Foxfire Village, Inc. v. Black & Veatch, Inc.

404 S.E.2d 912, 304 S.C. 366, 1991 S.C. App. LEXIS 85
CourtCourt of Appeals of South Carolina
DecidedMay 13, 1991
Docket1662
StatusPublished
Cited by17 cases

This text of 404 S.E.2d 912 (Foxfire Village, Inc. v. Black & Veatch, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Foxfire Village, Inc. v. Black & Veatch, Inc., 404 S.E.2d 912, 304 S.C. 366, 1991 S.C. App. LEXIS 85 (S.C. Ct. App. 1991).

Opinion

Bell, Judge:

This is an action for breach of contract for failure to provide agreed engineering services in connection with the construction of a water and sewer system for a mobile home subdivision. Foxfire Village, Inc., the owner and developer of the project, sued Black & Veatch, Inc., the consulting engineers, alleging breach of contract, breach of contract accompanied by a fraudulent act, fraud, negligent misrepresentation, and breach of fiduciary duty. Black & Veatch answered alleging, among other things, breach of contract, contributory negligence, and lack of damages. They also counterclaimed for the unpaid balance on the contract and for indemnification. The circuit court referred the matter to the master in equity to enter final judgment with direct appeal to the Supreme Court. The master entered judgment for Foxfire for breach of contract in the sum of $393,834.75. He incidentally found that Black & Veatch breached fiduciary duties to Foxfire. He dismissed the counterclaims. Black & Veatch appeals. Foxfire cross appeals on *369 its claims for breach of contract accompanied by a fraudulent act, fraud, and negligent misrepresentation. We affirm.

The master awarded damages for breach of contract. 1 Accordingly, the judgment is at law. In an action at law, the reviewing court must view the facts in the

light most favorable to the party prevailing at trial. South Carolina Federal Savings Bank v. Thornton-Crosby Development Co., __ S.C__, __, 399 S.E. (2d) 8,11 (Ct. App. 1990). If there is any evidence to support the judge’s findings of fact we must affirm the judgment. Id.

In 1982, Foxfire undertook to develop a mobile home park in North Myrtle Beach, South Carolina. In August of that year, Foxfire requested Moore, Gardner and Associates (now Black & Veatch) to provide engineering services for the project. A contract was signed on October 6,1982, with a written amendment executed on October 25, 1982. The contract, as amended, bound Black & Veatch to perform the following services, among others:

(1) Prepare a final development plan for the entire project showing proposed streets, water and sewer lines, drainage, and existing utility locations.
(2) Design proposed street and utility improvements and develop plans and specifications adequate in detail for construction of street alignments and grades, water distribution lines, gravity wastewater lines, master meter, grading plan and drainage, sewage pump station and force main.
(3) Submit engineering plans for local and state approvals.
(4) Expedite review by the South Carolina Department of Health and Environmental Control.
(5) Serve as the owner’s professional representative for the services covered by the contract and provide professional advice and consultation to the owner.
*370 (6) Provide all services in accordance with generally accepted professional practices.

Richard Delap was Black & Veatch’s project engineer for the Foxfire development. In October, 1982, Delap began supervising preparation of plans and specifications for the project. He knew the rules and regulations of the Department of Health and Environmental Control and was familiar with its permitting process. He knew that before issuing any construction permits for wastewater and water systems, the Department required a licensed engineer to submit and certify plans and specifications for the project and to complete the Department’s application form. He knew that Foxfire could not legally begin construction until the Department approved the plans and issued a permit for the project. He also knew Foxfire needed construction permits from the City of North Myrtle Beach and the South Carolina Coastal Council before it could build the project.

In January, 1983, Delap and officers of Foxfire attended a meeting of the North Myrtle Beach City Council at which the Council approved the project for a building permit, based on plans and specifications prepared and submitted by Delap. The record indicates, and the master found, that after this meeting Delap advised Foxfire officials they could begin construction on the project. Construction on the water and sewer systems began in late January, 1983. By August, 1983, all of Phase I of the project and part of Phase II were completed.

