Foxworth-Galbraith Lumber Co. v. Southwestern Contracting Corp.

165 S.W.2d 221
CourtCourt of Appeals of Texas
DecidedOctober 2, 1942
DocketNo. 14420
StatusPublished
Cited by29 cases

This text of 165 S.W.2d 221 (Foxworth-Galbraith Lumber Co. v. Southwestern Contracting Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Foxworth-Galbraith Lumber Co. v. Southwestern Contracting Corp., 165 S.W.2d 221 (Tex. Ct. App. 1942).

Opinion

McDONALD, Chief Justice.

This suit involves principally a contest between two lienholders. The case was tried without a jury, and there appears to be no substantial dispute, if any, as to the facts proved, although the parties disagree ■ as to the legal consequences of the facts proved.

The suit was filed by City National Bank in Wichita Falls, herein designated simply as bank. In its original petition it alleges in substance as follows:

That Southwestern Contracting Corporation, designated in this opinion as contractor, executed a note for $3,S00, payable to the bank, dated March 21, 1940, and secured by deed of trust lien on Lot 12 of Block 31 of a certain addition in Wichita Falls; that the contractor executed a second note for $3,500, payable to the bank, dated March 28, 1940, secured by a deed of trust lien on Lot 16, Block 32, of the same addition; that the contractor executed a third note for $5,700, payable • to the bank, dated October 16, 1940; that the amount of $8,586.28 is past due and owing on the principal, interest and attorney’s fees of the first two notes (the two $3,500 notes); and that $4,190.15 is owing on the third note (the $5,700 note) ; that the defendant Foxworth-Galbraith Lumber Company, designated in this opinion as lumber company, is asserting some kind of a lien or claim against the property in question, which is inferior to the lien held by plaintiff. It is also alleged that E. V. McCright, a vice-president of the contractor corporation, joined in the execution of the notes. Plaintiff prays for foreclosure of its liens securing the two $3,500 notes, and prays for judgment, without asking for foreclosure of lien, against the contractor and McCright for the unpaid principal, interest and attorney’s fees due on the $5,700 note.

In its answer and cross-action, the lumber company alleges that the bank actually advanced less than $3,500 on each of the loans secured by the two deeds of trust. It alleges in particular that only $2,500 was advanced against one of the lots, and onl}’- $2,632 against the other, and that the lumber company tendered payment to the bank, before its notes were turned over to attorneys, of the full amounts actually secured by the bank’s liens. The lumber company prays that no foreclosure be allowed in favor of the bank above the amounts just mentioned.

The bank filed a pleading in answer to that of the lumber company, designated as an answer to it. In it the bank alleges that on March 21st and March 28th, respectively, of 1940, the contractor executed the two notes for $3,500 each, and the two deeds of trust; that at that time the contractor was engaged in the construction of numerous houses in Wichita Falls, and that it was agreed and understood at that time between the bank and the contractor that the bank would advance to the contractor the amount of $7,000, when needed by the contractor for the construction of houses on the two lots in question, and that at the time the notes were executed the bank advanced $2,500 on each of said notes, and later advanced to the contractor the sum of $5,700; that the advancements were made by reason of the execution of the two $3,500 notes; that the bank has advanced to the contractor a to[223]*223tal of $10,700, upon which amount there has been paid the sum of $2,107.01, leaving a balance due and owing of $8,592.99, besides interest and attorney’s fees, “which amount is secured by the two deeds of trust liens hereinabove described”; and that if defendant lumber company has any claim, it is inferior to the two deeds of trust held by plaintiff; that as evidence of said advancements, the contractor executed two $2,500 notes and one $5,700 note; that as the advancements exceeded the amount of the two $3,500 notes, the bank demanded that McCright individually execute the $5,700 note. The prayer for recovery in this pleading is not entirely clear to us, but perhaps it can be construed as asking for judgment and foreclosure on all of the notes held by the bank.

The evidence reflects that the two original $2,500 notes were each several times renewed, a part of the interest being paid, but nothing being paid on the principal. The sum of $2,107-01 was paid on the $5,-700 note. As to the application of this payment, more will be said later in this opinion.

After all of the above notes were given to the bank, the contractor gave two notes to the lumber company, and deeds of trust securing them. One of the deeds of trust covered one of the lots in question, the other deed of trust covered the other lot. One of them recited that it was inferior to a lien of $2,632 in favor of the bank, and the other recited that it was inferior to a lien of $2,500 in favor of the bank.

