Fox v. Clark

44 A.D. 626, 60 N.Y.S. 237
CourtAppellate Division of the Supreme Court of the State of New York
DecidedOctober 15, 1899
StatusPublished
Cited by1 cases

This text of 44 A.D. 626 (Fox v. Clark) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fox v. Clark, 44 A.D. 626, 60 N.Y.S. 237 (N.Y. Ct. App. 1899).

Opinion

Woodward, J.:

The plaintiff in company with one Fallon entered into a written contract to erect two cottages for the defendant for the sum of $4,675. The firm of Fox & Fallon agreed to furnish all of the material and labor in the construction of these cottages, to be located in the village of New Rochelle, the work to be done according to the plans and specifications furnished by Charles Palliser, architect, and under his supervision. It was agreed that the first payment of $450 on each of the cottages should be made when the frames were up; the sheathing on and the roofs up. The second payment of $600 on each house “ when each house is ready for lathing and when each house is enclosed.” The third payment was to be made when the houses were inclosed, the sash in and the floors laid, and the final payment was to be made five days after the completion of the houses. This agreement was with the proviso “-thatin each case of the said payments, a certificate shall be obtained from and signed by Charles Palliser, architect, to the effect that the work is done m.st-ricfc accordance with the drawings and specifications, and that he considers the payment properly due.” The firm of Fox & Fallon began work in December, 1895. and subsequently the-architect gave two certificates for the payment of the $450 on each of the two buildings. On the 1st day of February, 1896, Richard B. Fallon, one of the parties to the contract, met the architect and asked him for a certificate for a second payment on one of the houses. The architect made an examination and found that the payment was not due; that there were several things yet to be done before'there was anything due under the terms Of the contract, and he made a memorandum of the work necessary 'to be done before he could give a certificate. The work continued upon the houses until the 7tii day of February, 1896, when the defendant received a'létter from Fox & Fallon stating that the second payments were due on both houses, and that, as they had not been paid, they had stopped work. No more work was done by this firm, and no further communication passed between them until the twelfth day of February, a legal holiday, when the defendant visited the premises to look over the houses. There was no carpenter work in progress upon the buildings at that time, but the plaintiff, who had been drinking, and was apparently much under the influence of liquor, was there in company with the architect and others. The architect was attempting to explain to the plaintiff what would he necessary to complete the work so that the second payment would be due. Upon the appearance of the defendant plaintiff demanded to know why the second payment was not made, and defendant told him.he was ready and willing to make the payment as soon as plaintiff secured the necessary certificates. The plaintiff then demanded the certificates from the architect, who explained to him the work necessary to be done in order that the plaintiff should be entitled to the second payment. The plaintiff fell into a rage, using harsh and abusive language toward the architect, who appealed to the defendant for protection. - At this point defendant interfered and told the plaintiff that he was drunk and ordered him to leave the premises. There is no material dispute up to this point, but it is contended on the part of the plaintiff that in ordering the plaintiff to leave the premises the defendant told him to present his bills, and that he (the defendant) would pay him all that was coming to him. Upon this there is a conflict of evidence, the defendant, corroborated by his witnesses, denying anything more than the order of the defendant for the plaintiff feo leave the premises; the plaintiff, supported by -his witnesses, holding'to-the promise of the defendant to .pay anything which might be due to the plaintiff. On this appeal from the decision of the referee, however, the plaintiff does not contend that this constituted a new contract, but that it was a rescission of the original contract, and he seeks to recover for that portion of the work and materials which had been furnished up to the twelfth day of February, when he was ordered from the premises. The learned referee computes the amount which the plaintiff had expended up to the time of the so-called rescission of the contract, and, after crediting the defendant with the $900 which he had paid, directs judgment for the balance, with costs and interest, aggregating $£¡745.25. The defendant sets up in his answer a counterclaim for-damages due to the refusal of the plaintiff to comply with the provisions of the contract, and denies that he refused to make payments when due, or that the contract was rescinded, and alleges full performance on his part of all of fche terms and conditions of the contract. We are of opinion that-the learned referee has erred in his application of the law to the facts in this case. There could be no question of .substantial performance of the contract, the contract was fertile completion of two cottages in the manner pointed out by the plans and specifications, but the payments were to be made in installments upon the certificate that the buildings had reached a certain stage of completion. The question on the l£fcn day [627]*627of February, 1896, was not whether the plaintiff had substantially complied with his contract, but whether- the second payment was due. The test of whether that payment was due was whether the buildings .were “ enclosed and ready for lathing,” and it was stipulated in the contract that the evidence of this fact should be the certificate of the architect to the effect “ that the work is done in strict accordance with the drawings and specifications, and that he considers the payment properly due.” The complaint contains no averment that the architect unreasonably withheld his certificate, as it should have done. (Weeks v. O'Brien, 141 N. Y 199, 202.) The defendant did not call the attention of the court to the defect, buc it may be said that there was no evidence in the case from which it could be fairly inferred that the architect was actuated by any improper motives in refusing to give the certificate at the time. He was required by the contract to state in effect that “the work is done in strict accordance with the drawings and specifications, and that he considers the payment properly due.” Admitting that evidence might be received in support of the theory that the certificate was unreasonably ■withheld, to establish such unreasonableness under the provisions of the contract it was necessary to show not only an absolute compliance with the drawings and specifications, but facts which would establish that the architect could not, with any fair degree of reason, have any doubt that the payment was “properly due.” We fail to find such evidence in the record. On the contrary, it appears from the plaintiff’s own admissions that the heating pipes, speaking tubes, etc., which the plans and specifications called for, and which it was necessary should be in place before the lathing could be completed, were not in the building at the date mentioned. This being merely a payment of an installment, there could be no substantial performance which would render the payment due. The plaintiff suffered no legal wrong by having his payment deferred until he had complied with the conditions necessary to entitle him to payment; he could have completed the construction within the terms and conditions of the contract, and recovered the amount agreed upon by showing a substantial performance of the whole contract, but he could not claim tha& a single installment was due, except by complying with the letter of the agreement under which the parties were acting.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hansen v. Hackman
37 Misc. 290 (New York Supreme Court, 1902)

Cite This Page — Counsel Stack

Bluebook (online)
44 A.D. 626, 60 N.Y.S. 237, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fox-v-clark-nyappdiv-1899.