At the time construction began, Delap had not applied to the Department for permits to construct the water and sewer systems. He did not advise Foxfire of this fact. On May 23, 1983, after the project was well under construction, Delap sent a letter to the Department enclosing plans and specifications and an Application for Permit to Construct. He did not reveal that the project was already under construction.

The application was received on May 30, 1983. In response to the application, the Department sent two letters, dated June 6, 1983, and June 29, 1983, informing Delap that the plans and specifications needed to be modified, that he needed to submit additional designs for certain components of the systems, that additional information about the systems was needed, and that certain additional items needed to be re *371 solved before the Department could issue the construction permit. Delap received but never responded to these letters.

Almost a year later, by a letter dated May 15,1984, the Department again wrote Delap, stating it had received no response to its prior letter about the Foxfire project. It went on to state that unless Delap responded within 30 days, the project would be dead-filed. Delap received but did not respond to this letter. As a result of Delap’s failure to respond, the application process was ended and the records were dead-filed.

In May, 1985, the Department learned the Foxfire project had been constructed without a permit and had been placed into operation without final inspection or approval by the Department. In October, it wrote Foxfire a letter (with a copy to Delap) stating that the project was in violation of state law and indicating that it would pursue an enforcement action unless Foxfire promptly took specified steps to resolve the matter. Upon receipt of this letter, Foxfire referred it to Delap, who stated the matter would be taken care of. Among other things, the letter required Foxfire to submit “as-built” plans of the project to the Department within 60 days. Delap did not prepare and submit the “as-built” drawings until May, 1986. With this submission, he also forwarded the original material and construction specifications for the project. By two further letters, dated June 4,1986, Delap forwarded applications for a Permit to Construct the water and sewer systems and the sewage pump station and also certified to the Department that the project was built in accordance with the specifications and the “as-built” drawings.

After reviewing the new submission, the Department, on June 26, 1986, wrote a letter to Ellis Spake, an engineer with Black & Veatch, requiring numerous revisions in the plans, specifications, and design for the project before it could be permitted. Spake did not respond to this letter.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

IOS, LLC v. Lander University
Court of Appeals of South Carolina, 2025
Perkins v. SCDOT
Court of Appeals of South Carolina, 2021
Beneficial Financial I v. Jon Windham
Court of Appeals of South Carolina, 2020
Oak Pointe v. Peffley
Court of Appeals of South Carolina, 2018
Bentrim v. Wells Fargo Bank
Court of Appeals of South Carolina, 2017
LANDBANK FUND VII, LLC v. Dickerson
632 S.E.2d 882 (Court of Appeals of South Carolina, 2006)
Anderson v. Greene
Court of Appeals of South Carolina, 2006
Enhance-It, L.L.C. v. American Access Technologies, Inc.
413 F. Supp. 2d 626 (D. South Carolina, 2006)
Osborn v. UNIVERSITY MED. ASSOC., MED. UNIV. OF SC
278 F. Supp. 2d 720 (D. South Carolina, 2003)
Osborn v. University Medical Associates of the Medical University
278 F. Supp. 2d 720 (D. South Carolina, 2003)
Robertson v. First Union National Bank
565 S.E.2d 309 (Court of Appeals of South Carolina, 2002)
Wilson Group, Inc. v. Quorum Health Resources, Inc.
880 F. Supp. 416 (D. South Carolina, 1995)
Hendrix v. Eastern Distribution, Inc.
446 S.E.2d 440 (Court of Appeals of South Carolina, 1994)
Myrtle Beach Pipeline Corp. v. Emerson Electric Co.
843 F. Supp. 1027 (D. South Carolina, 1993)
Mendelsohn v. Whitfield
430 S.E.2d 524 (Court of Appeals of South Carolina, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
404 S.E.2d 912, 304 S.C. 366, 1991 S.C. App. LEXIS 85, Counsel Stack Legal Research, https://law.counselstack.com/opinion/foxfire-village-inc-v-black-veatch-inc-scctapp-1991.