STATE OF MAINE SUPERIOR COURT CIVIL ACTION KNOX, ss. DOCKET NO. CV-04-17 RE f l q F """ ?;I? ,:,. - 'q,"g .. --. ... ., , , ., -~~
g 7 .,;< ., ,k >: , > ,7:\ 4d . , , + L FOX ISLAND GRANITE e~~NY,'i%13
Plaintiff @"t' -,::-! ,-' d
,$k$ t4y,-+
v. * mr DECISION A N D ORDER
AMERICAN GRANITE VANUFACTURERS, INC.,
T h s matter is before the court after bench trial on damages.
Plaintiff filed its complaint with the Clerk of the Superior Court on March 15,
2004. On April 8, 2004, a return of service was filed with the court indicating that the
summons and complaint had been served on Mchael J. Norris, Clerk of American
Granite Manufacturers, Inc. on March 23, 2004, at 3:05 p.m. On May 19, 2004, plaintiff
filed an affidavit and request for default and default judgment with the court and
default was entered by the associate clerk on May 25, 2004. Plaintiff requested a
hearing on damages.
A hearing on damages was held by tlxs court on October 21, 2004. Plaintiff was
present in the person of Daniel Bickford, president and shareholder of plaintiff
corporation along with its counsel. Defendant was represented by counsel and its
general manager. At the hearing, counsel for defendant first challenged the intention of
the court to proceed to hearing by first orally moving the court for a continuance
advising it that he had been retained by deferidant no earlier than 7:00 a.m. o'clock the
same morning. Counsel further advised the court that he had received a
communication at 6:00 p.m. the previous evening from the clerk of the defendant corporation and had been retained the following morning. First, counsel advised that
he had witnesses who were not able to testify as one was out of the country and the
others were in Massachusetts. It was represented that the defendant was not notified of
the instant hearing by its corporation clerk until two days previous. Counsel requested
an opportunity to move to set aside t l e default.
Upon inquiry by the court as to the nature of the excusable neglect to be
proposed and the nature of the meritorious defense, defendant's counsel advised that
investigation was being made as to the issue of jurisdiction, issue of service and why the
clerk of the corporation, a Massachusetts attorney, did not properly advise h s client.
As to the meritorious defense, he challenges the nature of the contract with the
individuals rather than the plaintiff corporation and the question of foreseeability of the
damages. Counsel also challenged the allegation by plaintiff that it had complied with
all of the terms of the contract in issue. Finally, defendant seeks to argue the failure of
the plaintiff to mitigate its damages.
After hearing argument of counsel, the court concluded that whatever issues
exist between the defendant and its clerklattorney is a matter between those parties
under Massachusetts's law and not before h s court. The court noted that sufficient
opportunity had been given the defendant to present pleadings including an extra 30
days from default requested by defendant's clerk/attorney and granted by plaintiff's
counsel. Further, with respect to any issues of jurisdiction or matters on the merits
relating to the defendant, the court indicated that it would give the parties sufficient
opportunity to challenge any of the conclusions reached by appropriate motion. The
matter went to hearing.
Because of the default, ". . . the allegations in the plaintiff's complaint are deemed
to be true and become findings of fact." McAlister v. Slosberg, 658 A.2d 658 (Me. 1995). Citing Brouillard v. Allen, 619 A.2d 988, 998 (Me. 1993); Forbes v. Wells Beach Casino, Inc.,
409 A.2d 646,652 (Me. 1979).
The complaint establishes that the plaintiff is a Maine corporation and the
defendant is a Massachusetts corporation. Plaintiff and defendant entered into a
contract on March 14, 2002, w h c h Bickford agreed to sell and the defendant agreed to
purchase all of plaintiff's production of certain types of granite to be produced by
plaintiff at its quarry. Pursuant to the agreement, the plaintiff shpped to the defendant
certain granite blocks w h c h were accepted by the defendant but who has refused and
failed to pay for the blocks.
Count I1 of the complaint establishes that the plaintiff delivered to the defendant
the granite blocks with reasonable expectation of being paid, defendant has refused to
pay, it would be unjust for defendant to retain said blocks without payment and that
plaintiff is entitled to reasonable value.