The effect of the judgment rendered by the trial court is to allow the bank a recovery of $3,500 principal, plus interest and attorneys’ fees, and foreclosure of lien, against each of the lots, and to allow the bank a money judgment only against the contractor and McCright upon a portion of the $5,700 note, the amount being arrived at as follows: enough of the $5,700 note was allocated, so to speak, to the secured portion of the loan transactions, so as to give the bank a secured loan of $3,500 against each of the lots. The payment of $2,107.01 was then applied to the unsecured portion of the $5.,700 note. Such calculations resulted in judgment in favor of the bank for foreclosure of lien in the amount of $4,238.70, including principal, interest and attorney’s fees, against each of the lots, and judgment for an unsecured debt of $2,144.93.

Speaking in terms of dollars and cents, the controversy involves the difference between the amount tendered by the lumber company to the bank as the total amount secured by liens against the two lots, to-wit, approximately $5,100, and the total of the two liens as adjudged by the trial court, to-wit, approximately $8,500. Although the contractor and McCright filed answers, they do not appear otherwise to have contested the suit, nor have they appealed.

The lumber company has appealed, presenting the contentions which we shall discuss.

The lumber company urges that the pleadings of the bank do not support the proof offered, and that neither the pleadings nor the proof supports the judgment.

As above set out, the bank’s original petition alleges the execution of the two $3,-500 notes, in March, 1940, and the execution of the $5,700 note in October, 1940. We find no allegations in this pleading which can be construed as alleging that the bank has or claims a lien to secure payment of the $5,700 note. The answer which the bank filed, in response to the lumber company’s answer and cross-action, does not purport to be an amended petition, nor does it have the requisites of one. It is not complete within itself, and obviously is not intended to be a substitute for the original petition.

The bank refers us to our new procedural rule No. 67, Texas Rules of Civil Procedure. As amended by Order of March 31, 1941, this rule reads as follows :

“Rule 67. Amendments to Conform to Issues Tried Without Objection. When issues not raised by the pleadings are tried by express or implied consent of the parties, they shall be treated in all respects as if they had been raised in the pleadings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robert P. Carswell v. Lori Lynn Cloud
Court of Appeals of Texas, 2003
White v. Sullins
917 S.W.2d 158 (Court of Appeals of Texas, 1996)
Hughes v. Team Bank (In Re Hughes)
172 B.R. 205 (N.D. Texas, 1993)
Bobby Smith Brokerage, Inc. v. Bones
741 S.W.2d 621 (Court of Appeals of Texas, 1987)
First Federal Savings & Loan Ass'n v. Stewart Title Co.
732 S.W.2d 98 (Court of Appeals of Texas, 1987)
Meeks v. Bell
710 S.W.2d 789 (Court of Appeals of Texas, 1986)
Ranger Insurance Co. v. Robertson
707 S.W.2d 135 (Court of Appeals of Texas, 1986)
Rankin v. Bateman
686 S.W.2d 707 (Court of Appeals of Texas, 1985)
Oldham's Farm Sausage Co. v. Salco, Inc.
633 S.W.2d 177 (Missouri Court of Appeals, 1982)
Realtex Corp. v. Tyler
627 S.W.2d 441 (Court of Appeals of Texas, 1981)
Jay Fikes and Associates v. Walton
578 S.W.2d 885 (Court of Appeals of Texas, 1979)
Coke Lumber & Manufacturing Co. v. First National Bank in Dallas
529 S.W.2d 612 (Court of Appeals of Texas, 1975)
Oakley v. Armstrong Transfer & Storage Co.
378 S.W.2d 912 (Court of Appeals of Texas, 1964)
Kemp v. Westbrook
358 S.W.2d 889 (Court of Appeals of Texas, 1962)
Bancroft v. Welch
250 S.W.2d 285 (Court of Appeals of Texas, 1952)
Temple Nat. Bank. v. Blackburn
235 S.W.2d 462 (Court of Appeals of Texas, 1950)
Prudential Fire Ins. Co. v. United Gas Corp.
191 S.W.2d 517 (Court of Appeals of Texas, 1945)
Texas, New Mexico & Oklahoma Coaches, Inc. v. Williams
191 S.W.2d 66 (Court of Appeals of Texas, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
165 S.W.2d 221, Counsel Stack Legal Research, https://law.counselstack.com/opinion/foxworth-galbraith-lumber-co-v-southwestern-contracting-corp-texapp-1942.