Fox Ridge Village, LP v. PUC

CourtCommonwealth Court of Pennsylvania
DecidedJune 9, 2021
Docket854 C.D. 2020
StatusUnpublished

This text of Fox Ridge Village, LP v. PUC (Fox Ridge Village, LP v. PUC) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fox Ridge Village, LP v. PUC, (Pa. Ct. App. 2021).

Opinion

IN THE COMMONWEALTH COURT OF PENNSYLVANIA

Fox Ridge Village, LP, : Petitioner : : v. : No. 854 C.D. 2020 : SUBMITTED: May 13, 2021 Public Utility Commission, : Respondent :

BEFORE: HONORABLE ANNE E. COVEY, Judge HONORABLE MICHAEL H. WOJCIK, Judge HONORABLE ELLEN CEISLER, Judge

OPINION NOT REPORTED

MEMORANDUM OPINION BY JUDGE CEISLER FILED: June 9, 2021

Fox Ridge Village, LP (Developer) petitions this Court for review of the Public Utility Commission’s (PUC) August 6, 2020 order adopting the initial decision of an administrative law judge (ALJ). The ALJ granted the petition of Pennsylvania-American Water Company (PAWC), which sought a declaratory order that PAWC complied with the Public Utility Code (Code),1 the PUC’s regulations, and PAWC’s tariff2 when it refused to accept water facilities constructed, or anticipated to be constructed, in Developer’s residential development (the Development), and to provide the Development with water service. After review, we affirm.

1 66 Pa.C.S. §§ 101 – 3316.

2 “Tariff,” as defined in Section 102 of the Code, refers to a public utility’s schedule of “rates, all rules, regulations, practices, or contracts involving any rate or rates . . . .” 66 Pa.C.S. § 102. I. Background While this litigation has an extensive procedural history, the underlying facts are largely undisputed. PAWC is a public utility that provides water and wastewater services throughout Pennsylvania. Certified Record (C.R.), Item No. 7, ALJ Initial Decision, Finding of Fact (F.F.) No. 1. Developer is a limited partnership, whose principal owner is Frank Zokaites (Zokaites). F.F. No. 2. The Development is located on approximately 30 acres of land in North Strabane Township (Township), Allegheny County. F.F. No. 3. On April 19, 2017, Developer and PAWC executed a Water Facilities Line Extension and Special Facilities Agreement (Agreement), which provided that Developer would construct the Development’s water facilities in exchange for PAWC’s agreement to provide water service to the Development. F.F. No. 17. PAWC’s tariff granted PAWC the exclusive right to determine the size and type of water mains installed in the Development as well as any other facilities required to provide the Development with adequate water service. F.F. No. 8. A steep hill in Phase II of the Development required the construction of a booster pump station to provide adequate water pressure to Phase II homes located above 1,220 feet in altitude. F.F. No. 6. In addition to the booster pump station, the Development’s water facilities required three pumps and a standby generator, which would operate in the event of power loss. F.F. Nos. 9, 14-15. The Agreement specified that the two pumps used for domestic water service would provide 70 gallons per minute (gpm) and the third pump would provide 750 gpm for fire protection service. F.F. No. 19. Exhibit C of the Agreement included a proposal from USEMCO, a PAWC-approved vendor, for the construction of the booster pump station, including three pumps and a diesel generator. F.F. No. 21.

2 The Agreement further provided that the water facilities constructed by Developer would become part of PAWC’s water system upon PAWC’s inspection, testing, and acceptance of the water facilities. F.F. No. 18. PAWC would not provide water service to the Development unless PAWC approved all plans and specifications prior to construction of the water facilities and Developer obtained all necessary permits and met the requirements of “all governmental agencies having jurisdiction.” F.F. No. 20. On April 28, 2017, and May 12, 2017, PAWC contacted Developer to inquire about the submittal package PAWC would ordinarily have received from its approved vendors. F.F. No. 24. Developer subsequently notified PAWC that it had chosen to use a non-approved vendor, Dakota Pump, Inc. (Dakota), to construct the water facilities, which would include two separate electric substations in lieu of a generator. F.F. No. 25. On May 30, 2017, and June 5, 2017, PAWC informed Developer that the generator was necessary and that Dakota was not a PAWC- approved vendor. F.F. No. 26. PAWC also notified Developer in a June 11, 2017 letter that a booster station constructed by Dakota might not be acceptable to PAWC. F.F. No. 27. Thereafter, the parties engaged in extensive discussions regarding the terms of Dakota’s proposal. F.F. Nos. 29-34, 36-40. In August 2017, PAWC accepted a portion of the water facilities located within the Development and began providing water service at that time. F.F. No. 64. However, PAWC could not provide adequate water pressure to any homes in Phase II of the Development located above 1,220 feet. F.F. No. 65. As a result, PAWC refused to provide water service until Developer installed an acceptable booster pump station. Id.