Count I11 of the complaint asserts that in anticipation of the defendant honoring
the contract, plaintiff purchased substantial amounts of equipment and incurred other
start-up expenses but, because of defendant's breach, plaintiff was forced to cease
operation and to sell its equipment all at substantial losses. In addition to the forced
sale of the equipment at a discount, plaintiff lost money invested in the enterprise and
substantial profits that would have arisen from the enterprise.
Daniel F. Bickford and Lucy M. Bickford are lifelong residents of Vinalhaven.
They have owned a granite quarry in that community since 1985. In November of 2001,
Mr. Bickford became aware that American Granite Manufacturers, Inc. (AGM) of
Marlborough, Massachusetts, had expressed an interest in acquiring some Maine
granite. Mr. Bickford sent to a Mr. Marcello Mallegni some samples of Vinalhaven
granite. Upon Mr. Mallegni's positive response, Mr. Bickford visited with hm in Marlborough, Massachusetts. Subsequently, Mr. Mallegni visited Mr. Bickford at the
quarry. That same month, Mr.. Bickford wrote to Mr. Mallegni acknowledgng the
previous visit and relayed some information as to operational expenses to open and
operate the quarry. After Mr. Mallegni communicated to Mr. Bickford that he had an
interest in purchasing all of the quzry's production, Mr. Bickjord, through the use of
h s corporation, developed a business plan. Through the use of h s business plan and
communications with Mr. Mallegni, plai~tiffacquired a $200,000 line of credit with the
Damariscotta Bank & Trust. T h s line of credit was secured by a certificate of deposit in
the possession of the bank belonging to an investor supporting plaintiff's efforts.
A second letter was sent in January 2002 to Mi. Mallegni at h s address at
Leamar Industries at the same address as American Granite Manufacturers, Inc. with
more details as to the work being done to prepare for the production of the quarry. In
the letter, Mi. Bickford Qscussed h s line of credit, the price of the product and
equipment being prepared for purchase or lease to operate the quarry.
Again, in February, continuing the consultation with Mr. Mallegni, Mr. Bickford
advised h m that he had arranged financing for a large caterpillar tractor forklift, drill
rigs and air compressors, and arrangements for delivery. Arrangements had been made
for living quarters for a consultant and Mr. Bickford advised Mr. Mallegni that any
contract entered into would be required to be presented to the bank.
Free access — add to your briefcase to read the full text and ask questions with AI
STATE OF MAINE SUPERIOR COURT CIVIL ACTION KNOX, ss. DOCKET NO. CV-04-17 RE f l q F """ ?;I? ,:,. - 'q,"g .. --. ... ., , , ., -~~
g 7 .,;< ., ,k >: , > ,7:\ 4d . , , + L FOX ISLAND GRANITE e~~NY,'i%13
Plaintiff @"t' -,::-! ,-' d
,$k$ t4y,-+
v. * mr DECISION A N D ORDER
AMERICAN GRANITE VANUFACTURERS, INC.,
T h s matter is before the court after bench trial on damages.
Plaintiff filed its complaint with the Clerk of the Superior Court on March 15,
2004. On April 8, 2004, a return of service was filed with the court indicating that the
summons and complaint had been served on Mchael J. Norris, Clerk of American
Granite Manufacturers, Inc. on March 23, 2004, at 3:05 p.m. On May 19, 2004, plaintiff
filed an affidavit and request for default and default judgment with the court and
default was entered by the associate clerk on May 25, 2004. Plaintiff requested a
hearing on damages.
A hearing on damages was held by tlxs court on October 21, 2004. Plaintiff was
present in the person of Daniel Bickford, president and shareholder of plaintiff
corporation along with its counsel. Defendant was represented by counsel and its
general manager. At the hearing, counsel for defendant first challenged the intention of
the court to proceed to hearing by first orally moving the court for a continuance
advising it that he had been retained by deferidant no earlier than 7:00 a.m. o'clock the
same morning. Counsel further advised the court that he had received a
communication at 6:00 p.m. the previous evening from the clerk of the defendant corporation and had been retained the following morning. First, counsel advised that
he had witnesses who were not able to testify as one was out of the country and the
others were in Massachusetts. It was represented that the defendant was not notified of
the instant hearing by its corporation clerk until two days previous. Counsel requested
an opportunity to move to set aside t l e default.
Upon inquiry by the court as to the nature of the excusable neglect to be
proposed and the nature of the meritorious defense, defendant's counsel advised that
investigation was being made as to the issue of jurisdiction, issue of service and why the
clerk of the corporation, a Massachusetts attorney, did not properly advise h s client.
