Four Points Business v. Fred Rojas D/B/A Mega Contractors

CourtCourt of Appeals of Texas
DecidedAugust 27, 2013
Docket01-12-00413-CV
StatusPublished

This text of Four Points Business v. Fred Rojas D/B/A Mega Contractors (Four Points Business v. Fred Rojas D/B/A Mega Contractors) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Four Points Business v. Fred Rojas D/B/A Mega Contractors, (Tex. Ct. App. 2013).

Opinion

Opinion issued August 27, 2013

In The

Court of Appeals For The

First District of Texas ———————————— NO. 01-12-00413-CV ——————————— FOUR POINTS BUSINESS, INC., Appellant V. FRED ROJAS, D/B/A MEGA CONTRACTORS, Appellee

On Appeal from the County Civil Court at Law No. 1 Harris County, Texas Trial Court Case No. 981423

MEMORANDUM OPINION

This appeal involves a construction project to renovate a formerly

abandoned convenience store. Appellant Four Points Business, Inc. hired appellee

Fred Rojas as a general contractor to complete the renovations, but the project took longer than Four Points anticipated. Four Points sued Rojas, who counterclaimed

to recover under quantum meruit. After a bench trial, the trial court entered a

judgment in favor of Rojas. Four Points appeals, contending that the judgment

lacks a sufficient evidentiary basis. Because the trial court was free to credit

Rojas’s testimony and disbelieve the testimony and evidence Four Points

presented, we affirm.

Background

Four Points, which owns convenience stores, contracted with Fred Rojas, a

general contractor, to fully remodel a previously abandoned convenience store

located at 6643 Cullen Boulevard in Houston. The parties agreed that Rojas was

responsible for obtaining blueprints and permits, rebuilding the interior of the

store, installing new electrical fixtures and two 3.5-ton air conditioning units, and

wrapping the building with new stucco. The agreement excluded repairs for major

damage to the walk-in cooler and the structure of the building. The total estimated

price for the project was listed as $70,000. Although no completion date for the

project was listed in the agreement, a payment schedule was included that listed six

payment dates: December 25, 2009; January 8, 2010; January 22, 2010; February

5, 2010; February 19, 2010; and the “balance at receiving of certificate of

occupancy.” The agreement was signed on December 26, 2009.

2 Rojas began work on the project and Four Points made the first two

scheduled payments on time. A dispute then arose regarding obtaining permits

from the City of Houston. The president of Four Points, Wahid Lala, testified that

he refused to make further payments until Rojas obtained permits from the City.

He testified that Rojas had assured him that the necessary permits would be

obtained within two weeks of starting the project and that the entire project would

be completed by the end of March 2010. Rojas, on the other hand, testified that he

had not told Four Points that he could obtain the permits by a date certain and that

he had no control over how long the City would take to issue the permits, although

he had undertaken all the actions necessary to obtain them.

Because of the dispute over obtaining the permits, Four Points refused to

make several of the other scheduled payments on time. Although Rojas agreed to

accept late payments from Four Points due to the delay in obtaining the permits, he

explained that the untimely payments nevertheless delayed work on the project.

The project was further delayed when it was discovered that the store’s power

transformers could not accommodate the renovated wiring. The electric utility

provided two different options to perform the needed upgrade, but Four Points did

not make a decision for several months on how to proceed, which caused further

delay.

3 The parties also disputed whether Rojas completed all of the work in the

contract. Four Points claimed that while Rojas was eventually paid all of the

money, he had completed only half of the work listed in the agreement. Rojas

testified that he had completed all of the work in the agreement, which cost him

$69,050, while Four Points only paid him $66,000. He also performed additional

work to improve the store beyond that set forth in the written agreement, which he

claims was orally approved by Four Points. Rojas upgraded the walls of the walk-

in cooler, installed a large new canopy with lighting, and upgraded the electrical

system. Rojas stated that the value of the additional work was $15,250, but Four

Points never paid him for it.

To complete the project, the parties executed an addendum to the original

contract on November 20, 2010. Rojas was to finish the remaining restoration

work within 30 days, including installing the air conditioners and finishing work

on the walk-in cooler, counter, and ceiling tiles. Four Points was to deposit $7,000

in escrow that would be released upon completion of the work. But Four Points

failed to make the deposit, because, according to Lala, the title company would not

allow the money to be placed in escrow without Rojas signing an escrow letter.

