Fountainhead Development Corp. v. Dailey

588 S.E.2d 768, 263 Ga. App. 677, 2003 Fulton County D. Rep. 2905, 2003 Ga. App. LEXIS 1205
CourtCourt of Appeals of Georgia
DecidedSeptember 23, 2003
DocketA03A1428
StatusPublished
Cited by6 cases

This text of 588 S.E.2d 768 (Fountainhead Development Corp. v. Dailey) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fountainhead Development Corp. v. Dailey, 588 S.E.2d 768, 263 Ga. App. 677, 2003 Fulton County D. Rep. 2905, 2003 Ga. App. LEXIS 1205 (Ga. Ct. App. 2003).

Opinion

Ruffin, Presiding Judge.

Roger and Violet Dailey sued Fountainhead Development Corporation, Inc. (“Fountainhead”), Chateau Elan Realty, Inc. (“Chateau Elan Realty”), Premier Builders, Inc. (“Premier”), and Premier’s president, Michael Massey, for negligent representation, breach of contract, negligent construction, fraudulent conversion, and breach of warranty relating to the construction of their new home. They also sought litigation expenses and punitive damages.

Premier and Massey filed for bankruptcy, imposing an automatic stay on the Daileys’ claims against them. 1 A jury subsequently found Fountainhead and Chateau Elan Realty liable on the Daileys’ claims for breach of contract, fraudulent conversion, and litigation expenses. It found against the Daileys on the remaining claims. Fountainhead and Chateau Elan Realty appeal, arguing that the trial court erred in failing to direct a verdict for them. We agree and reverse.

In reviewing a trial court’s directed verdict ruling, we construe the evidence and all inferences in favor of the verdict. 2 A directed verdict is only proper when “there is no conflict in the evidence as to any material issue and the evidence introduced, with all reasonable deductions therefrom, demands a certain verdict.” 3

Viewed in this manner, the evidence shows that, in 1998, the Daileys began looking for a new residence. In August or September of that year, they visited several properties north of Atlanta, including homes in the Chateau Elan subdivision. They liked several vacant lots within Chateau Elan and decided to build a house there.

Several weeks later, the Daileys met with Andy Williams of Chateau Elan Realty, a real estate office located in Chateau Elan that sold property within the subdivision. Williams informed the Daileys that, once they selected a lot, they would negotiate a construction contract with the assigned builder. Williams explained at trial that Fountainhead, the subdivision developer, had entered into a marketing plan with two builders, Premier and Bell-Harrison Homes. Under that plan, Fountainhead assigned each available lot to one of the two builders, which would then contract directly with prospective homeowners for the house construction.

The Daileys selected a lot that had been assigned to Premier, *678 and they met with the builder to negotiate the construction details. On January 19, 1999, the Daileys executed a new home construction agreement with Premier. According to its terms, the agreement was “made and entered into . . . [b]etween Premier Builders Inc., (Builder) . . . and Roger E. [and] Violet M. Dailey (Homeowner).” The contract established $442,605 as the price of construction and obligated the Daileys to pay Chateau Elan Realty a real estate commission of $23,295. The agreement also contained a merger clause, which stated, in part:

This Agreement constitutes the sole and entire agreement between the parties. No representation, promise or inducement not included in this Agreement is relied upon or shall be binding upon any partly]. [The] term Agreement as used herein, as well as the terms herein, hereof, hereunder and the like mean this Agreement in its entirety.

The Daileys obtained a construction loan in their name and provided Premier with draws to finance the construction. Between January 1999 and January 2000, they paid the builder over $385,000. By the beginning of 2000, however, progress on the house had stopped, and the Daileys learned that Premier had failed to pay several subcontractors. Although the house was not complete, Premier did not return to the job site after March 17, 2000. Shortly thereafter, Mr. Dailey informed Phillip Mulherin, a Fountainhead assistant vice president, about the situation. Mr. Dailey told Mulherin that Fountainhead and Chateau Elan Realty were responsible because they chose the builder. Mulherin denied any responsibility.

The Daileys eventually finished their home in May or June 2000 by hiring subcontractors themselves. After they moved into the house, they discovered that certain work completed by Premier needed to be redone. According to Roger Dailey, the cost to repair and finish the home exceeded the contract price by $141,993.52.

The Daileys sued Fountainhead and Chateau Elan Realty for . damages arising from Premier’s failure to complete their house in accordance with the new construction agreement. Their claims centered around an agency theory. According to the Daileys, Fountainhead and Chateau Elan Realty were liable, as principals, for the conduct of Premier and Massey, their agents.

The verdict form required jurors to determine whether such an agency relationship existed. It further instructed jurors to consider the Daileys’ claims for breach of the construction contract, negligent construction, fraudulent conversion, litigation expenses, and punitive damages “if and only if [they found] for the [Daileys] on the issue of agency.” The jury ultimately concluded that Massey and Premier *679 were agents of Fountainhead and Chateau Elan Realty. It held Fountainhead and Chateau Elan Realty liable for breach of the construction contract and fraudulent conversion, but found for the defendants on the remaining agency-based claims. 4

On appeal, Fountainhead and Chateau Elan Realty argue that the undisputed evidence shows that they are not liable to the Daileys as principals. We agree.

The Daileys do not contend that an actual agency relationship existed in this case. Instead, they claim that an ostensible or apparent agency developed between Fountainhead and Chateau Elan Realty, as principals, and Premier and Massey, as agents. “The relation of principal and agent arises wherever one person, expressly or by implication, authorizes another to act for him or subsequently ratifies the acts of another in his behalf.” 5 Under the theory of apparent or ostensible agency, a claimant may subject an alleged principal to liability by establishing: “(1) that the alleged principal held out another as its agent; (2) that the plaintiff justifiably relied on the care or skill of the alleged agent based upon the alleged principal’s representation; and (3) that this justifiable reliance led to the injury.” 6

The Daileys argue that the evidence presented a question of fact as to an ostensible agency relationship, precluding a directed verdict. For example, they cite to evidence that Fountainhead and Chateau Elan Realty referred to Premier as “our builder” and required them to hire Premier for the construction of their home. The undisputed evidence also shows, however, that the Daileys contracted directly with Premier through the new construction agreement.

Our Supreme Court addressed a similar situation in Kingsberry Homes v. Findley. 7

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Williams v. JET ONE JETS, INC.
755 F. Supp. 2d 1281 (N.D. Georgia, 2010)
Dunn v. Venture Building Group, Inc.
642 S.E.2d 156 (Court of Appeals of Georgia, 2007)
Ellis v. Fuller
638 S.E.2d 433 (Court of Appeals of Georgia, 2006)
MCG Health, Inc. v. Nelson
606 S.E.2d 576 (Court of Appeals of Georgia, 2004)
Bacon v. Volvo Service Center, Inc.
597 S.E.2d 440 (Court of Appeals of Georgia, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
588 S.E.2d 768, 263 Ga. App. 677, 2003 Fulton County D. Rep. 2905, 2003 Ga. App. LEXIS 1205, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fountainhead-development-corp-v-dailey-gactapp-2003.