As to the meritorious defense, he challenges the nature of the contract with the
individuals rather than the plaintiff corporation and the question of foreseeability of the
damages. Counsel also challenged the allegation by plaintiff that it had complied with
all of the terms of the contract in issue. Finally, defendant seeks to argue the failure of
the plaintiff to mitigate its damages.
After hearing argument of counsel, the court concluded that whatever issues
exist between the defendant and its clerklattorney is a matter between those parties
under Massachusetts's law and not before h s court. The court noted that sufficient
opportunity had been given the defendant to present pleadings including an extra 30
days from default requested by defendant's clerk/attorney and granted by plaintiff's
counsel. Further, with respect to any issues of jurisdiction or matters on the merits
relating to the defendant, the court indicated that it would give the parties sufficient
opportunity to challenge any of the conclusions reached by appropriate motion. The
matter went to hearing.
Because of the default, ". . . the allegations in the plaintiff's complaint are deemed
to be true and become findings of fact." McAlister v. Slosberg, 658 A.2d 658 (Me. 1995). Citing Brouillard v. Allen, 619 A.2d 988, 998 (Me. 1993); Forbes v. Wells Beach Casino, Inc.,
409 A.2d 646,652 (Me. 1979).
The complaint establishes that the plaintiff is a Maine corporation and the
defendant is a Massachusetts corporation. Plaintiff and defendant entered into a
contract on March 14, 2002, w h c h Bickford agreed to sell and the defendant agreed to
purchase all of plaintiff's production of certain types of granite to be produced by
plaintiff at its quarry. Pursuant to the agreement, the plaintiff shpped to the defendant
certain granite blocks w h c h were accepted by the defendant but who has refused and
failed to pay for the blocks.
Count I1 of the complaint establishes that the plaintiff delivered to the defendant
the granite blocks with reasonable expectation of being paid, defendant has refused to
pay, it would be unjust for defendant to retain said blocks without payment and that
plaintiff is entitled to reasonable value.
Count I11 of the complaint asserts that in anticipation of the defendant honoring
the contract, plaintiff purchased substantial amounts of equipment and incurred other
start-up expenses but, because of defendant's breach, plaintiff was forced to cease
operation and to sell its equipment all at substantial losses. In addition to the forced
sale of the equipment at a discount, plaintiff lost money invested in the enterprise and
substantial profits that would have arisen from the enterprise.
Daniel F. Bickford and Lucy M. Bickford are lifelong residents of Vinalhaven.
They have owned a granite quarry in that community since 1985. In November of 2001,
Mr. Bickford became aware that American Granite Manufacturers, Inc. (AGM) of
Marlborough, Massachusetts, had expressed an interest in acquiring some Maine
granite. Mr. Bickford sent to a Mr. Marcello Mallegni some samples of Vinalhaven
granite. Upon Mr. Mallegni's positive response, Mr. Bickford visited with hm in Marlborough, Massachusetts. Subsequently, Mr. Mallegni visited Mr. Bickford at the
quarry. That same month, Mr.. Bickford wrote to Mr. Mallegni acknowledgng the
previous visit and relayed some information as to operational expenses to open and
operate the quarry. After Mr. Mallegni communicated to Mr. Bickford that he had an
interest in purchasing all of the quzry's production, Mr. Bickjord, through the use of
h s corporation, developed a business plan. Through the use of h s business plan and
communications with Mr. Mallegni, plai~tiffacquired a $200,000 line of credit with the
Damariscotta Bank & Trust. T h s line of credit was secured by a certificate of deposit in
the possession of the bank belonging to an investor supporting plaintiff's efforts.
A second letter was sent in January 2002 to Mi. Mallegni at h s address at
Leamar Industries at the same address as American Granite Manufacturers, Inc. with
more details as to the work being done to prepare for the production of the quarry. In
the letter, Mi. Bickford Qscussed h s line of credit, the price of the product and
equipment being prepared for purchase or lease to operate the quarry.
Again, in February, continuing the consultation with Mr. Mallegni, Mr. Bickford
advised h m that he had arranged financing for a large caterpillar tractor forklift, drill
rigs and air compressors, and arrangements for delivery. Arrangements had been made
for living quarters for a consultant and Mr. Bickford advised Mr. Mallegni that any
contract entered into would be required to be presented to the bank.