Rojas testified that he was never told that he needed to be present for the money to

be deposited. Four Points ultimately hired a different contractor to complete the

project.

4 Four Points sued Rojas for breach of contract, negligence, unjust

enrichment, and promissory estoppel. In his counterclaims, Rojas alleged the same

causes of action against Four Points with the addition of a quantum meruit cause of

action. After a bench trial, the trial court entered judgment in favor of Rojas,

awarding him $15,250 in damages and $10,000 in attorney’s fees. The trial court

filed written findings of fact and conclusions of law in support of its judgment.

Among other things, the trial court found that Rojas substantially completed the

work contemplated in the original agreement and completed work on several items

excluded from the original contract, for which he was never paid. The trial court

assessed the value of this work at $15,250. Additionally, the trial court concluded

that Four Points breached its agreements with Rojas when it failed to make timely

payments under the original contract and failed to deposit money in escrow under

the addendum.

Four Points then timely filed this appeal. In seven issues on appeal, Four

Points challenges: (1) the trial court’s judgment for failing to specify the claims

upon which Rojas prevailed; (2) the finding that Rojas suffered damages when

only testimony, not invoices or proof of payments, was introduced at trial; (3) the

damages award when Rojas allegedly failed to plead quantum meruit; (4) the

finding that Four Points anticipatorily breached when Rojas testified that he agreed

to accept late payments; (5) the trial court’s failure to find that Four Points suffered

5 damages given the evidence offered; (6) the trial court’s failure to enter judgment

in favor of Four Points; and (7) the attorney’s fees award.

Analysis

I. Form of judgment

In its first issue, Four Points contends that the trial court’s judgment should

be reversed for failing to state the claim upon which Rojas prevailed. “A judgment

must be sufficiently definite and certain to define and protect the rights of all

litigants, or it should provide a definite means of ascertaining such rights, to the

end that ministerial officers can carry the judgment into execution without

ascertainment of facts not therein stated.” Stewart v. USA Custom Paint & Body

Shop, Inc., 870 S.W.2d 18, 20 (Tex. 1994) (quoting Steed v. State, 183 S.W.2d

458, 460 (Tex. 1944)). In other words, a valid final judgment must be

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Haggar Clothing Co. v. Hernandez
164 S.W.3d 386 (Texas Supreme Court, 2005)
Progressive County Mutual Insurance Co. v. Kelley
284 S.W.3d 805 (Texas Supreme Court, 2009)
Fort Worth Independent School District v. City of Fort Worth
22 S.W.3d 831 (Texas Supreme Court, 2000)
Lamajak, Inc. v. Frazin
230 S.W.3d 786 (Court of Appeals of Texas, 2007)
Adams v. First National Bank of Bells/Savoy
154 S.W.3d 859 (Court of Appeals of Texas, 2005)
BMC Software Belgium, NV v. Marchand
83 S.W.3d 789 (Texas Supreme Court, 2002)
COC Services, Ltd. v. CompUSA, Inc.
150 S.W.3d 654 (Court of Appeals of Texas, 2004)
Texaco, Inc. v. Anh Thi Phan
137 S.W.3d 763 (Court of Appeals of Texas, 2004)
Chavez v. McNeely
287 S.W.3d 840 (Court of Appeals of Texas, 2009)
Stewart v. USA Custom Paint & Body Shop, Inc.
870 S.W.2d 18 (Texas Supreme Court, 1994)
Merrell Dow Pharmaceuticals, Inc. v. Havner
953 S.W.2d 706 (Texas Supreme Court, 1997)
Truly v. Austin
744 S.W.2d 934 (Texas Supreme Court, 1988)
Pepi Corp. v. Galliford
254 S.W.3d 457 (Court of Appeals of Texas, 2007)
Catalina v. Blasdel
881 S.W.2d 295 (Texas Supreme Court, 1994)
Johnston v. Kruse
261 S.W.3d 895 (Court of Appeals of Texas, 2008)
Ortiz v. Jones
917 S.W.2d 770 (Texas Supreme Court, 1996)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Henry v. Masson
333 S.W.3d 825 (Court of Appeals of Texas, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
Four Points Business v. Fred Rojas D/B/A Mega Contractors, Counsel Stack Legal Research, https://law.counselstack.com/opinion/four-points-business-v-fred-rojas-dba-mega-contrac-texapp-2013.