Fox Islands Wind Neighbors v. Maine Dep't of Envtl. Protection

Superior Court of Maine·Decided March 10, 2014·No. KENap-11-42·Unpublished

Opinion

STATE OF MAINE SUPERIOR COURT KENNEBEC, ss CIVIL ACTION DOCKET NO. AP-11i42;.

lliJMill~ V'r.t.f~ ? ,t/o .-/c;..'

7 t\,t:_; r "--1// "'~,/ " .'

, If, r u

' )/ jl

FOX ISLANDS WIND NEIGHBORS, et al., Petitioners,

v. ORDER ON RULE 80C PETITION

MAINE DEPARTMENT OF ENVIRONMENTAL PROTECTION, et al., Respondents.

Before this Court are: 1) Rule 80C Petition filed by Fox Island Wind Neighbors (the "Petitioners" or the "Neighbors") seeking review the "Condition Compliance Order" (the "CCO") issued on June 30, 2011 by the Department of Environmental Protection (the "DEP"); and 2) a motion to dismiss the Neighbors' Petition on mootness grounds filed by Party-in- Interest, Fox Island Wind, LLC ("FIW").

PROCEDURAL BACKGROUND

On July 28, 2011, the Neighbors and various individual residents of Vinalhaven, Maine filed a Rule 80C Petition for review of the CCO issued on June 30, 2011 by the DEP, which approved a "Revised Operating Protocol" submitted by FIW in response to the DEP's determination that FIW violated 06-096 C.M.R. ch. 375, §10 (2001) while operating a small-

scale wind energy project located on the island ofVinalhaven. 1 In their Petition, the Neighbors asserted that the ceo was the product of political intervention, which undermined the judgment ofthe DEP's professional staff and consultants. (Pet. 19.) The Petition further argued that the

ceo was in violation of statutory provisions requiring wind energy projects to be regulated to prevent excessive noise, in excess of statutory authority, unsupported by substantial evidence,

arbitrary and capricious, and affected by abuse of discretion. (Pet. 21-22.)

This case has a complex procedural history and the Court has issued multiple orders. On March 20, 2012 the Court denied a Motion to Dismiss brought by FIW and the DEP who claimed that this Court lacked jurisdiction as the CCO at issue was "certification" would not be judicially reviewable by statute. 35-A M.R.S.A §3456(2). The Court found that because the

ceo at issue was better characterized as "enforcement" -- if for no other reason than the certification of this wind project occurred on June 5, 2009 and the complaints of violations of the

noise rules arose over a year later after certification (on July 17 and 18, 2010). Moreover, the Court found that prior to the final agency action at issue, the DEP had included in the certification enforcement mechanisms by establishing operational and complaint protocols which would have to be followed if complaints were made and validated regarding noise levels after the turbines began spinning.

Nine days later, the DEP filed a Motion to Reconsider the order denying the motions to dismiss, adding a new argument not raised in the initial briefing, namely whether the Neighbors had standing to challenge the DEP's enforcement of violations ofthe CCO. The Court first noted that the DEP had previously conceded that if the CCO at issue constituted enforcement then the

1 The license, Certification# L-24564-ES-A-N, to operate a small scale wind energy project, issued by the DEP to FIW, contained a finding that FIW's turbines satisfied noise control rules pursuant to 06-096 C.M.R. ch. 375, § 10 (2001), but was subject to conditions, including sound monitoring and an amendment of certification if violations occur. It included special condition #8 in the certification, and a mandatory amendment process if noise standards were exceeded.

Court had jurisdiction to review the agency action but only if the dispute was between the Department and the developer. The Court rejected the DEP's argument that no Maine citizen who lives adjacent to a small-scale wind development has the right to seek judicial review of even post-certification actions of the Department, and the argument that the only remedy for abutters to wind projects would be to pursue and prevail in a common law claim for nuisance against the developer. The Court rejected the Respondents' reliance upon Great Hill Fill & Gravel v. Board of Environmental Protection, 641 A.2D 184 (Me. 1994) and relied instead upon the Law Court's decision in Friends of Lincoln Lakes v. Department of Environmental Protection, Maine Supreme Judicial Court, Mem. Docket No. BEP-10-554 (June 6, 2011), as well as general principles of standing in denying the motion to reconsider. Lindemann v. Comm 'non Governmental Ethics and Election Practices, 2008 ME 187, 961 A.2d 538.