On March 14,2002, Daniel and Lucy Bickford entered into a "Granite Purchasing
Agreement" prepared by Mr. Mallegni between American Granite Manufacturers, Inc.
of Marlborough, Massachusetts, and Daniel F. and Lucy M. Bickford both of
Vinalhaven. T h s agreement was signed by the president of American Granite
Manufacturers, Inc., later found not to be Mi. Mallegni in spite of Mi. Bickford's
understanding of Mr. Mallegni's authority. The agreement provided that AGM was to purchase "all of the 'gangsaw size1first choice granite block production," and was to be
shipped FOB Rockland, Maine, AGM agreed to make payments of each shipment
within 30 days, it was for a term of five years with an option in AGM to renew for
another five years, AGM agreed to "use its best efforts" to provide to the Bickfords a
qualified quarry assistant with plaintiff providing, amoEg other h n g s , housing for the
consultant, AGM reserved the right of refusal to purchase any or all second choice
material and the right to assign the agreement to another en?ity. In addi?ion, paragraph
5 reads:
Neither party of tlus agreement is required to perform if it is determined that the granite reserve will not produce at a level or quality of material to satisfy both parties.
Mr. and Mrs. Bickford had previously created a corporation called Fox Island
Granite Company, Inc. upon the expectation that they might, at some time, start
production of the quarry. They transferred the purchase agreement to the corporation
for performance. Plaintiff moved the heavy equipment onto the property, it contracted
with a blasting contractor and they removed the top layer of granite. Mr. Mallegni and
associates came to the Island to review the situation. He indicated to Mr. Bickford that
he liked the stone and would like to get delivery from the stone that had been
produced. Mallegni specifically requested that the stone he viewed on the site be
delivered to the Marlborough location. Tlus slupment took place in August of 2002. An
invoice of Fox Island Granite Co., Inc., dated October 30, 2002, indicates that blocks of
granite were delivered August 17, 22, 24 and 29 for a total of seven blocks or 689 cubic
feet. At the agreed price of $8.00 a cubic foot, defendant was invoiced $5,512. Tlus has
not been paid.
Having expended a substantial sum of money in opening the quarry and
preparing for production and without any funds received from the defendant, plaintiff complained to Mr. Mallegni that he was maintaining inventory for whch he was
receiving no compensation and that if defendant expected to receive the full
production, he needed some financial arrangements. As a result, Mr. Mallegni created
an agreement representing that the defendant would advance to the plaintiff $20,000 on
the 2Yd day of August, 2002, to secure plaintiff's agreement to s h p $20,000 worth of
granite blocks and material w i h n the following 60 days. The security of the
transaction was represented by a promissory note executed by Daniel F. Bickford as
president and treasurer of Fox Island Granite Company, Inc. as well as indvidually.
Having received no funds under either agreement or the note, Daniel Bickford
wrote AGM, attention Marcello Mallegni, on September 6, 2002. At that time, he
complained that he had received no money, phone calls had not been returned, and he
inquired as to the status of Mr. Mallegnils position with respect to the acceptability of
the product. Mr. Bickford made clear that he had already invested nearly $200,000 into
quarry development and he needed cash to produce product. He asked for a
representative of the defendant to come to Vinalhaven to assist in continued
production. Mr. Bickford received no response from that communication.
The result of these activities is that plaintiff has expended substantial sums of
money to open a granite quarry, test the material and s h p product to the defendant in
accordance with a written agreement properly signed and executed by the president of
the defendant corporation and for whch he has received, in spite of promises, not a red
cent.
Defendant argues that the product actually delivered did not meet the terms of
the contract as to size and quality. The unrebutted evidence is that Mr. Mallegni, at
least representing some authority with regard to AGM, and having been aware of the
purchasing agreement signed, asked the material to be delivered knowing that it was less than quality material and smaller than the requested size. Defendant received and
accepted the material and expressed no objection to its quality or size until suggested
by defendant's representative at the hearing on damages. As pointed out by the
plaintiff, 11 M.R.S.A. 5 2-602, the Maine Uniform Commercial Code, provides that,
"Rejection of gcods =ust be witbin 2 reasonzb!e time zfter their delivery cr tender. It is
ineffective unless the buyer seasonably notifies the seller." Furthermore, when goods
are deemed accepted, "The buyer must pay at contract rate for any goods accepted."
