Fowler v. Johnston City & Big Muddy Coal & Mining Co.

127 N.E. 31, 292 Ill. 440
CourtIllinois Supreme Court
DecidedApril 21, 1920
DocketNo. 13118
StatusPublished
Cited by15 cases

This text of 127 N.E. 31 (Fowler v. Johnston City & Big Muddy Coal & Mining Co.) is published on Counsel Stack Legal Research, covering Illinois Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fowler v. Johnston City & Big Muddy Coal & Mining Co., 127 N.E. 31, 292 Ill. 440 (Ill. 1920).

Opinion

Mr.- Justice Stone

delivered the opinion of the court:

The plaintiff in error owns and operates two adjacent and contiguous mines in Williamson county, Illinois. The first mine was sunk and in operation several years prior to the revision in 1911 of the statute on mines and miners, of which enactment section 9 is presented to this court for construction. The first mine, or mine No. 1, complies in every respect with the provision of said section of the statute relative to hoisting and escapement shafts. Subsequent to the enactment of said statute the plaintiff in error sunk mine No. 2, which is adjacent to and contiguous to mine No. 1. Instead of opening an escapement shaft in mine No. 2 plaintiff in error constructed an underground passageway connecting with its mine No. 1 at a point 1000 feet from the hoisting shaft of mine No. 2. It is conceded by the plaintiff in error that this underground communicating passageway, as well as the hoisting shaft in mine No. 2, is more than 2000 feet from either the escapement shaft or the hoisting shaft in mine No. 1, and it admits that both mine No. 1 and mine No. 2 are operated and worked by shafts at a depth of 235 feet from the surface of the ground, and that mine No. 1 has approximately 400 employees and that . approximately 190 men are employed underground in mine No. 2. It is conceded that the underground communicating passageway is constructed in the manner required by the statute, and the same is true of the escapement shaft in mine No. 1. The director of the department of mines and minerals of the State of Illinois and the State mine inspector notified the plaintiff in error, before the commencement of this suit, to sink an escapement shaft in its mine No. 2 not less than 500 feet nor more than 2000 feet from the main hoisting shaft, and upon failure to comply with said notice the. defendant in error, as State’s attorney in and for said county, brought this suit at the direction of the department of mines and minerals to enjoin the plaintiff in error from continuing to operate mine No. 2 until it had constructed and was maintaining an escapement shaft in conformity with the requirements of the statute. The cause was submitted to the chancellor on bill and answer. ' The chancellor, after hearing arguments, entered a decree enjoining plaintiff in error from the further operation of mine No. 2 until an escapement shaft had been constructed within the distance prescribed by statute from the hoisting shaft of mine No. 2.

The only issue presented in this court by the assignments of error is whether dr not the underground communicating passageway in question to mine No. 1 as a means of egress from mine No. 2, — the escapement shaft in mine No. 1 being a distance in excess of 2000 feet from the hoisting shaft in mine No. 2, — is a compliance with section 9. That section, so far as it refers to this issue, is as follows:

“(a) For every coal mine in this State, whether worked by shaft, slope or drift, there shall be provided and maintained, in addition to the hoisting shaft, or other place of delivery, an escapement shaft or opening to the surface, or an underground communicating passageway with a contiguous mine, so that there shall be at least two distinct and available means of egress to all persons employed in such coal mines.

“(b) In mines sunk after the passage of this act, the first escapement shaft shall be separated from the main shaft by such extent of natural strata as may be agreed upon by the inspector of the district and the owner of the property, but the distance between the main shaft and the escapement shaft shall not be less than 500 feet nor more than 2000 feet: Provided, that in mines employing ten (10) men or less the distance between the hoisting shaft and the escapement shaft shall not be less than two hundred and fifty (250) feet.