On April13, 2012, the Neighbors filed an amended petition, which added two additional claims for relief under the United State Constitution and 42 U.S.C. 1983: Count III alleged that the CCO violated the Neighbors' right to petition the DEP protected by the First Amendment; and Count IV alleged that the CCO discriminated against the Neighbors in violation of the Fourteenth Amendment's Equal Protection Clause by depriving them of the right to be protected from excessive noise that is available to any other Maine resident in close proximity to a wind project. FIW and DEP then filed motions to dismiss the independent claims, which were granted by the Court on November 1, 2012. The Court found that the Neighbors had available to them a means to obtain direct judicial review of the agency action through the Maine Administrative Procedure Act, and that review under Rule 80C could provide adequate remedies for the Neighbors if they prevailed. The Court also noted that constitutional arguments could be made as part of the Rule 80C proceeding and issued a Consent Order addressing this issue and other

matters on November 27, 2012. The consent order allowed the Neighbors to include their constitutional arguments in their Rule 80C brief on the merits pursuant to 5 M.R.S.A. § 11007(4)(C)(1). The parties proceeded to brief the merits ofthe Rule 80C proceeding, and oral argument was conducted on July 15,2013. Just before oral argument, the Court met with counsel to the parties to· suggest a judicially-assisted settlement conference with another Superior Court Justice.

On July 19, 2013, FIW moved this Court to dismiss the Neighbors' 80C Petition on mootness grounds. FIW argues that the Petition is now moot because of the DEP's May 7, 2013 findings that FIW is operating in compliance with the DEP' s noise regulation as a result of FIW having installed serrated fins on its turbine blades and thereby having decreased noise by 2-4 dB A.

The parties agreed in late summer of2013 to participate in multiple sessions of judicially-

assisted settlement conferences, but the undersigned Justice was notified in November of 2013 that settlement efforts were unsuccessful. The Court then took the matter under advisement.

FACTUAL BACKGROUND

On March 24, 2009, FIW applied with the DEP to build and operate a small-scale wind energy development project on Vinalhaven, Maine. (Br. of Pet. 5.) On June 5, 2009, the DEP issued FIW a Certification pursuant to 35-A M.R.S.A. § 3456 approving the project. (Petitioners' Rule 80C Brief Appendix 10.i Condition No.8 of the Certification provided:

If the compliance data indicates that, under most favorable conditions for sound propagation and maximum amplitude modulation, the proposed project is not in compliance with Department standards as described in Finding 3, within 60 days of a determination of non-compliance by the Department, the applicant shall submit, for review and approval, a revised operation protocol that demonstrates

2 Hereinafter, record materials cited in Petitioners' Rule 80C Brief Appendix containing most relevant documents from the record will be referred to as "Pet. App."

that the project will be in compliance at all the protected locations surrounding the development.

In other words, according to Condition No.8, ifFIW's turbines were to produce noise in excess of applicable standards, FIW would be required to implement a noise-reduction operation plan using a "revised operation protocol."

Free access — add to your briefcase to read the full text and ask questions with AI

Fox Islands Wind Neighbors v. Maine Dep't of Envtl. Protection, (Me. Super. Ct. 2014).

Fox Islands Wind Neighbors v. Maine Dep't of Envtl. Protection (Fox Islands Wind Neighbors v. Maine Dep't of Envtl. Protection) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Yick Wo v. Hopkins
118 U.S. 356 (Supreme Court, 1886)
Snowden v. Hughes
321 U.S. 1 (Supreme Court, 1944)
Burlington Truck Lines, Inc. v. United States
371 U.S. 156 (Supreme Court, 1962)
Carcieri v. Salazar
555 U.S. 379 (Supreme Court, 2009)
Mekhoukh v. Ashcroft
358 F.3d 118 (First Circuit, 2004)
Powell v. Alexander
391 F.3d 1 (First Circuit, 2004)
SFW Arecibo Limited v. Rodriguez
415 F.3d 135 (First Circuit, 2005)
Torromeo v. Town of Fremont
438 F.3d 113 (First Circuit, 2006)
Carcieri v. Kempthorne
497 F.3d 15 (First Circuit, 2007)
Creative Environments, Inc. v. Robert Estabrook
680 F.2d 822 (First Circuit, 1982)
Christopher v. Smithkline Beecham Corp.
132 S. Ct. 2156 (Supreme Court, 2012)
Newton v. LePage
700 F.3d 595 (First Circuit, 2012)
Lindemann v. Commission on Governmental Ethics and Election Practices
2008 ME 187 (Supreme Judicial Court of Maine, 2008)
Thacker v. Konover Development Corp.
2003 ME 30 (Supreme Judicial Court of Maine, 2003)
New England Telephone & Telegraph Co. v. Public Utilities Commission
448 A.2d 272 (Supreme Judicial Court of Maine, 1982)