11 M.R.S.A. § 2-607. In addition, the general manager of the defendant testified that the
goods that had been delivered and whch he inspected back in 2002, had either been cut
to slabs for sale or put in the junk pile. In either event, they were still in the possession
of or had been sold by the defendant.
The defense raised the issue of the liability of h s particular defendant, the role
of plaintiff's corporation in the transaction under a contract signed by individual
shareholders and the relationship between Mr. Mallegnils corporation and defendant.
Mr. Bickford testified that he understood Mr. Mallegni to be the president of the
defendant corporation. The general manager testified that was not true but he agreed
that the contract in question had, in fact, been signed by the president of the defendant
corporation. He further testified that Mr. Mallegni is the president, treasurer and owner
of Leamar Industries, and a shareholder and director in the defendant. Finally, the
general manager testified that in 2002 both AGM and Leamar Industries were located at
896 Boston Post Road in Marlborough, a condition whch existed at the time Mr.
Bickford visited the site. It is further clear that numerous communications were sent by
plaintiff to defendant on stationery of the plaintiff corporation, clearly putting
defendant on notice that Fox Island Granite Company, Inc. was the main party-in-
interest and that the issue had not been raised until th_ls hearing on damages. Plaintiff believes it had a five-year production contract. Plaintiff further
presented undisputed evidence that core samples had been taken of the quarry of the
quality of the product at the lower levels and that Mr. Mallegni was fully satisfied with
the quality and quantity he was to receive. T h s testimony by plaintiff addresses the
assertion by the defense that the plaintiff cannot daim lost profits becal~seof par2graph
5 to the agreement that if the granite does not "produce at a level of quality of material
to satisfy both parties," they may be excused from performance. This court concludes
that defendant, through its agent Mr. Mallegni, was fully satisfied as to the quantity and
quality expected to be delivered. Because of defendant's complete failure to perform, to
the slightest degree, under an agreement whch it voluntarily entered into, it can hardly
argue that any level of due hligence would not suggest that it expected to receive
granite of a quality and quantity consistent with the pre-blasting investigation. T h s
agreement was prepared by Mr. Mallegni and reviewed by plaintiff's counsel.
Defendant had a full opportunity to respond to the procedural deadlines, first to raise
issues as to liability and secondly, after seven months, to acknowledge proceedings as
to damages and to make arrangements for presentation of substantive evidence with
regard to the terms and expectations under the agreement. As noted by the court at the
time of the hearing, defendant received 30 days notice of the date, time and location of
the hearing.
There is unrebutted sworn testimony that the plaintiff was required to reimburse
Damariscotta Bank & Trust on its business line of credit the amount of $200,000. It is
further unrebutted that the plaintiff incurred the following expenses to prepare the
quarry for production solely in anticipation of performance of the agreement in
question: Maine Drilling and Blasting (blasting work at the quarry) - $38,000
Southworth Milton (lease on excavator) - $27,500
Ingersol Rand (lease on drill rig) - $26,500
Loss of down payment on the front-end loader (repossessed) - $15,000
Miscellaneous administrative and operational expense - $5,000
Plaintiff has expended the amount of $312,000 in anticipation of performance of the
contract.
Plaintiff delivered material to defendant upon defendant's instructions in
accordance with their agreement and accepted the product notwithstanding its top-
level quality deficiencies and substandard size under the contract.
The law is clear that subject to limitations of the ability to perform and
unforseeabiilty, an injured party is entitled to recover for all loss actually suffered as a
result of the breach of a contract. It is the sole province of the factfinder to determine
the amount. Claims for lost profits may not be speculative and are allowable only if
they can be estimated with a reasonable certainty. Marquis v. Farm Family Mutual Ins.
Co., 728 A.2d 644 (Me. 1993).
