Fourchy v. United States

88 Ct. Cl. 564, 1939 U.S. Ct. Cl. LEXIS 230, 1939 WL 4238
United States Court of Claims·Decided April 3, 1939·No. No. 43386·Published·Cited by 1 cases

Opinion

GseeN, Judge,

delivered the opinion of the court:

This suit is brought to recover $33,394.80 as a balance due for architectural services.

It appears that under the Act of Congress of January 7, 1925 (43 Stat. 724), the construction was authorized for the necessary buildings of the United States Industrial Reformatory to be located at Chillicothe, Ohio. The original act provided that prisoners confined in the several United States penitentiaries, prisons, or reformatories should be employed in the construction of the buildings thereof. The Act of May 29, 1928 (45 Stat. 883, 906), made a preliminary appropriation for the purpose of carrying out the project and authorized the Secretary of the Treasury, if in his discretion it would be impracticable to have the plans therefor prepared [574] in the office of the Supervising Architect of the Treasury-Department, to “contract for all or any portion of such work to be performed by such suitable person or firm as he may select.” In accordance with this provision, the Secretary selected the plaintiff as a suitable person to prepare the plans, drawings, designs, specifications, and estimates necessary and entered into a contract with him for that purpose on October 18,1928. The contract is set out in full in Exhibit A attached to the petition and the portions thereof which bear specially upon the matters involved in this suit are set out verbatim in the findings. A reading of these provisions shows that the work to be performed and the manner in which payment was to be made were specified in detail.

Plaintiff promptly entered into the performance of the contract and performed the work contemplated therein including changes and additions ordered by the defendant. He was engaged during a period of approximately five years in the performance of his services on the project, and was at the expense of maintaining an office with clerical force employing almost constantly a number of technical experts, sometimes as many as fourteen working exclusively on this job. Plaintiff and the officials of the Bureau of Prisons made a detailed study of the requirements of the project which resulted in the preparation and submission of preliminary plans as required under division A of the contract. On March 12, 1929, the plans so prepared and submitted were approved by the Secretary of the Treasury and the Attorney General. In accordance with the contract, plaintiff was subsequently paid architectural fees on the estimated cost of $2,807,000 as set forth therein. The' controversy in the case arises under claims made by the plaintiff for work under what are commonly called change orders, with one exception which will be hereinafter noted.

There are four items upon which plaintiff seeks a recovery:

(1) $1,724.80 as a balance due by reason of the elimination by the defendant of ground lighting and garage and fire engine building;

(2) $7,500 as a balance due for redesigning and making new working drawings for mess hall and kitchen, and for [575] revision of design of school and auditorium (assembly hall and chapel);

(3) $20,650 for a design of the buildings described in paragraph (2) above; or, in the alternative, $10,420.44 as an arbitrated amount due under the decision of the Supervising Architect of the Treasury pursuant to the provisions of the contract;

(4) $3,520 for working drawings for a low pressure steam distribution system and a centralized hot water system.

The evidence shows that as the work progressed a controversy arose between the plaintiff and the Director of Prisons, the latter claiming that the cost of construction of the project in accordance with the plans, drawings, and details submitted by the plaintiff would exceed the limit of the appropriations made therefor. The plaintiff claims that this objection was unfounded. The controversy between the two became acrimonious and apparently considerable feeling was engendered between them. Each seems to have been partly right and partly wrong, but we have made no finding thereon because under our view of the law of the case what took place between the two is immaterial for several reasons. The important question is as to what matters were in disagreement or dispute between the plaintiff and defendant and how they were settled.

We think that all of the claims of plaintiff arising out of change orders were settled by the decision of the Supervising Architect in accordance with the provisions of the contract and that this will appear from a consideration of the evidence as shown by the findings.

Free access — add to your briefcase to read the full text and ask questions with AI

Fourchy v. United States, 88 Ct. Cl. 564, 1939 U.S. Ct. Cl. LEXIS 230, 1939 WL 4238 (cc 1939).

88 Ct. Cl. 564 (Fourchy v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Proffit v. United States
42 Ct. Cl. 248 (Court of Claims, 1907)