“(c) It shall be unlawful to employ underground, at any one time, more men than in the judgment of the inspector are necessary to complete speedily the connections with the escapement shaft or adjacent mine; and said number must not exceed ten men at any one time for any purpose in said mine until such escapement or connection is completed. * * *

“(e) Such escapement shaft or opening or communication with a contiguous mine as aforesaid, shall be constructed in connection with every seam of coal worked in such mine, and all passageways communicating with the escapement shaft or place of exit, from the main hauling ways to said place of exit, shall be maintained free of obstruction at least five feet high and five feet wide. Such passageways must be so graded and drained that it will be impossible for water to accumulate in any depression or dip of the same in quantities sufficient to obstruct the free and safe passage of men. No passageway to an escapement shall pass through a stable. At all points where the passageway to the escapement shaft or other place of exit is intersected by other roadways or entries, conspicuous signboards shall be placed, indicating the direction it is necessary to take .in order to reach such place of exit.

“(f) When operators of adjacent mines have, by agreement, established underground communications between said mines as an escapement outlet for the men employed in both, the intervening doors shall remain unlocked and ready at all times for immediate use. When such communication has once been established between contiguous mines, the operator of- either shall not close the same without the consent of the operator of the contiguous mine and of the State inspector for the district: Provided, that when either operator desires to abandon mining operations the expense and duty of maintaining such communication shall devolve upon the party continuing operations and using the same.”

It is contended by plaintiff in error that the requirement of the statute with reference to distance of an escapement shaft from the main hoisting shaft of a mine is applicable also to an underground communicating passageway with a contiguous mine. It is contended by the defendant in error that the provision of the statute with reference to distance does not permit an escapement shaft to be further than 2000 feet from the hoisting shaft of a mine, even though an underground communicating passageway is constructed ; that the underground communicating passageway can only be utilized to reach an escapement shaft within the distance of 2000 feet prescribed by the statute. The question therefore is whether by this act the legislature intended that an escapement shaft should be within 2000 feet of every hoisting shaft, whether the escapement shaft be in the same mine or in a contiguous mine connected by a communicating passageway, or whether the purpose of the statute is met by connecting one mine with a contiguous mine at a point not more than 2000 feet from the hoisting shaft, even though the escapement shaft in the contiguous mine may be more than 2000 feet from the hoisting shaft. In other words, does this contiguous mine, here known as mine No. x, when it is connected by. an underground passageway at a point not more than 2000 feet from the hoisting shaft in mine No. 2, afford the second means of egress from mine No. 2, as contemplated by the act in relation to mines and miners as revised in 1911 ?

The construction of section 9 of the act has not been previously before this court and no cases construing similar statutes have been pointed out in the briefs of counsel.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Indian Valley Golf Club, Inc. v. Village of Long Grove
481 N.E.2d 277 (Appellate Court of Illinois, 1985)
Village of Glencoe v. Metropolitan Sanitary District
320 N.E.2d 524 (Appellate Court of Illinois, 1974)
PEO. EX REL. OAK SUP & FURNITURE v. Dept. of Rev.
320 N.E.2d 236 (Appellate Court of Illinois, 1974)
People ex rel. Oak Supply & Furniture Co. v. Department of Revenue
320 N.E.2d 236 (Appellate Court of Illinois, 1974)
Freeman Coal Mining Corp. v. Ruff
228 N.E.2d 279 (Appellate Court of Illinois, 1967)
People Ex Rel. Skonberg v. Paxton
211 N.E.2d 591 (Appellate Court of Illinois, 1965)
Hagen v. City of Rock Island
163 N.E.2d 495 (Illinois Supreme Court, 1959)
People Ex Rel. Powell v. Board of Education
99 N.E.2d 592 (Appellate Court of Illinois, 1951)
Cadwell v. National Tea Co.
98 N.E.2d 516 (Appellate Court of Illinois, 1951)
Stiska v. City of Chicago
90 N.E.2d 742 (Illinois Supreme Court, 1950)
Illinois Central Railroad v. Village of South Pekin
29 N.E.2d 590 (Illinois Supreme Court, 1940)
Walter v. Northern Insurance of New York
18 N.E.2d 906 (Illinois Supreme Court, 1938)
Landry v. E. G. Shinner & Co.
176 N.E. 895 (Illinois Supreme Court, 1931)
Glos v. Glos
173 N.E. 604 (Illinois Supreme Court, 1930)
New Erie Coal Co. v. H. McMullen & Sons
247 Ill. App. 515 (Appellate Court of Illinois, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
127 N.E. 31, 292 Ill. 440, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fowler-v-johnston-city-big-muddy-coal-mining-co-ill-1920.