In plaintiff's business plan, it indicated that it expected to produce roughly
40,000 cubic feet per year at $8.00 a cubic foot. Mr. Bickford testified that h s
information came from the core samples taken from the property. These core samples
were brought from a level of 50 feet and provided information as to the volume of
granite and its quality. Mr. Bickford testified that the $8.00 per cubic foot was a
negotiated price agreed upon between hmself and Mr. Mallegni. Mr. Bickford testified
that he discussed the 40,000 cubic feet per year with Mr. Mallegni and that when he
visited the Marlborough site, he found a full line fabrication facility with a large
inventory of granite blocks from around the world. It was a big plant and Bickford was satisfied that defendant would have full capacity to buy and utilize what could be
produced. Further, with respect to the business plan, Mr. Bickford's investigation
revealed that all costs of production and overhead would amount to $5.00 per cubic foot
and his business plan reflected that projection. As a consequence, Mr. Bickford believed
that due to h s investigatior-i, a five-year contract for production would result in a m u d
sales of $320,000 with annual costs of $200,000 for a projected gross profit of $120,000.
Since t h s was a five-year cor,tract, he believed that he cozld expect $600,000 in profits
from the operation. The court is satisfied that these numbers are not speculative and
are estimated with reasonable certainty.
The defendant has brought no motions to challenge the jurisdiction of the court
to provide relief from default. The defendant did bring a motion to amend the
pleadings to allow it to argue the evidence presented at the hearing of the failure of the
plaintiff to mitigate its damages. The evidence is that by the end of the year of 2002, it
should have been obvious to the plaintiff that defendant was not going to perform and
plaintiff made no effort to obtain another entity to w h c h it could sell its production in
order to mitigate these damages. Mr. Bickford's response was that selling a unique
product like Vinalhaven granite requires marketing for w h c h he has no resources.
It is certainly appropriate and proper to move to amend the pleadings to make
them conform to the evidence. T h s can be done when it is clear that the parties have
actually tried the issue to be added. However, the court cannot grant h s motion for
two reasons. First, there is no pleadng by the defendant to amend. No documentation
was entered in the docket of h s case by the defendant until counsel entered lus
appearance at the hearing on damages orally and in open court. Secondly, the duty to
mitigate is an affirmative defense and under Maine notice pleadings, it must be pled at
an appropriate time to put the plaintiff on notice that it is to be an issue. Otherwise, the court may refuse to accept any evidence on that issue. Further, M.R. Civ. P. 12(b)makes
it clear that every defense must be asserted in a responsive pleading.
For all the foregoing reasons, on the evidence, plaintiff is entitled to $5,512 for
goods sold and accepted by the defendant as stated on plaintiff's invoice of October 30,
2002. Plaintiff is further entitled to recovery of the monies expended in reliance upon
its contract with defendant in the amount of $312,000 as its total cash expenditures.
Finally, plaintiff has provided a reasonable basis for the court to find that in terms of its
contract and its investigation of its ability to perform, there are reasonable grounds to
expect that because of defendads breach, plaintiff has lost profits in the amount of
$600,000 represented by $120,000 for five years.
The entry will be:
Judgment for plaintiff in the amount of $917,512 plus costs; prejudgment interest for 2004 to be at 4.28%; prejudgment interest for 2005 to be at 5.77%; post-judgment interest to run at 8.77%.
Dated: April ,2005 Donald H. Marden Justice, Superior Court 04/29/2005 M A I N E J U D I C I A L INFORMATION SYSTEM ebridges KNOX COUNTY SUPERIOR COURT nlj x x i 0 1 3 PAGE A - ATTORNEY BY CASE V I E W FOX I S L A N D GRANITE CO :[NC VS AMERICAN GRANITE MANUFACTURERS I N C LITN:AOCSsr -2004-0028061 CASE # : R O C S C - C V - 2 0 0 4 - 0 0 0 1 7 ................................................................................ SEL VD REPRESENTATION TYPE DATE 01 0 0 0 0 0 0 3 7 0 6 ATTORNEY:CHOWDRY, FRANK K N ADDR:10 FREE STREET PO BOX 4 5 1 0 PORTLAND ME 0 4 1 1 2 F F0R:AMERICAN GRANITE MANUFACTURERS I N C DEF RTND 18/21/2084
0 2 0 0 0 0 0 0 0 3 0 2 ATTORNEY:LIPMAN, D A V I D A D D R : 2 2 7 WATER STREET PO BOX 1 0 5 1 AUGUSTA ME 0 4 3 3 2 - 1 0 5 1 F FOR: FOX I S L A N D GRANITE CO :[NC PL RTND 03/15/2004
E n t e r O p t i o n : A=Add, B+Sel=Browse, M=More, R+Sel=RltnEdit:
S e l e c t t h e E X I T KEY f o r p a g e s e l e c t i o n l i n e .