amount of work to be done, and that later, in the estimate he made of the work done, he allowed the plaintiff $182.00 for fourteen manholes, regarding them as extra work, to be paid for as extra work under the contract. His language was, “I didn’t regard the shelter holes as being a part of the original contract, but I did regard them as being extra work.” It was not pretended that there was any understanding or agreement with the plaintiff that he was to receive compensation on any such basis as that allowed by the engineer, or that plaintiff received this money from the defendant company with any understanding or agreement on his part that it was full payment. Such being the evidence in the case — and much more of like tenor could be added —to have affirmed the point submitted would have been manifest error. The first assignment is overruled.

The second assignment has still less to support it. A point was submitted to the effect that the $182.00 allowed by the engineer and paid by the company, was a mere gratuity, and in no way a recognition of liability on the part of the defendant company to the plaintiff on account of the construction of the manholes. This point admitted of no other answer than refusal by the trial judge. This assignment is overruled.

The plaintiff, called on his own behalf as a witness, was permitted without objection to testify to the value and price of work in connection with the construction of the manholes. At the conclusion of this testimony the court was asked to strike it out. The refusal of the motion is the subject of the third assignment. The reasons urged in support of the motion, if any, do not appear in the record. The gist of the point, as we gather it from the argument in the brief is, that even though it [415]*415be conceded that the construction of the manholes was not specifically required of the plaintiff under the contract, yet it was such extra work as the engineer might require under its terms, to be paid for by the company at the rates therein provided for extra work, and that the engineer having classified the work done in connection therewith as extra work, and the price therefor having been fixed and determined by the engineer, that such determination was conclusive on the plaintiff, and therefore the testimony as to the cost of the construction was inadmissible. The argument overlooks a very material part of the section of the contract that is here appealed to. It is there expressly stipulated that “the contractor shall abide by such price or prices provided he commence work with a full knowledge of the same.” There is no pretense that the plaintiff before entering upon the construction of the holes was advised of the prices he would be allowed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re KELLETT AIRCRAFT CORP.
173 F.2d 689 (Third Circuit, 1949)
In Re Kellett Aircraft Corporation
173 F.2d 689 (Third Circuit, 1949)
Giles v. Vockel
166 A. 849 (Supreme Court of Pennsylvania, 1933)
Gordon Bros. Inc. v. Kelley
92 Pa. Super. 485 (Superior Court of Pennsylvania, 1927)
Pennsylvania R. R. v. Cameron
124 A. 638 (Supreme Court of Pennsylvania, 1924)
Sollenberger & Branthaver v. Scattergood
82 Pa. Super. 571 (Superior Court of Pennsylvania, 1923)
Rothschild v. Trexler Co.
82 Pa. Super. 116 (Superior Court of Pennsylvania, 1923)
Snowiss v. Elias Loeb & Co.
81 Pa. Super. 124 (Superior Court of Pennsylvania, 1922)
Meaker Galvanizing Co. v. Charles E. McInnes & Co.
116 A. 400 (Supreme Court of Pennsylvania, 1922)
Dillon's Estate
111 A. 919 (Supreme Court of Pennsylvania, 1920)
Dimmick v. Banning, Cooper & Co.
100 A. 871 (Supreme Court of Pennsylvania, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
96 A. 987, 251 Pa. 409, 1916 Pa. LEXIS 479, Counsel Stack Legal Research, https://law.counselstack.com/opinion/foye-v-lilley-coal-coke-co-pa-1916.