3 On August 17, 2017, Developer filed a complaint in the Court of Common Pleas of Allegheny County (trial court), seeking an order compelling PAWC to accept the water facilities in the Development and provide water service thereto. ALJ Decision at 2. The trial court found that the PUC had primary and exclusive jurisdiction over the issues raised by Developer and dismissed Developer’s claims on that basis. Id. The trial court’s order also stayed the proceedings. Id. On September 7, 2017, PAWC filed an Amended Petition for Declaratory Order (Amended Petition)3 with the PUC, averring that it refused to accept the Development’s water facilities because they did not meet the specifications established in the Agreement. R.R. at 5a-14a. PAWC’s Amended Petition sought a declaration that, in refusing to accept the water facilities as constructed, or which Developer expected to construct, PAWC complied with the Code, the PUC’s regulations, and PAWC’s tariff. Id. at 7a. Developer filed an answer, denying any alleged deficiencies in the Development’s water facilities and asserting that the water pressure in the Development was sufficient and installation of a pump station was unnecessary. R.R. at 15a, 22a. Developer further asserted that PAWC’s refusal to accept the Development’s water facilities and provide water service exceeded the scope of PAWC’s tariff and constituted a violation of the Agreement, with which Developer had fully complied. Id. at 23a, 25a. Developer requested injunctive relief compelling PAWC to install water meters in the Development and provide water service and requested a declaratory order that the generator required by PAWC under the Agreement was unnecessary. Id. at 27a, 29a. Additionally, Developer filed a

3 PAWC filed a Petition for Declaratory Order on August 28, 2017. C.R., Item No. 95. It filed the Amended Petition to reflect the trial court’s dismissal of Developer’s claims and its stay of those proceedings. Reproduced Record (R.R.) at 6a.

4 separate Emergency Petition for Injunctive Relief (Emergency Petition),4 which sought an order compelling PAWC to install water meters and water lines in the Development.5 C.R., Item No. 93. The ALJ issued an interim order on October 19, 2017, directing the parties to test the Development’s water pressure in the presence of the Township Fire Department. C.R., Item No. 76. The resulting tests performed at a fire hydrant and a blow-off valve located at the top of a hill revealed residual pressure readings between 0 and 12 pounds per square inch (psi) and water flow of 531-1,100 gpm. ALJ Decision, F.F. Nos. 41-52. The Township Fire Department concluded that the fire hydrant was not capable of supplying the water pressure or water flow necessary to properly respond during a fire emergency. F.F. Nos. 55-56. Following several weeks of continued negotiations, Developer filed petitions to withdraw its Emergency Petition and the Petition for Declaratory Order (collectively, Withdrawal Petitions), citing the existence of a settlement agreement between the parties. C.R., Item Nos. 56-57; R.R.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mazzella v. Koken
739 A.2d 531 (Supreme Court of Pennsylvania, 1999)
Muhammad v. Strassburger, McKenna, Messer, Shilobod & Gutnick
587 A.2d 1346 (Supreme Court of Pennsylvania, 1991)
Germantown Cab Co. v. Public Utility Commission
97 A.3d 410 (Commonwealth Court of Pennsylvania, 2014)
Chester Water Authority v. Pennsylvania Public Utility Commission
868 A.2d 384 (Supreme Court of Pennsylvania, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
Fox Ridge Village, LP v. PUC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fox-ridge-village-lp-v-puc-pacommwct-2021.