Fourchy v. United States

88 Ct. Cl. 564, 1939 U.S. Ct. Cl. LEXIS 230, 1939 WL 4238
CourtUnited States Court of Claims
DecidedApril 3, 1939
DocketNo. 43386
StatusPublished
Cited by1 cases

This text of 88 Ct. Cl. 564 (Fourchy v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fourchy v. United States, 88 Ct. Cl. 564, 1939 U.S. Ct. Cl. LEXIS 230, 1939 WL 4238 (cc 1939).

Opinion

GseeN, Judge,

delivered the opinion of the court:

This suit is brought to recover $33,394.80 as a balance due for architectural services.

It appears that under the Act of Congress of January 7, 1925 (43 Stat. 724), the construction was authorized for the necessary buildings of the United States Industrial Reformatory to be located at Chillicothe, Ohio. The original act provided that prisoners confined in the several United States penitentiaries, prisons, or reformatories should be employed in the construction of the buildings thereof. The Act of May 29, 1928 (45 Stat. 883, 906), made a preliminary appropriation for the purpose of carrying out the project and authorized the Secretary of the Treasury, if in his discretion it would be impracticable to have the plans therefor prepared [574]*574in the office of the Supervising Architect of the Treasury-Department, to “contract for all or any portion of such work to be performed by such suitable person or firm as he may select.” In accordance with this provision, the Secretary selected the plaintiff as a suitable person to prepare the plans, drawings, designs, specifications, and estimates necessary and entered into a contract with him for that purpose on October 18,1928. The contract is set out in full in Exhibit A attached to the petition and the portions thereof which bear specially upon the matters involved in this suit are set out verbatim in the findings. A reading of these provisions shows that the work to be performed and the manner in which payment was to be made were specified in detail.

Plaintiff promptly entered into the performance of the contract and performed the work contemplated therein including changes and additions ordered by the defendant. He was engaged during a period of approximately five years in the performance of his services on the project, and was at the expense of maintaining an office with clerical force employing almost constantly a number of technical experts, sometimes as many as fourteen working exclusively on this job. Plaintiff and the officials of the Bureau of Prisons made a detailed study of the requirements of the project which resulted in the preparation and submission of preliminary plans as required under division A of the contract. On March 12, 1929, the plans so prepared and submitted were approved by the Secretary of the Treasury and the Attorney General. In accordance with the contract, plaintiff was subsequently paid architectural fees on the estimated cost of $2,807,000 as set forth therein. The' controversy in the case arises under claims made by the plaintiff for work under what are commonly called change orders, with one exception which will be hereinafter noted.

There are four items upon which plaintiff seeks a recovery:

(1) $1,724.80 as a balance due by reason of the elimination by the defendant of ground lighting and garage and fire engine building;

(2) $7,500 as a balance due for redesigning and making new working drawings for mess hall and kitchen, and for [575]*575revision of design of school and auditorium (assembly hall and chapel);

(3) $20,650 for a design of the buildings described in paragraph (2) above; or, in the alternative, $10,420.44 as an arbitrated amount due under the decision of the Supervising Architect of the Treasury pursuant to the provisions of the contract;

(4) $3,520 for working drawings for a low pressure steam distribution system and a centralized hot water system.

The evidence shows that as the work progressed a controversy arose between the plaintiff and the Director of Prisons, the latter claiming that the cost of construction of the project in accordance with the plans, drawings, and details submitted by the plaintiff would exceed the limit of the appropriations made therefor. The plaintiff claims that this objection was unfounded. The controversy between the two became acrimonious and apparently considerable feeling was engendered between them. Each seems to have been partly right and partly wrong, but we have made no finding thereon because under our view of the law of the case what took place between the two is immaterial for several reasons. The important question is as to what matters were in disagreement or dispute between the plaintiff and defendant and how they were settled.

We think that all of the claims of plaintiff arising out of change orders were settled by the decision of the Supervising Architect in accordance with the provisions of the contract and that this will appear from a consideration of the evidence as shown by the findings.

It appears that the plaintiff was required to submit a proposal for redesigning the mess hall and kitchen together with assembly hall and chapel, and school building. Plaintiff prepared plans for redesigning these buildings, which plans have been referred to in a discussion of the evidence as the second set, but the drawings were never approved, it apparently having been considered that they could not have been carried out without exceeding the appropriation although the Treasury Department after-wards admitted that they could have been. The plaintiff was instructed to prepare a new set of drawings and [576]*576did so, this last or third set representing a new design without any overlapping or utilization of the previous ones as shown by the Treasury letter to which reference will hereinafter be made. A controversy and dispute arose as to what should be paid the plaintiff for the second and third sets of the drawings. Plaintiff made a certain proposal with reference to the settlement of these matters and there was correspondence in regard thereto but no definite agreement was reached or concluded. Plaintiff claimed to be entitled to receive $2,500 for the second set of plans under a proposition of settlement accepted by the Treasury Department and to be entitled to payment for the third set in accordance with the contract. The $2,500 was paid and a controversy again arose as to whether it was in payment for the second plans or in settlement of all that was due plaintiff under the change orders as claimed by defendant. Finally plaintiff asked to have the matters in dispute submitted to the Supervising Architect to determine how much was due him, in accordance with the provisions of the contract when disputes arose over work done under change orders. The results of this submission are summarized in a letter written in behalf of the Treasury Department to the Comptroller General by the Director of the Procurement Division thereof dated July 26, 1934, which reviewed the matter in dispute and stated the facts in relation thereto. This letter, the material parts of which are set out verbatim in the findings, is we think the best kind of evidence of the facts recited therein. It shows definitely that the Treasury understood that the $2,500 was paid for drawing what is called the second set of plans and that a new set of drawings was ordered and prepared representing a “distinctly new design showing no overlapping or utilization of the previous ones”. It also shows that plaintiff’s claim for further compensation was submitted to the Supervising Architect pursuant to the terms of the contract and that he found plaintiff to be entitled to additional compensation therefor in the sum of $10,420.44. The payment of this amount was accordingly recommended. The letter, when considered together with all the other evidence bearing on this matter, amply sup[577]*577ports plaintiff’s alternative claim for compensation for the third, set of plans in the sum found by the Supervising Architect.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Proffit v. United States
42 Ct. Cl. 248 (Court of Claims, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
88 Ct. Cl. 564, 1939 U.S. Ct. Cl. LEXIS 230, 1939 WL 4238, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fourchy-v-united-states-cc-1939.